Question

In: Accounting

On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows:

January 1, 2021 $ 1,820,000
March 1, 2021 1,440,000
June 30, 2021 1,640,000
October 1, 2021 1,440,000
January 31, 2022 396,000
April 30, 2022 729,000
August 31, 2022 1,026,000

On January 1, 2021, the company obtained a $4,400,000 construction loan with a 14% interest rate. The loan was outstanding all of 2021 and 2022. The company’s other interest-bearing debt included two long-term notes of $2,000,000 and $8,000,000 with interest rates of 10% and 12%, respectively. Both notes were outstanding during all of 2021 and 2022. Interest is paid annually on all debt. The company’s fiscal year-end is December 31.

Required:
1. Calculate the amount of interest that Mason should capitalize in 2021 and 2022 using the specific interest method.
2. What is the total cost of the building?
3. Figure the amount of interest expense that will appear in the 2021 and 2022 income statements.

  • Req 1 and 3
  • Required the amount of interest that Mason should capitalize in 2021 and 2022 using the specific interest method and interest expense that will appear in the 2021 and 2022 income statements. (Do not round intermediate calculations.)
  • Interest capitalized    2021 2022
  • $ $

Interest expense $ $

Total cost of building $

Solutions

Expert Solution

Solution 1:
Year 2021: Weighted-Average accumulated expenditure and interest capitalized
Date Amount Capitalization period Weighted Average Accumulated Expenditures
01 January 2021 $18,20,000 12/12 $18,20,000
01 March 2021 $14,40,000 10/12 $12,00,000
30 June 2021 $16,40,000 6/12 $8,20,000
01 October 2021 $14,40,000 3/12 $3,60,000
Total $63,40,000 $42,00,000
*Interest rate 14%
Interest capitalized in 2021 $5,88,000
Year 2022: Weighted-Average accumulated expenditure
Date Amount Capitalization period Weighted Average Accumulated Expenditures
01 January 2022 $69,28,000 9/9 $69,28,000
31 January 2022 $3,96,000 8/9 $3,52,000
30 April 2022 $7,29,000 5/9 $4,05,000
31 August 2022 $10,26,000 1/9 $1,14,000
Total $90,79,000 $77,99,000
Weighted average interest rate of all other debt
Debt Amount Interest rate Interest amount
10% Note $20,00,000 10% $2,00,000
12% Note $80,00,000 12% $9,60,000
Totals $1,00,00,000 $11,60,000
Weighted average rate (total interets/ total debt) 11.60%
Year 2022: Interest Capitalized
Debt Amount
4400000*14%*9/12 = $4,62,000
(7799000- 4400000)*11.60%*9/12 = $2,95,713
Total interest capitalized in 2022 $7,57,713
Solution 2:
Computation of Cost of Building
Total expenditure before capitalization(9079000-588000) $84,91,000
Add: Interest capitalized in 2021 $5,88,000
Add: Interest capitalized in 2021 $7,57,713
Total cost of Building $98,36,713
Solution 3:
Computation of Interest expense
Debt Amount Interest rate Interest amount
Construction Loan $44,00,000 14% $6,16,000
10% Note $20,00,000 10% $2,00,000
12% Note $80,00,000 12% $9,60,000
Total interest incurred $17,76,000
2021 2022
Total inerest incurred $17,76,000 $17,76,000
Less: Interest Capitalized $5,88,000 $7,57,713
Interest Expense $11,88,000 $10,18,287

Related Solutions

On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 2,020,000 March 1, 2021 1,740,000 June 30, 2021 1,940,000 October 1, 2021 1,740,000 January 31, 2022 441,000 April 30, 2022 774,000 August 31, 2022 1,071,000 On January 1, 2021, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,090,000 March 1, 2021 780,000 June 30, 2021 980,000 October 1, 2021 780,000 January 31, 2022 297,000 April 30, 2022 630,000 August 31, 2022 927,000 On January 1, 2021, the company obtained a $3,300,000 construction loan with a 16% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,680,000 March 1, 2021 1,260,000 June 30, 2021 1,460,000 October 1, 2021 1,260,000 January 31, 2022 369,000 April 30, 2022 702,000 August 31, 2022 999,000 On January 1, 2021, the company obtained a $4,000,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,200,000 March 1, 2021 900,000 June 30, 2021 1,100,000 October 1, 2021 900,000 January 31, 2022 315,000 April 30, 2022 648,000 August 31, 2022 945,000 On January 1, 2021, the company obtained a $3,500,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,940,000 March 1, 2021 1,680,000 June 30, 2021 1,880,000 October 1, 2021 1,680,000 January 31, 2022 432,000 April 30, 2022 765,000 August 31, 2022 1,062,000 On January 1, 2021, the company obtained a $4,800,000 construction loan with a 14% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,350,000 March 1, 2021 1,080,000 June 30, 2021 1,280,000 October 1, 2021 1,080,000 January 31, 2022 342,000 April 30, 2022 675,000 August 31, 2022 972,000 On January 1, 2021, the company obtained a $3,800,000 construction loan with a 15% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,500,000 March 1, 2021 1,200,000 June 30, 2021 1,400,000 October 1, 2021 1,200,000 January 31, 2022 360,000 April 30, 2022 693,000 August 31, 2022 990,000 On January 1, 2021, the company obtained a $4,000,000 construction loan with a 14% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 2,020,000 March 1, 2021 1,740,000 June 30, 2021 1,940,000 October 1, 2021 1,740,000 January 31, 2022 441,000 April 30, 2022 774,000 August 31, 2022 1,071,000 On January 1, 2021, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,820,000 March 1, 2021 1,440,000 June 30, 2021 1,640,000 October 1, 2021 1,440,000 January 31, 2022 396,000 April 30, 2022 729,000 August 31, 2022 1,026,000 On January 1, 2021, the company obtained a $4,400,000 construction loan with a 14% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT