In: Accounting
The high low method is used to estimate the fixed and variable costs by comparing the relationship of the Highest and Lowest value of costs to the highest and lowest value of units (machine hours in this case).
Variable Cost per unit can be calculated using the formulae:
Highest Cost = $ 12,080
Lowest Cost = $ 9,580
Highest Units = 15,500 machine hours
Lowes Units = 11,500 machine hours
Therefore,
Variable Cost per unit = (12,080 - 9,580) / (15,500 - 11,500)
= $ 0.625 per unit
We can calculate fixed cost using the formulae:
= 12,080 - (15,500 x 0.625)
=12080 - 9,688
Fixed Cost = $ 2,392 per months
At expected 14,000 machine hours
Estimated Total Production Cost = Fixed Cost + (Estimated units x variable cost per unit)
= 2,392 + (14,000 x 0.625)
= 2392 + 8750
=$ 11,142
Therefore the estimated total production cost using high low method is $ 11,142