Question

In: Accounting

On January 1, 2015, Toby Manufacturing Company began construction of a building to be used as...

On January 1, 2015, Toby Manufacturing Company began construction of a building to be used as its second office. The building is completed on August 31, 2016. Expenditures on the project were as follows:

January 3, 2015 $900,000

March 1, 2015 600,000

June 30, 2015 700,000

November 1, 2015 600,000

January 31, 2016 800,000

April 30, 2016 900,000

August 31, 2016 675,000

In order to finance the project, the company obtained a $2 million loan with a 10% interest on January 1, 2015. The principal of the loan will be paid off at the end of 2016. The company’s other interest-bearing debt includes two long-term notes of $5,000,000 and $7,000,000 with interest rates of 6% and 9%, respectively. Both notes are outstanding during all of 2015 and 2015. The company’s fiscal year-end is December 31.

Required: 1. Calculate the amount of interest that Toby should capitalize in 2015 and 2016 using the specific interest method. 2. Calculate interest expense that will appear in the 2015 and 2016 income statements. 3. What is the total cost of the building?

Solutions

Expert Solution

Solution:

1.

Date Of expenditure Amount of expenditure
3-Jan-2015                                                                          9,00,000
1-Mar-2015                                                                          6,00,000
30-Jun-2015                                                                          7,00,000
1-Nov-2015                                                                          6,00,000
31-Jan-2016                                                                          8,00,000
30-Apr-2016                                                                          9,00,000
31-Aug-2016                                                                          6,75,000
Amount Interest
Specific Borrowing                                                                        20,00,000 10%
Other Borrowing 1                                                                        50,00,000 6%
Other Borrowing 2                                                                        70,00,000 9%
Step 1: Weighted average Accumulated Expenses
900000 X 12/12                                                                          9,00,000
600000 X 10/12                                                                          5,00,000
700000 X 6/12                                                                          3,50,000
600000 X 2/12                                                                          1,00,000
Total                                                                        18,50,000
Interest to be capitalized in 2015 1850000 X 10%
i.e.                                                                          1,85,000
Interest to be capitalized in 2016
Weighted average Accumulated Expenses
800000 X 7/12                                                                          4,66,667
900000 X 4/12                                                                          3,00,000
675000 X 0/12                                                                                       -  
Total                                                                          7,66,667
Interest to be capitalised
From Specific Borrowing 150000 X 10% X 8/12
i.e.                                                                              10,000 ------(1)
From Other Borrowings
5000000 x 6%                                                                          3,00,000
7000000 x 9%                                                                          6,30,000
Total                                                                          9,30,000
Interest Rate 930000 x 100/(5000000+7000000)
i.e.                                                                                  7.75
616667 X 7.75% X 8/12                                                                              31,861 ------(2)
Total Interest to be capitalized                                                                              41,861 ------(1)+(2)
2. Interest expenses that appear in income statement in 2015
Total Interest
From Specific Borrowing 2000000 x 10%           2,00,000
From Other Borrowing 5000000 x 6% + 7000000 x 9%           9,30,000
Total Interest        11,30,000 -----(3)
Interest Capitalised during the year 2015           1,85,000 -----(4)
Interest showed in income statement in 2015 year           9,45,000 -----(3)-(4)
Since the principle amount is not repaid the amount of total interest in 2016 also remains the same
i.e.        11,30,000 -----(5)
Interest Capitalised during the year 2016              41,861 -----(6)
Interest showed in income statement in 2016 year        10,88,139 -----(5)-(6)
3. Total Cost of building
Expenses incurred 900000+600000+700000+600000+800000+900000+675000
i.e.                                                                        51,75,000 -----(7)
Interest to be capitalized 185000+41861
i.e.                                                                          2,26,861 -----(8)
Total Building cost                                                                        54,01,861 -----(7)+(8)

Related Solutions

On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 2,020,000 March 1, 2021 1,740,000 June 30, 2021 1,940,000 October 1, 2021 1,740,000 January 31, 2022 441,000 April 30, 2022 774,000 August 31, 2022 1,071,000 On January 1, 2021, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,710,000 March 1, 2018 1,320,000 June 30, 2018 1,520,000 October 1, 2018 1,320,000 January 31, 2019 378,000 April 30, 2019 711,000 August 31, 2019 1,008,000 On January 1, 2018, the company obtained a $4,200,000 construction loan with a 16% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,050,000 March 1, 2018 870,000 June 30, 2018 390,000 October 1, 2018 690,000 January 31, 2019 675,000 April 30, 2019 990,000 August 31, 2019 1,710,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 900,000 June 30, 2018 1,100,000 October 1, 2018 900,000 January 31, 2019 315,000 April 30, 2019 648,000 August 31, 2019 945,000 On January 1, 2018, the company obtained a $3,500,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,420,000 March 1, 2018 1,140,000 June 30, 2018 1,340,000 October 1, 2018 1,140,000 January 31, 2019 351,000 April 30, 2019 684,000 August 31, 2019 981,000 On January 1, 2018, the company obtained a $3,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,070,000 March 1, 2018 840,000 June 30, 2018 380,000 October 1, 2018 710,000 January 31, 2019 1,170,000 April 30, 2019 1,485,000 August 31, 2019 2,700,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,300,000 March 1, 2018 720,000 June 30, 2018 340,000 October 1, 2018 640,000 January 31, 2019 450,000 April 30, 2019 765,000 August 31, 2019 1,260,000 On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 660,000 June 30, 2018 520,000 October 1, 2018 620,000 January 31, 2019 360,000 April 30, 2019 675,000 August 31, 2019 1,080,000 On January 1, 2018, the company obtained a $3 million construction loan with a 11% interest...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT