Question

In: Accounting

The following is six months of data on the cost and production volume to manufacture crates...

The following is six months of data on the cost and production volume to manufacture crates of skittles. In order to better predict costs, the manager is trying to understand the relationship between production volume and cost. Use the hi-lo method to determine the cost equation. Round as needed to the closest penny.  (Please report the cost equation in y=mx+b format).

Production Volume Total Cost
July 265 $4,920
August 320 $5,210
September 745 $8,760
October 410 $6,020
November 530 $7,300
December 740 $12,900

Solutions

Expert Solution

High low method assumes that linear model of cost behaviour is valid. Hence, the following equation can be used to compute variable and fixed costs.

y = a + bx

where:

y = total cost;

a = total fixed costs;

b = variable cost per level of activity (or units);

x = level of activity (or number of units).

Step 1

Determine the lowest point of activity (x1) and the corresponding cost (y1), and the highest point of activity (x2) and its corresponding cost (y2)

Highest point of activity (x1) = September = 745

Corresponding cost at highest point (y1) = September = $8,760

Lowest point of activity (x2) = July = 265

Corresponding cost at lowest point (y2) = July = $4.920

Step 2

Compute for the variable cost per unit or slope (b) using the formula:

b =

y2 - y1

x2 - x1

b= $8,760 – $4,920

      $745 – 265

b= 8 per unit

Step 3

Determine the fixed cost (a) by substituting the slope in the cost equation

Y = a + bx

Adding the value from highest point September

8,760 = a + 8 X 745

a = 8,760 – 5,960

a = 2,800

Step 4

Now that we have isolated both the fixed and the variable components, we can express total cost in the following equation:

Y = $2,800 + 8x

Where Y is total cost and x is production volume.


Related Solutions

Based on the last six months of data, suppose that the percent of daily volume that...
Based on the last six months of data, suppose that the percent of daily volume that occurs in each hour is as follows: 9:30-10:30          20% 10:30-11:30         10% 11:30-12:30         10% 12:30-1:30           10% 1:30-2:30              10% 2:30-3:30              15% 3:30-4:00              25% You need to design a VWAP algo to buy 28,000 shares Start time: 12:30 End time 4:00 Please enter your order sizes at the end of each hour 10:30 11:30 12:30 1:30 2:30 3:30 Close:
Adams Company’s cost and production data for two recent months included the following: March April Production...
Adams Company’s cost and production data for two recent months included the following: March April Production (units) 300 600 Rent $ 1,700 $ 1,700 Utilities $ 400 $ 800 Required Separately calculate the rental cost per unit and the utilities cost per unit for both March and April. Identify which cost is variable and which is fixed. Separately calculate the rental cost per unit and the utilities cost per unit for both March and April. (Round your answers to 2...
Graphing Mixed Cost During a recent six-month period, Wade Corporation had the following monthly production volume...
Graphing Mixed Cost During a recent six-month period, Wade Corporation had the following monthly production volume and total monthly maintenance expense: Units Produced Maintenance Expense March ...................................................21,000 140,000 April ....................................................15,000 112,000 May.....................................................30,000 184,000 June ....................................................27,000 172,000 July .....................................................35,000 208,000 August ..................................................25,000 160,000 Required Assume that all volumes are in the relevant range. a . Explain why the data indicate that the maintenance expense is neither a fixed nor a variable expense. b . Construct a scattergraph and plot the maintenance...
Fromme's Frocks has the following machine hours and production costs for the last six months of...
Fromme's Frocks has the following machine hours and production costs for the last six months of last year: Month Machine Hours Production Cost July 15,000 $12,075 August 13,500 10,800 September 11,500 9,580 October 15,500 12,080 November 14,800 11,692 December 12,100 9,922 If Fromme expects to incur 14,000 machine hours in January, what will be the estimated total production cost using the high-low method?
Fromme's Frocks has the following machine hours and production costs for the last six months of...
Fromme's Frocks has the following machine hours and production costs for the last six months of last year: Month Machine Hours Production Cost July 16,600 $ 12,155 August 15,100 12,400 September 13,100 9,740 October 17,100 12,240 November 16,400 11,772 December 13,700 9,970 If Fromme expects to incur 12,200 machine hours in January, what will be the estimated total production cost using the high-low method? $8,732.63. $9,177.50. $7,625.00. $19,865.00.
(1) Fromme's Frocks has the following machine hours and production costs for the last six months...
(1) Fromme's Frocks has the following machine hours and production costs for the last six months of last year: Month Machine Hours Production Cost July 17,000 $ 12,175 August 15,500 12,800 September 13,500 9,820 October 17,500 12,280 November 16,800 11,792 December 14,100 9,982 If Fromme expects to incur 12,600 machine hours in January, what will be the estimated total production cost using the high-low method? (A) $20,029.00. (B) $8,841.60. (C) $7,749.00. (D) $9,266.50. (3) Case (A) Case (B) Case (C)...
Board? Games, Inc. makes board games. The following data pertains to the last six? months:            ...
Board? Games, Inc. makes board games. The following data pertains to the last six? months:             Direct Labor Hours                     Manufacturing Overhead Month 1: ?45,000                                      $295,000 Month 2: ?60,000 ?$320,000 Month 3: ?57,000 ?                                    $323,000 Month 4: ?52,000    ?$247,250 Month 5: ?34,000                                   ?$178,200 Month 6: ?25,000    ?$162,500 Based on this? data, what would the estimated manufacturing overhead be at a level of? 48,000 direct labor? hours?
A company is planning its production schedule over the next six months (it is currently the...
A company is planning its production schedule over the next six months (it is currently the end of month 2). The demand (in units) for its product over that timescale is as shown below: Month 3 4 5 6 7 8 Demand 5000 6000 6500 7000 8000 9500 The company currently has in stock: 1000 units which were produced in month 2; 2000 units which were produced in month 1; 500 units which were produced in month 0. The company...
Work in Process Account Data for Two Months; Cost of Production Reports Pittsburgh Aluminum Company uses...
Work in Process Account Data for Two Months; Cost of Production Reports Pittsburgh Aluminum Company uses a process cost system to record the costs of manufacturing rolled aluminum, which consists of the smelting and rolling processes. Materials are entered from smelting at the beginning of the rolling process. The inventory of Work in Process—Rolling on September 1 and debits to the account during September were as follows: Bal., 400 units, 30% completed: Direct materials (400 x $3.1)$ 1,240 Conversion (400...
Work in Process Account Data for Two Months; Cost of Production Reports Pittsburgh Aluminum Company uses...
Work in Process Account Data for Two Months; Cost of Production Reports Pittsburgh Aluminum Company uses a process cost system to record the costs of manufacturing rolled aluminum, which consists of the smelting and rolling processes. Materials are entered from smelting at the beginning of the rolling process. The inventory of Work in Process—Rolling on September 1 and debits to the account during September were as follows: Bal., 600 units, 30% completed: Direct materials (600 x $7.2) $ 4,320 Conversion...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT