Question

In: Finance

Problem 10-7 NPV Your division is considering two investment projects, each of which requires an up-front...

Problem 10-7 NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 6,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 7,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' net present values, assuming the cost of capital is 10%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' net present values, assuming the cost of capital is 15%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' IRRs at these same costs of capital? Round your answers to two decimal places. Project A % Project B %

Please show all work/calculations!

Solutions

Expert Solution

Project A
Discount rate 5.000%
Year 0 1 2 3
Cash flow stream -17000000 6000000 10000000 20000000
Discounting factor 1.000 1.050 1.103 1.158
Discounted cash flows project -17000000.000 5714285.714 9070294.785 17276751.971
NPV = Sum of discounted cash flows
NPV Project A = 15061332.47
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project B
Discount rate 5.000%
Year 0 1 2 3
Cash flow stream -17000000 20000000 10000000 7000000
Discounting factor 1.000 1.050 1.103 1.158
Discounted cash flows project -17000000.000 19047619.048 9070294.785 6046863.190
NPV = Sum of discounted cash flows
NPV Project B = 17164777.02
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project A
Discount rate 10.000%
Year 0 1 2 3
Cash flow stream -17000000 6000000 10000000 20000000
Discounting factor 1.000 1.100 1.210 1.331
Discounted cash flows project -17000000.000 5454545.455 8264462.810 15026296.018
NPV = Sum of discounted cash flows
NPV Project A = 11745304.28
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project B
Discount rate 10.000%
Year 0 1 2 3
Cash flow stream -17000000 20000000 10000000 7000000
Discounting factor 1.000 1.100 1.210 1.331
Discounted cash flows project -17000000.000 18181818.182 8264462.810 5259203.606
NPV = Sum of discounted cash flows
NPV Project B = 14705484.60
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project A
Discount rate 15.000%
Year 0 1 2 3
Cash flow stream -17000000 6000000 10000000 20000000
Discounting factor 1.000 1.150 1.323 1.521
Discounted cash flows project -17000000.000 5217391.304 7561436.673 13150324.649
NPV = Sum of discounted cash flows
NPV Project A = 8929152.63
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project B
Discount rate 15.000%
Year 0 1 2 3
Cash flow stream -17000000 20000000 10000000 7000000
Discounting factor 1.000 1.150 1.323 1.521
Discounted cash flows project -17000000.000 17391304.348 7561436.673 4602613.627
NPV = Sum of discounted cash flows
NPV Project B = 12555354.65
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project A
IRR is the rate at which NPV =0
IRR 38.77%
Year 0 1 2 3
Cash flow stream -17000000.000 6000000.000 10000000.000 20000000.000
Discounting factor 1.000 1.388 1.926 2.672
Discounted cash flows project -17000000.000 4323613.781 5192676.702 7483709.517
NPV = Sum of discounted cash flows
NPV Project A = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 38.77%
Project B
IRR is the rate at which NPV =0
IRR 67.46%
Year 0 1 2 3
Cash flow stream -17000000.000 20000000.000 10000000.000 7000000.000
Discounting factor 1.000 1.675 2.804 4.696
Discounted cash flows project -17000000.000 11943285.351 3566051.625 1490663.025
NPV = Sum of discounted cash flows
NPV Project B = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

Related Solutions

Problem 12-7 NPV Your division is considering two investment projects, each of which requires an up-front...
Problem 12-7 NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects'...
Problem 10-07 NPV Your division is considering two investment projects, each of which requires an up-front...
Problem 10-07 NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $19 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' net...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  4,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $23 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' net present...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $23 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  6,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 8,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' net present values,...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  6,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 7,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $   Project B $   What are the two projects' net present values,...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $23 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 8,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' net present values,...
1.NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
1.NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 6,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 7,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are...
Your division is considering two investment projects, each of which requires an up-front expenditure of $17...
Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%, 10% and 15%? What are the two projects' IRRs at these same costs of capital?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT