Question

In: Economics

Discuss in details the seven tools and techniques for estimating activity resources process. 1- Answer in...

Discuss in details the seven tools and techniques for estimating activity resources process.

1- Answer in details
2- write the answer (please don't post a picture)

Thanks

Solutions

Expert Solution

7 UniqueEstimation Tools and Techniques  used across Estimate Activity Resources, Estimate Activity Durations and Estimate Costs processes are:

  1. Alternatives analysis: It is a technique where you look at various ways to assign resources by varying the number of resources as well as the kind of resources and then decides upon the best one.
  2. Analogous Estimating: It is a technique where you refer to those previous projects which were having, scope or activities, similar to your current project.Then you figure out how much time and/or these activities have taken earlier, during that project, to make estimation for duration and/or cost of similar activities in your project.
  3. Bottomup Estimating: Using this technique you estimate resources or costs by breaking down complex activities into smaller pieces and working out resource or cost assignments for these smaller activities using other resource / cost estimating tools and techniques.
  4. Expert Judgment: This technique is used in all  estimation processes.Experts, with expertise appropriate to the concerned activity, are asked to estimate the resources and/or duration and/or cost.
  5. Parametric Estimating: This estimation, like analogous estimation technique, requires historical information gathered from previous projects.This technique is used for both cost and time estimates calculations.Unlike analogous estimation technique, parametric estimation requires plugging the historical data into a formula, spreadsheet, database, or computer program to come up with an estimate.It is sometime also referred as Quantitative based estimating.E.g When you need to determine what would be the total cost of construction when you have cost per square foot or the units of work multiplied by productivity unit rate to estimate activity duration.Project Management Software Estimation T
  6. Published Estimating Data: This technique is used only for estimating activity resources.This published data can include articles, books, journals and periodicals from various industries that have proven data with similar projects.Using the Published Estimating Data Project Managers can make a rough estimation of how many resources they need.
  7. Reserve Analysis: Used for estimating activity duration and cost, reserve analysis includes estimation of additional time to the project schedule and additional cost to the project budget.It is more of like analysis for the contingency or adding buffers to the estimations.

Related Solutions

Discuss in details the seven tools and techniques for estimating activity resources process.
Discuss in details the seven tools and techniques for estimating activity resources process.
Discuss in details the seven tools and techniques for estimating activity resources process.
Discuss in details the seven tools and techniques for estimating activity resources process.
Discuss in details the seven tools and techniques for estimating activity resources process. please write the...
Discuss in details the seven tools and techniques for estimating activity resources process. please write the answer not pic .
List the main members of the set of techniques known as the Seven Tools of Total...
List the main members of the set of techniques known as the Seven Tools of Total Quality Management (TQM). Then, mention two out of this list which are considered key techniques for defining processes and identifying sources of variation. At which stage in a CQI project life-cycle are these two key techniques needed the most?
1. Triangulation is a technique used in estimating where the results of three estimating techniques are...
1. Triangulation is a technique used in estimating where the results of three estimating techniques are averaged or compared to improve the overall estimate based on a single method. True False 2. Quality is directly impacted by the balance achieved in the triple constraint. True False 3. Which of the following is NOT a knowledge area for project managers as specified in your text a. Time Management b. Cost Management c. Risk Management d. Skills Management
comprehensively discuss the main financial management tools and techniques
comprehensively discuss the main financial management tools and techniques
Discuss the tools and techniques best suited for resistance to change?
Discuss the tools and techniques best suited for resistance to change?
WEEK 9 DISCUSSION Answer any two of the questions below: Discuss any approaches, tools, or techniques...
WEEK 9 DISCUSSION Answer any two of the questions below: Discuss any approaches, tools, or techniques that may be helpful in assessing and identifying risks in IS projects. How can communication help in identifying AND managing risk? Give an example from your personal or professional experience. When looking at risks in the project environment, why are we concerned with the impact and probability of a potential risk event? When is the best time to assess potential risks in an IS...
The two Tools & Techniques of the Create WBS process are Decomposition and Expert Judgement. In...
The two Tools & Techniques of the Create WBS process are Decomposition and Expert Judgement. In this context, what is Expert Judgment?.
Debate the inputs, tools and techniques, and the outputs of the risk management process as prescribed...
Debate the inputs, tools and techniques, and the outputs of the risk management process as prescribed by the PMI. Your discussion must reference the case study even if you have to make some assumptions. PMI: Project Management Institute (PMI), in A Guide to the Project Management Body of Knowledge (PMBOKĀ®
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT