Question

In: Accounting

Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking...

Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 71,000 Pounds started into production during May 360,000 Pounds completed and transferred out ? Pounds in process, May 31; materials 75% complete; conversion 25% complete 31,000 Cost data: Work in process inventory, May 1: Materials cost $ 90,100 Conversion cost $ 46,400 Cost added during May: Materials cost $ 468,590 Conversion cost $ 255,335 Required: 1. Compute the equivalent units of production for materials and conversion for May. 2. Compute the cost per equivalent unit for materials and conversion for May. 3. Compute the cost of ending work in process inventory for materials, conversion, and in total for May. 4. Compute the cost of units transferred out to the next department for materials, conversion, and in total for May. 5. Prepare a cost reconciliation report for May.

Solutions

Expert Solution

Solution

Material Conversion
Equivalent Units of Production                             423,250                 407,750

.

Material Conversion
Cost per equivalent Unit $ 1.32 $ 0.74

.

Material Conversion Total
Ending Inventory $ 30,690 $ 5,735 $ 36,425

.

Material Conversion Total
Units Completed and transferred $ 528,000 $ 296,000 $ 824,000

.

Cost Reconciliation
Costs to be accounted for:
Beginning Wip cost $ 136,500
Cost incurred during period $ 723,925
Total cost to be accounted for $ 860,425
Costs accounted for as follows:
Cost of Units Transferred Out $ 824,000
Cost of Ending Wip $ 36,425
Total cost accounted for $ 860,425

Working

Reconciliation of Units
A Beginning WIP                   71,000
B Introduced                 360,000
C=A+B TOTAL                 431,000
D Transferred out                 400,000
E=C-D Ending WIP                   31,000

.

Statement of Equivalent Units(Weighted average)
Material Conversion
Units Complete % Equivalent units Complete % Equivalent units
Transferred out                             400,000 100%                  400,000 100%                 400,000
Ending WIP                                31,000 75%                    23,250 25%                     7,750
Total                             431,000 Total                  423,250 Total                 407,750

.

Cost per Equivalent Units (Weighted average)
COST Material Conversion TOTAL
Beginning WIP Inventory Cost (A) $ 90,100 $ 46,400 $ 136,500
Cost incurred during period (B) $ 468,590 $ 255,335 $ 723,925
Total Cost to be accounted for (C=A+B) $ 558,690 $ 301,735 $ 860,425
Total Equivalent Units(D)                 423,250                  407,750
Cost per Equivalent Units (E=C/D) $ 1.32 $ 0.74 $ 2.06

.

Statement of cost (Weighted average)
Cost Equivalent Cost/unit Ending WIP Transferred
Units Cost Allocated Units Cost Allocated
Material $ 1.32                   23,250 $          30,690.00                     400,000 $        528,000.00
Conversion $ 0.74                     7,750 $             5,735.00                     400,000 $        296,000.00
TOTAL $ 860,425 TOTAL $ 36,425 TOTAL $ 824,000

Related Solutions

Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 70,000 Pounds started into production during May 350,000 Pounds completed and transferred out ? Pounds in process, May 31; materials 70% complete; conversion 30% complete 30,000 Cost data:...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 66,000 Pounds started into production during May 310,000 Pounds completed and transferred out ? Pounds in process, May 31; materials 70% complete; conversion 30% complete 26,000 Cost data:...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 76,000 Pounds started into production during May 410,000 Pounds completed and transferred out ? Pounds in process, May 31; materials 60% complete; conversion 40% complete 36,000 Cost data:...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 87,000 Pounds started into production during May 520,000 Pounds completed and transferred out ? Pounds in process, May 31; materials 75% complete; conversion 25% complete 47,000 Cost data:...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 81,000 Pounds started into production during May 460,000 Pounds completed and transferred out ? Pounds in process, May 31; materials 80% complete; conversion 20% complete 55,000 Cost data:...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 64,000 Pounds started into production during May 290,000 Pounds completed and transferred out ? Pounds in process, May 31; materials 60% complete; conversion 40% complete 24,000 Cost data:...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 73,000 Pounds started into production during May 380,000 Pounds completed and transferred out ? Pounds in process, May 31; materials 80% complete; conversion 20% complete 33,000 Cost data:...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 89,000 Pounds started into production during May 540,000 Pounds completed and transferred out ? Pounds in process, May 31; materials 80% complete; conversion 20% complete 60,000 Cost data:...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 87,000 Pounds started into production during May 520,000 Pounds completed and transferred out ? Pounds in process, May 31; materials 75% complete; conversion 25% complete 47,000 Cost data:...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 60,000 Pounds started into production during May 250,000 Pounds completed and transferred out ? Pounds in process, May 31; materials 60% complete; conversion 40% complete 20,000 Cost data:...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT