Question

In: Operations Management

A company is planning its production schedule over the next six months (it is currently the...

A company is planning its production schedule over the next six months (it is currently the end of month 2). The demand (in units) for its product over that timescale is as shown below:

Month              3        4       5       6        7       8
Demand             5000     6000    6500    7000     8000    9500

The company currently has in stock: 1000 units which were produced in month 2; 2000 units which were produced in month 1; 500 units which were produced in month 0.

The company can only produce up to 6000 units per month and the managing director has stated that stocks must be built up to help meet demand in months 5, 6, 7 and 8. Each unit produced costs £15 and the cost of holding stock is estimated to be £0.75 per unit per month (based upon the stock held at the beginning of each month).

The company has a major problem with deterioration of stock in that the stock inspection which takes place at the end of each month regularly identifies ruined stock (costing the company £25 per unit). It is estimated that, on average, the stock inspection at the end of month t will show that 11% of the units in stock which were produced in month t are ruined; 47% of the units in stock which were produced in month t-1 are ruined; 100% of the units in stock which were produced in month t-2 are ruined. The stock inspection for month 2 is just about to take place.

The company wants a production plan for the next six months that avoids stockouts. Formulate their problem as a linear program.

Because of the stock deterioration problem the managing director is thinking of directing that customers should always be supplied with the oldest stock available. How would this affect your formulation of the problem?

Solution

Variables

Let

Pt be the production (units) in month t (t=3,...,8)

Iit be the number of units in stock at the end of month t which were produced in month i (i=t,t-1,t-2)

Sit be the number of units in stock at the beginning of month t which were produced in month i (i=t-1,t-2)

dit be the demand in month t met from units produced in month i (i=t,t-1,t-2)

Constraints

production limit

Pt <= 6000

initial stock position

I22 = 1000

I12 = 2000

I02 = 500

relate opening stock in month t to closing stock in previous months

St-1,t = 0.89It-1,t-1

St-2,t = 0.53It-2,t-1

inventory continuity equation where we assume we can meet demand in month t from production in month t. Let Dt represent the (known) demand for the product in month t (t=3,4,...,8) then

closing stock = opening stock + production - demand

and we have

It,t = 0 + Pt - dt,t

It-1,t = St-1,t + 0 - dt-1,t

It-2,t = St-2,t + 0 - dt-2,t

where

dt,t + dt-1,t + dt-2,t = Dt

no stockouts

all inventory (I,S) and d variables >= 0

Objective

Presumably to minimise cost and this is given by

SUM{t=3 to 8}15Pt + SUM{t=3 to 9}0.75(St-1,t+St-2,t) + SUM{t=3 to 8}25(0.11It,t+0.47It-1,t+1.0It-2,t)

Solve using Solver in Excel or GAMS.

Solutions

Expert Solution

In stock

Month 0 = 500 units

Month 1 = 2000 units

Month 2 = 1000 units

Now given the information that stock inspection will happen at the end of month t, we know that 11% of 1000 units will be ruined, 47% of 2000 units will be ruined and all 500 units from month 0 will be ruined.

Hence at the beginning of month 3 we shall have 890 + 1060 = 1950 units.

Now if we use this information on the spreadsheet it should look like the picture shown below.

Stock leftover is the number of units that remains after production and previous stock has been used to satisfy demand for the month.

Stock ruined is calculated by adding 0% from t-2, 47% from t-1 and 11% from t

Stock remaining is calculated by subtracting stock ruined from summation of month t, t-1, and t-2

Unit required is calculated by subtracting stock remaining for month t-1 from demand for month t

Units produced are the decision variables

The costs (production cost, holding cost and ruined stock cost) are calculated by multiplying their cost against number of units.

Finally on excel we setup a few constraints,

Units produced must be less than or equal to 6000

Units produced must be an integer

Stock leftovers must be greater than or equal to 0 (no stock out)

Once this is setup, use the solver to find the decision variables and minimize the cost. The screeshots are shown below.


Related Solutions

XYZ Enterprises needs to schedule operations for the next six months. Create a Master Schedule including...
XYZ Enterprises needs to schedule operations for the next six months. Create a Master Schedule including calculating Available-to-Promise (ATP) Inventory for each time period in the scheduling horizon using the following information: Beginning Inventory of 60 units; Forecasted Demand of 40 units per period; Standard Production Quantity of 50 units, and confirmed Customer Orders of 42 units for Month 1, 35 units for Month 2, 10 units for Month 3, and 5 units for Month 4.
The PROCOM Corporation is planning its financing for the next six months. PROCOM makes one item,...
The PROCOM Corporation is planning its financing for the next six months. PROCOM makes one item, which it sells through the retail shop in the front of the factory. The planning process was started with profit-and loss computations. Profit is revenue less expenses and revenue is quantity times the unit price. Expenses are made up fixed costs and variable costs. Fixed costs include: rent, salaries, and utilities. Variable costs depend directly on the quantity. These costs are materials and labor....
Abc inc. is planning the production schedule for the next 8 weeks. the forecasted demand for...
Abc inc. is planning the production schedule for the next 8 weeks. the forecasted demand for the next 8 weeks is 700, 800, 900, 500, 1100, 1000, 800, and 900 respectively. abc can produce 800 units per week in regular time and 200 more in overtime. the regular time production cost is $10.00 per unit which takes into account $4.00 for materials, $1.00 for utilities, and $5.00 for manpower. the manpower cost for overtime is twice the regular rate. holding...
Aggregate Planning Given the projected demands for the next six months, prepare an aggregate plan that...
Aggregate Planning Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time, overtime, subcontract and backorders. Regular time is limited to 150 units per month (Cost per Unit = $20 ). Overtime is limited to a maximum of 30 units per month (Cost per Unit =$30). Units purchased from the subcontractor (Cost per Unit = $26 ) cannot exceed 40 per month and the total purchases from the subcontractor over the 6...
A manufacturer of integrated circuits is planning production for the next four months. The forecast demand...
A manufacturer of integrated circuits is planning production for the next four months. The forecast demand for the circuits is shown in the following table. Circuit September October November December IC341 650 875 790 1100 IC256 900 350 1200 1300 At the beginning of September, the warehouse is expected to be completely empty. There is room for no more than 1,800 integrated circuits to be stored. Holding costs for both types is $0.05 per unit per month. Because workers are...
Question 4 (25 marks):In the planning of the monthly production for the next four months, in...
Question 4 :In the planning of the monthly production for the next four months, in each month a company must operate either a normal shift or an extended shift (but not both) if it produces. It may choose not to produce in a month. A normal shift costs $100,000 per month and can produce up to 5,000 units per month. An extended shift costs $140,000 per month and can produce up to 7,500 units per month. The cost of holding...
The current price of a non-dividend-paying stock is $30. Over the next six months it is...
The current price of a non-dividend-paying stock is $30. Over the next six months it is expected to rise to $36 or fall to $28. Assume the risk-free rate is 10% per annum (continuously compounded). What, to the nearest cent, is the price of an American put option with a strike price of $33? (Your answer should be in the unit of dollar, but without the dollar sign. For example, if your answer is $1.02, just enter 1.02.)
The current price of a non-dividend-paying stock is $30. Over the next six months it is...
The current price of a non-dividend-paying stock is $30. Over the next six months it is expected to rise to $36 or fall to $28. Assume the risk-free rate is 10% per annum. What, to the nearest cent, is the price of a European put option with a strike price of $33? (Your answer should be in the unit of dollar, but without the dollar sign. For example, if your answer is $1.02, just enter 1.02.)
The current price of a non-dividend-paying stock is $50. Over the next six months it is...
The current price of a non-dividend-paying stock is $50. Over the next six months it is expected to rise to $60 or fall to $48. Assume the risk-free rate is zero. An investor sells call options with a strike price of $55. What is the value of each call option according to the one-step binomial model? Please enter your answer as a number rounded to two decimal places (with no dollar sign).
A stock is currently at $30. Over each of the next two three-months periods, the stock...
A stock is currently at $30. Over each of the next two three-months periods, the stock may move up to a factor 1.20 or down by a factor of 0.80 each period. A call option with strike price of $32 and maturity of six months is available. The current risk-free rate is 4% per year. Is the call option in the money, at money, or out of money. Explain. Find the value of this call option using the binomial tree...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT