Question

In: Accounting

On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,550,000 at 7% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $9,000,000, 11% bonds $3,000,000, 7% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 680,000 March 31 1,280,000 June 30 896,000 September 30 680,000 December 31 480,000 Required: Calculate the amount of interest capitalized for 2018 using the specific interest method. (Do not round the intermediate calculations. Round your percentage answers to 1 decimal place (i.e. 0.123 should be entered as 12.3%).)

Solutions

Expert Solution

Date Expenditure * Weight = Average
January 1 $680,000 12/12 $680,000
March 31 $1,280,000 9/12 $960,000
June 30 $896,000 6/12 $448,000
September 30 $680,000 3/12 $170,000
December 31 $480,000 0/12 -
$4,016,000 $2,258,000
Average * Interest Rate = Capitalized interest
Average Accumulated Expenditure $2,258,000
Construction Loan $1,550,000 7% $108,550
Other Loan(Not construction) $708,000 10% $70,800
$179,300

Other Loan = 2,258,000 - 1,550,000 = $708,000

$9,000,000*11% = $9,000,000 11% $990,000

3,000,000*7% = $3,000,000 7% $210,000

$12,000,000 $1,200,000

1,200,000/12,000,000 = 10%


Related Solutions

On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,100,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $7,000,000, 13% bonds $3,000,000, 8% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 860,000 March 31 1,460,000 June 30 1,112,000 September 30 860,000...
On January 1, 2018, the Highlands Company began construction ona new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,200,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018:$9,000,000, 10% bonds$6,000,000, 8% long-term noteConstruction expenditures incurred during 2018 were as follows:January 1$900,000March 311,500,000June 301,160,000September 30900,000December 31700,000Required:Calculate the amount of interest capitalized for 2018 using the specific interest...
On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $2,200,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: $9,000,000, 10% bonds $6,000,000, 8% long-term note Construction expenditures incurred during 2021 were as follows: January 1 $ 900,000 March 31 1,500,000 June 30 1,160,000 September 30 900,000...
On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $2,500,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: $9,000,000, 9% bonds $6,000,000, 8% long-term note Construction expenditures incurred during 2021 were as follows: January 1 $ 1,000,000 March 31 1,600,000 June 30 1,280,000 September 30 1,000,000...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,710,000 March 1, 2018 1,320,000 June 30, 2018 1,520,000 October 1, 2018 1,320,000 January 31, 2019 378,000 April 30, 2019 711,000 August 31, 2019 1,008,000 On January 1, 2018, the company obtained a $4,200,000 construction loan with a 16% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,050,000 March 1, 2018 870,000 June 30, 2018 390,000 October 1, 2018 690,000 January 31, 2019 675,000 April 30, 2019 990,000 August 31, 2019 1,710,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 900,000 June 30, 2018 1,100,000 October 1, 2018 900,000 January 31, 2019 315,000 April 30, 2019 648,000 August 31, 2019 945,000 On January 1, 2018, the company obtained a $3,500,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,420,000 March 1, 2018 1,140,000 June 30, 2018 1,340,000 October 1, 2018 1,140,000 January 31, 2019 351,000 April 30, 2019 684,000 August 31, 2019 981,000 On January 1, 2018, the company obtained a $3,900,000 construction loan with a 12% interest rate....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT