Question

In: Accounting

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019.

Expenditures on the project were as follows:

January 1, 2018

$

1,070,000

March 1, 2018

840,000

June 30, 2018

380,000

October 1, 2018

710,000

January 31, 2019

1,170,000

April 30, 2019

1,485,000

August 31, 2019

2,700,000


On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest rate. The loan was outstanding all of 2018 and 2019. The company’s other interest-bearing debt included two long-term notes of $6,000,000 and $8,000,000 with interest rates of 8% and 10%, respectively. Both notes were outstanding during all of 2018 and 2019. Interest is paid annually on all debt. The company’s fiscal year-end is December 31. Assume the $3 million loan is not specifically tied to construction of the building.

Required:
1. Calculate the amount of interest that Mason should capitalize in 2018 and 2019 using the weighted-average method.
2. What is the total cost of the building?
3. Calculate the amount of interest expense that will appear in the 2018 and 2019 income statements.

Solutions

Expert Solution

Solution 1:

Weighted average interest rate of all debt
Debt Amount Interest rate Interest amount
Loan $30,00,000 14% $4,20,000
8% Note $60,00,000 8% $4,80,000
10% Note $80,00,000 10% $8,00,000
Totals $1,70,00,000 $17,00,000
Weighted average rate (total interets/ total debt) 10.00%
Year 2021: Weighted-Average accumulated expenditure and interest capitalized
Date Amount Capitalization period Weighted Average Accumulated Expenditures
01 January 2021 $10,70,000 12/12 $10,70,000
01 March 2021 $8,40,000 10/12 $7,00,000
30 June 2021 $3,80,000 6/12 $1,90,000
01 October 2021 $7,10,000 3/12 $1,77,500
Total $30,00,000 $21,37,500
*Interest rate 10.00%
Interest capitalized in 2021 $2,13,750
Year 2022: Weighted-Average accumulated expenditure
Date Amount Capitalization period Weighted Average Accumulated Expenditures
01 January 2022 $32,13,750 9/9 $32,13,750
31 January 2022 $11,70,000 8/9 $10,40,000
30 April 2022 $14,85,000 5/9 $8,25,000
31 August 2022 $27,00,000 1/9 $3,00,000
Total $85,68,750 $53,78,750
*Interest rate 10.00%
Interest capitalized in 2022 $4,03,406
Solution 2:
Computation of Cost of Building
Total expenditure before capitalization(8568750-213750) $83,55,000
Add: Interest capitalized in 2021 $2,13,750
Add: Interest capitalized in 2021 $4,03,406
Total cost of Building $89,72,156
Solution 3:
Computation of Interest expense
Debt Amount Interest rate Interest amount
Loan $30,00,000 14% $4,20,000
8% Note $60,00,000 8% $4,80,000
10% Note $80,00,000 10% $8,00,000
Total interest incurred $17,00,000
2021 2022
Total inerest incurred $17,00,000 $17,00,000
Less: Interest Capitalized $2,13,750 $4,03,406
Interest Expense $14,86,250 $12,96,594

Related Solutions

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,710,000 March 1, 2018 1,320,000 June 30, 2018 1,520,000 October 1, 2018 1,320,000 January 31, 2019 378,000 April 30, 2019 711,000 August 31, 2019 1,008,000 On January 1, 2018, the company obtained a $4,200,000 construction loan with a 16% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,050,000 March 1, 2018 870,000 June 30, 2018 390,000 October 1, 2018 690,000 January 31, 2019 675,000 April 30, 2019 990,000 August 31, 2019 1,710,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 900,000 June 30, 2018 1,100,000 October 1, 2018 900,000 January 31, 2019 315,000 April 30, 2019 648,000 August 31, 2019 945,000 On January 1, 2018, the company obtained a $3,500,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,420,000 March 1, 2018 1,140,000 June 30, 2018 1,340,000 October 1, 2018 1,140,000 January 31, 2019 351,000 April 30, 2019 684,000 August 31, 2019 981,000 On January 1, 2018, the company obtained a $3,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,300,000 March 1, 2018 720,000 June 30, 2018 340,000 October 1, 2018 640,000 January 31, 2019 450,000 April 30, 2019 765,000 August 31, 2019 1,260,000 On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 660,000 June 30, 2018 520,000 October 1, 2018 620,000 January 31, 2019 360,000 April 30, 2019 675,000 August 31, 2019 1,080,000 On January 1, 2018, the company obtained a $3 million construction loan with a 11% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,940,000 March 1, 2018 1,680,000 June 30, 2018 1,880,000 October 1, 2018 1,680,000 January 31, 2019 432,000 April 30, 2019 765,000 August 31, 2019 1,062,000 On January 1, 2018, the company obtained a $4,800,000 construction loan with a 14% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,850,000 March 1, 2018 1,500,000 June 30, 2018 1,700,000 October 1, 2018 1,500,000 January 31, 2019 405,000 April 30, 2019 738,000 August 31, 2019 1,035,000 On January 1, 2018, the company obtained a $4,500,000 construction loan with a 12% interest rate....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT