Question

In: Accounting

Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job...

Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data:   

Job A256 Job A257 Job A258 Job A260
Beginning balance $ 1,050 $ 540 $ 0 $ 0
Charged to the jobs during October:
Direct materials $ 2,840 $ 4,000 $ 1,420 $ 3,770
Direct labor $ 1,240 $ 840 $ 530 $ 360
Manufacturing overhead applied $ 4,462 $ 1,830 $ 2,560 $ 480
Units completed 218 0 110 0
Units in process at the end of October 0 308 0 261
Units sold during October 158 0 51 0

Jobs A256 and A258 were completed during October. The other two jobs had not yet been completed at the end of October. There was no finished goods inventory on October 1.

       

In October, overhead was overapplied by $1,390. The company adjusts its cost of goods sold every month for the amount of the underapplied or overapplied overhead.

Required:     

1. Using the direct method, what is the cost of goods sold for October?

2. What is the total value of the finished goods inventory at the end of October?

      

3. What is the total value of the work in process inventory at the end of October?

Solutions

Expert Solution

Solution:

Part 1 – Using the direct method, Cost of Goods Sold for October is $9,043

Direct method means the calculation of cost before charging over or under applied overhead to Cost of Goods Sold.

Working

Job A256

Job A257

Job A258

Job A260

TOTAL

Beginning balance

$1,050

$540

$0

$0

Charged to the jobs during October:

Direct materials

$2,840

$4,000

$1,420

$3,770

Direct labor

$1,240

$840

$530

$360

Manufacturing overhead applied

$4,462

$1,830

$2,560

$480

Total Manufacturing Cost (A)

9,592

7,210

4,510

4,610

Status

Completed

Not Completed

Completed

Not Completed

Total Units Completed (B)

218 Units

110 Units

Cost per Completed Unit (A/B)

$44.00

$41.00

Units Sold during October

158 Units

51 Units

Total Cost of Goods Sold (Cost per Completed Unit x Units Sold)

$6,952.00

$2,091.00

$9,043.00

Part 2 --- Total Value of Finished Goods Inventory at the end of October

Value of Finished Goods Ending Inventory

Completed Jobs

Job A256

Job A258

Units completed

218

110

Units sold during October

158

51

Ending Finished Goods Inventory

(Completed Units - Sold Units)

60

59

Cost per Completed Unit

$44

$41

Value of Finished Goods Inventory

$2,640

(60*$44)

$2,419

(59*41)

Total Value of Finished Goods Inventory = $2,640 + $2,419 = $5,059

Part 3 – Total Value of Work in Process Inventory

Jobs Not Completed

Job A257

Job A260

Total

Total Manufacturing Cost (Refer Part 1)

$7,210

$4,610

$11,820

Total Value of Work IN Process Inventory = $11,820

Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you


Related Solutions

Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job...
Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data:    Job A256 Job A257 Job A258 Job A260 Beginning balance $ 1,060 $ 530 $ 0 $ 0 Charged to the jobs during October: Direct materials $ 2,820 $ 4,040 $ 1,530 $ 3,780 Direct labor $ 1,150 $ 880 $ 520 $ 310 Manufacturing overhead applied...
In a job shop operation, four jobs may be performed on any of four machines. The...
In a job shop operation, four jobs may be performed on any of four machines. The hours required for each job on each machine are presented in the following table. The plant supervisor would like to assign jobs so that total time is minimized. Find the best solution. Which assignments should be made? Machine Job W X Y Z A12 10 14 16 13 A15 12 13 15 12 B2 9 12 12 11 B9 14 16 18 16
1. Prepare a job cost sheet for each job worked on during the month. 2. Prepare...
1. Prepare a job cost sheet for each job worked on during the month. 2. Prepare journal entries to record the events and transactions a through i. 3. Post the journal entries for the transactions to the following T-accounts, each of which started the month with a zero balance. 4. Prepare a report showing the total cost of each job in process and prove that the sum of their costs equals the Work in Process Inventory account balance. Prepare similar...
Adams Company is a manufacturing company that has worked on several production jobs during the first...
Adams Company is a manufacturing company that has worked on several production jobs during the first quarter of the year. Below is a list of all the jobs for the quarter: Balance Job. No. 356 357 358 359 360 $ 450 1,235 378 689 456 Jobs 356, 357, 358, and 359 were completed. Jobs 356 and 357 were sold at a profit of $500 on each job.   12. What is the ending balance of Work in Process for Adams...
In a small job shop department there are four jobs to be assigned to three workers....
In a small job shop department there are four jobs to be assigned to three workers. The table below indicates the weekly costs incurred by assigning each worker to each job. The objective is to find the optimal assignment that will minimize the total cost.                      Worker/Job │   I      II     III    IV A     │ 12      10    11    15   B     │ 13      16    14    12   C     │ 11 12    13    10       Formulate this problem as a linear programming model...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q.
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
Adams Company is a manufacturing company that has worked on several production jobs during the first quarter of the year
Adams Company is a manufacturing company that has worked on several production jobs during the first quarter of the year. Below is a list of all the jobs for the quarter:                 Balance Job No. 356 $ 450 Job No. 357   1,235Job No. 358  378 Job No. 359   689ob No. 360  456 Jobs 356, 357, 358, and 359 were completed. Jobs 356 and 357 were sold at a profit of $500 on each job. What is the ending balance...
​Adams Company is a manufacturing company that has worked on several production jobs during the first quarter of the year.
Adams Company is a manufacturing company that has worked on several production jobs during the first quarter of the year. Below is a list of all the jobs for the quarter:Job No350 Jobs 356, 357, 358, and 359 were completed. Jobs 356 and 357 were sold at a profit of $500 on each job. What is the ending balance of Cost of Goods Sold for Adams Company at the end of the first quarter? a. $1,685 b. $2,685 c. $685 d. $456
Kyle Forman worked 48 hours during the week for Erickson Company at two different jobs. His...
Kyle Forman worked 48 hours during the week for Erickson Company at two different jobs. His pay rate was $14.90 for the first 40 hours, and his pay rate was $11.00 for the other 8 hours. Round your overtime rate and other interim computations to two decimal places and use the rounded amount in subsequent computations. Round the final answers to the nearest cent. Determine his gross pay for that week if the company uses the one-half average rate method....
Assume that Ali Services company bills its clients for jobs completed during the month. On October...
Assume that Ali Services company bills its clients for jobs completed during the month. On October 31, 2004, Ali Services company billed its clients $450,000 for products sold during October. During November, Ali Services company collected 20 percent of its sales billed on October 31. the cost price this products was $200,000 which is paid 80 percent in cash. What would be recorded by Ali Services company under the cash basis?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT