In: Finance
Cowboys Copies, Inc., wants to upgrade its copy machines. Its
last update was 2 years ago, when it spent $1,150 on equipment with
an assumed life of 5 years and. The firm uses MACRS depreciation.
The old equipment can be sold today for $800. A new system can be
installed today for $1,500. This will have a 3 year life and will
be depreciated under MACRS 3 year schedule. At the end of 3 years,
the new equipment will be worthless (therefore, market value of
zero).
The company projects unit sales associated with the new equipment
as follows:
Year | Sales (in Units) |
1 | 72 |
2 | 80 |
3 | 64 |
Thereafter | 0 |
Investment in net working capital will be 20 percent of the
sales for the following year.
Therefore, total net working capital for year 0 would be 20 percent
of the sales in year 1 and for year 1, you will need total net
working capital amounting to 20 percent of the sales for year 2 in
dollar values (not in units). The production costs are $15 per
unit, and the units are priced at $40 each. The firm is in the 40
percent marginal tax bracket and required rate of return is
12%.
MACRS Schedule
Year | 3 year | 5 year |
1 | 33.33 | 20.00 |
2 | 44.45 | 32.00 |
3 | 14.81 | 19.20 |
4 | 7.41 | 11.52 |
5 | 11.52 | |
6 | 5.76 |
a. What are the operating cash flows for Years 1 to 3?
b. what are the cash flows from net working capital for years 1 to 3?
c. what is the cash flow from the sales of the od equipment at year 3?
d. what is the NPV of this project? would you accept this project?
e. what is the IRR of this project? would you accept this project?
Depreciation Schedule as per Marcs and Tax Savings per year Schedule:
|
a) b) c) in a single table
Operating Cash Flows for year 1 to 3
|
Notes:
d)
NPV = 901.03 / ( 1.12)1 + 1112.37 / ( 1.12)2 + 685.7 / (1.12)3 - 1500 + 800
= $ 1,302.83
Note: The sale value of old equipment has been added back to intial investment
NPV > 0. So, I will accept this project.
e) IRR is calculated using Excel or Financial Calculator. Excel function is IRR( ).
NPV, if set to 0 will give the value of IRR which is used to discount the present value.
IRR = 121%.
IRR > Required Rate of Return or Cost of Capital.
Hence, we will accept the project.