Question

In: Finance

All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...

All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index.

Criteria Project_A Project_B Project_C Project_D Project_E Project_F Project_G
NPV= $14,154 $77,992 $29,515 $11,564 ($8,849) $26,514 $30,022
IRR= 28.66% 20.33% 19.72% 45.52% 9.03% 16.40% 16.05%
MIRR= 17.28% 14.35% 12.86% 22.76% 9.53% 11.97% 12.45%
PI= 1.57 1.31 1.20 2.16 0.97 1.13 1.17

The cost of capital (r) is 10%.

Which of the following 10 statements are true (there are several, select all that are correct). Consider each statement on its own separate from the others listed:

Question 1 options:

If projects A & B are mutually exclusive, projects C and D are also mutually exclusive and projects F and G are also mutually exclusive (all others are independent), under the IRR rule projects B, C, and G should be undertaken

If all projects are independent, under the PI rule, projects A, B, C, D, F, and G should be taken

If all projects are independent, under the NPV rule, only project E should be rejected

If projects A & B are mutually exclusive, projects C and D are also mutually exclusive and projects F and G are also mutually exclusive (all others are independent), under the NPV rule projects B, C, and G should be undertaken

If all projects are independent, under the IRR rule only projects A, B, C, D, F and G should be taken

If all projects are mutually exclusive, under the NPV rule only project B should be taken

If all projects are independent, under the MIRR rule only project E should be rejected

If projects A & B are mutually exclusive, projects C and D are also mutually exclusive and projects F and G are also mutually exclusive (all others are independent), under the PI rule projects B, C, and G should be undertaken

If projects A & B are mutually exclusive, projects C and D are also mutually exclusive and projects F and G are also mutually exclusive (all others are independent), under the MIRR rule projects B, C, and F should be undertaken

If all projects are mutually exclusive, under the NPV rule projects A, B, C, D, F and G should be taken

All projects are shown above - Project G is the last project....

Solutions

Expert Solution

Question 1 options:

If projects A & B are mutually exclusive, projects C and D are also mutually exclusive and projects F and G are also mutually exclusive (all others are independent), under the IRR rule projects B, C, and G should be undertaken (False, because higher IRR is chosen over lower IRR. So project A,D and F should be undertaken)

If all projects are independent, under the PI rule, projects A, B, C, D, F, and G should be taken(True)

If all projects are independent, under the NPV rule, only project E should be rejected(True) Positive NPV is undertaken

If projects A & B are mutually exclusive, projects C and D are also mutually exclusive and projects F and G are also mutually exclusive (all others are independent), under the NPV rule projects B, C, and G should be undertaken (True). High NPV is undertaken

If all projects are independent, under the IRR rule only projects A, B, C, D, F and G should be taken (True) IRR is greater than Cost of capital.

If all projects are mutually exclusive, under the NPV rule only project B should be taken (True) because it has highest NPV

If all projects are independent, under the MIRR rule only project E should be rejected (True)

If projects A & B are mutually exclusive, projects C and D are also mutually exclusive and projects F and G are also mutually exclusive (all others are independent), under the PI rule projects B, C, and G should be undertaken (False higher PI is preferable so Project A,D and G are undertaken and PI has to be more than 1 to undertake the project).

If projects A & B are mutually exclusive, projects C and D are also mutually exclusive and projects F and G are also mutually exclusive (all others are independent), under the MIRR rule projects B, C, and F should be undertaken (False) higher MIRR are undertaken

If all projects are mutually exclusive, under the NPV rule projects A, B, C, D, F and G should be taken (False, if projects are mutually exclusive then Project B is undertaken as it has highest NPV)


Related Solutions

All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:    Project_A     Project_B     Project_C     Project_D     Project_E     Project_F     Project_G NPV=    $137,083    $31,290    $6,016    $7,647    ($584)    $12,521    $9,214 IRR=    31.80%    48.34%    12.03%    11.30%    9.94%    26.79%    37.87% MIRR=    18.52%    23.52%...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria: Project_A Project_B Project_C Project_D Project_E Project_F Project_G NPV= $137,083 $36,290 $6,016 $7,647 ($584) $14,521 $8,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 0.999 2.28 1.92 The discounting rate (r) is 10%. Which of the following...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Project A Project B Project C Project D Project E Project F Project G NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224) IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47% MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50% PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871 Which of the following...
3. Understanding the IRR and NPV The net present value (NPV) and internal rate of return...
3. Understanding the IRR and NPV The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Cute Camel Woodcraft Company: Last Tuesday, Cute Camel Woodcraft Company lost a portion of its planning and financial data when both its main and its backup servers crashed. The company’s CFO remembers that the internal rate of return (IRR) of Project Gamma is...
3. Understanding the IRR and NPV The net present value (NPV) and internal rate of return...
3. Understanding the IRR and NPV The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Blue Hamster Manufacturing Inc.: Last Tuesday, Blue Hamster Manufacturing Inc. lost a portion of its planning and financial data when both its main and its backup servers crashed. The company’s CFO remembers that the internal rate of return (IRR) of Project Delta is...
3. Understanding the IRR and NPV The net present value (NPV) and internal rate of return...
3. Understanding the IRR and NPV The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Cold Goose Metal Works Inc.: Last Tuesday, Cold Goose Metal Works Inc. lost a portion of its planning and financial data when both its main and its backup servers crashed. The company’s CFO remembers that the internal rate of return (IRR) of Project...
The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are...
The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Cold Goose Metal Works Inc.: Last Tuesday, Cold Goose Metal Works Inc. lost a portion of its planning and financial data when both its main and its backup servers crashed. The company’s CFO remembers that the internal rate of return (IRR) of Project Omicron is 13.2%, but he can’t...
Describe the use of internal rate of return (IRR), net present value (NPV), and the payback...
Describe the use of internal rate of return (IRR), net present value (NPV), and the payback method in evaluating project cash flows.
Use both the NET present value (NPV) and the Internal Rate of return (IRR) to assess...
Use both the NET present value (NPV) and the Internal Rate of return (IRR) to assess and draw conclusions when advising a company which is wondering whether to K18 000 on an item of equipment in order to obtain cash profits as shown below                       Year                                          K                         1                                              6000                         2                                              8000 3            5000 4                                              1000 Note: The company requires a return of 10% per annum.
The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are...
The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Blue Hamster Manufacturing Inc.: Last Tuesday, Blue Hamster Manufacturing Inc. lost a portion of its planning and financial data when both its main and its backup servers crashed. The company’s CFO remembers that the internal rate of return (IRR) of Project Lambda is 11.3%, but he can’t recall how...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT