Question

In: Accounting

On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows:

January 1, 2021 $ 1,680,000

March 1, 2021 1,260,000

June 30, 2021 1,460,000

October 1, 2021 1,260,000

January 31, 2022 369,000

April 30, 2022 702,000

August 31, 2022 999,000

On January 1, 2021, the company obtained a $4,000,000 construction loan with a 12% interest rate. The loan was outstanding all of 2021 and 2022. The company’s other interest-bearing debt included two long-term notes of $3,000,000 and $7,000,000 with interest rates of 8% and 10%, respectively. Both notes were outstanding during all of 2021 and 2022. Interest is paid annually on all debt. The company’s fiscal year-end is December 31.

Required:

1. Calculate the amount of interest that Mason should capitalize in 2021 and 2022 using the specific interest method.

2. What is the total cost of the building?

3. Calculate the amount of interest expense that will appear in the 2021 and 2022 income statements.

Solutions

Expert Solution

2021 2022
Interest Capitalised $               4,53,000 $   5,67,411
Interest Expense $               9,67,000 $   8,52,589
Total cost of building $            87,50,411
Workings:
Expenditure for 2021
Jan 1,2021 $            16,80,000 X 12/12 = $        16,80,000
March 1, 2021 $            12,60,000 X 10/12 = $        10,50,000
June 30, 2021 $            14,60,000 X 6/12 = $          7,30,000
October 1, 2021 $            12,60,000 X 3/12 = $          3,15,000
$            56,60,000 $        37,75,000
Interest Capitalised in 2021
$            37,75,000 X 12.00% = $          4,53,000
Expenditure for 2022
Jan 1, 2022 ($5660000+$453000) $            61,13,000 X 9/9 = $        61,13,000
Jan 31, 2022 $               3,69,000 X 8/9 = $          3,28,000
April 30, 2022 $               7,02,000 X 5/9 = $          3,90,000
August 31. 2022 $               9,99,000 X 1/9 = $          1,11,000
$            81,83,000 $        69,42,000
Interest Capitalised in 2022
$                      69,42,000
Less: $                      40,00,000 X 12.00% X 9/12 = $          3,60,000
$                      29,42,000 X 9.40% X 9/12 = $          2,07,411
Interest Capitalised in 2022 = $          5,67,411
Weighted Average rate of all debt:-
$            30,00,000 X 8% = $          2,40,000
$            70,00,000 X 10% = $          7,00,000
$         1,00,00,000 $          9,40,000
Weighted Average rate of all debt = 9.40%
($940000 / $ 10000000)
Interest Expense for 2021:
Total Interest Incurred ($40,00,000*12%)+($30,00,000*8%)+($70,00,000*10%) = $        14,20,000
Less : Interest Capitalised = $          4,53,000
2021 Expense = $          9,67,000
Interest Expense for 2022:
Total Interest Incurred = $        14,20,000
Less : Interest Capitalised = $          5,67,411
2022 Expense = $          8,52,589
Cost of Building
Expenditure for 2021 = $        56,60,000
Interest Capitalised in 2021 = $          4,53,000
Expenditure for 2022 = $        20,70,000
Interest Capitalised in 2022 = $          5,67,411
Cost of Building = $        87,50,411

Related Solutions

On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 2,020,000 March 1, 2021 1,740,000 June 30, 2021 1,940,000 October 1, 2021 1,740,000 January 31, 2022 441,000 April 30, 2022 774,000 August 31, 2022 1,071,000 On January 1, 2021, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,090,000 March 1, 2021 780,000 June 30, 2021 980,000 October 1, 2021 780,000 January 31, 2022 297,000 April 30, 2022 630,000 August 31, 2022 927,000 On January 1, 2021, the company obtained a $3,300,000 construction loan with a 16% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,200,000 March 1, 2021 900,000 June 30, 2021 1,100,000 October 1, 2021 900,000 January 31, 2022 315,000 April 30, 2022 648,000 August 31, 2022 945,000 On January 1, 2021, the company obtained a $3,500,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,820,000 March 1, 2021 1,440,000 June 30, 2021 1,640,000 October 1, 2021 1,440,000 January 31, 2022 396,000 April 30, 2022 729,000 August 31, 2022 1,026,000 On January 1, 2021, the company obtained a $4,400,000 construction loan with a 14% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,940,000 March 1, 2021 1,680,000 June 30, 2021 1,880,000 October 1, 2021 1,680,000 January 31, 2022 432,000 April 30, 2022 765,000 August 31, 2022 1,062,000 On January 1, 2021, the company obtained a $4,800,000 construction loan with a 14% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,350,000 March 1, 2021 1,080,000 June 30, 2021 1,280,000 October 1, 2021 1,080,000 January 31, 2022 342,000 April 30, 2022 675,000 August 31, 2022 972,000 On January 1, 2021, the company obtained a $3,800,000 construction loan with a 15% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,500,000 March 1, 2021 1,200,000 June 30, 2021 1,400,000 October 1, 2021 1,200,000 January 31, 2022 360,000 April 30, 2022 693,000 August 31, 2022 990,000 On January 1, 2021, the company obtained a $4,000,000 construction loan with a 14% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 2,020,000 March 1, 2021 1,740,000 June 30, 2021 1,940,000 October 1, 2021 1,740,000 January 31, 2022 441,000 April 30, 2022 774,000 August 31, 2022 1,071,000 On January 1, 2021, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,820,000 March 1, 2021 1,440,000 June 30, 2021 1,640,000 October 1, 2021 1,440,000 January 31, 2022 396,000 April 30, 2022 729,000 August 31, 2022 1,026,000 On January 1, 2021, the company obtained a $4,400,000 construction loan with a 14% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT