Question

In: Accounting

On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its...

On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $2,200,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: $9,000,000, 10% bonds $6,000,000, 8% long-term note Construction expenditures incurred during 2021 were as follows: January 1 $ 900,000 March 31 1,500,000 June 30 1,160,000 September 30 900,000 December 31 700,000

Required: Calculate the amount of interest capitalized for 2021 using the specific interest method.

Solutions

Expert Solution

Answer : $436,360

Explanation :

1 . Weighted-average rate of all other debt

Bonds $9,000,000 ($9,000,000 *10%) = $900,000
Long-term note $6,000,000 ($6,000,000 * 8%) = $480,000
$15,000,000 $1,380,000

Weighted-average rate of all other debt =

$1,380,000 / $15,000,000

9.2%

2. Weighted-average Accumulated expenditure

Date (A) Expenditure (B) Weight (C) Average (B*C)
January 1 $900,000 12/ 12 $900,000
March 31 $1,500,000 9/ 12 $1,125,000
June 30 $1,160,000 6/12 $580,000
September 30 $900,000 3/12 $225,000
December 31 $700,000 0/12 $0
Weighted-average Accumulated expenditure $2,830,000

Computation of amount of interest capitalize.

Average Exp (A) Interest Rate (B) Capitalized Interest (B*C)
Construction loan $2,200,000 8 % $176,000
Accumulated expenditure $2,830,000 [Note 2] 9.2% [Note1] $260,360
Interest capitalize $436,360

Related Solutions

On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $2,500,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: $9,000,000, 9% bonds $6,000,000, 8% long-term note Construction expenditures incurred during 2021 were as follows: January 1 $ 1,000,000 March 31 1,600,000 June 30 1,280,000 September 30 1,000,000...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,100,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $7,000,000, 13% bonds $3,000,000, 8% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 860,000 March 31 1,460,000 June 30 1,112,000 September 30 860,000...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,550,000 at 7% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $9,000,000, 11% bonds $3,000,000, 7% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 680,000 March 31 1,280,000 June 30 896,000 September 30 680,000...
On January 1, 2018, the Highlands Company began construction ona new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,200,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018:$9,000,000, 10% bonds$6,000,000, 8% long-term noteConstruction expenditures incurred during 2018 were as follows:January 1$900,000March 311,500,000June 301,160,000September 30900,000December 31700,000Required:Calculate the amount of interest capitalized for 2018 using the specific interest...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 2,020,000 March 1, 2021 1,740,000 June 30, 2021 1,940,000 October 1, 2021 1,740,000 January 31, 2022 441,000 April 30, 2022 774,000 August 31, 2022 1,071,000 On January 1, 2021, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,090,000 March 1, 2021 780,000 June 30, 2021 980,000 October 1, 2021 780,000 January 31, 2022 297,000 April 30, 2022 630,000 August 31, 2022 927,000 On January 1, 2021, the company obtained a $3,300,000 construction loan with a 16% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,680,000 March 1, 2021 1,260,000 June 30, 2021 1,460,000 October 1, 2021 1,260,000 January 31, 2022 369,000 April 30, 2022 702,000 August 31, 2022 999,000 On January 1, 2021, the company obtained a $4,000,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,200,000 March 1, 2021 900,000 June 30, 2021 1,100,000 October 1, 2021 900,000 January 31, 2022 315,000 April 30, 2022 648,000 August 31, 2022 945,000 On January 1, 2021, the company obtained a $3,500,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,820,000 March 1, 2021 1,440,000 June 30, 2021 1,640,000 October 1, 2021 1,440,000 January 31, 2022 396,000 April 30, 2022 729,000 August 31, 2022 1,026,000 On January 1, 2021, the company obtained a $4,400,000 construction loan with a 14% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,940,000 March 1, 2021 1,680,000 June 30, 2021 1,880,000 October 1, 2021 1,680,000 January 31, 2022 432,000 April 30, 2022 765,000 August 31, 2022 1,062,000 On January 1, 2021, the company obtained a $4,800,000 construction loan with a 14% interest rate....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT