Question

In: Accounting

35-38 Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z....

35-38

Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $829,500 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:

Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity
Machining Machine-hours $ 246,000 12,000 MHs
Machine setups Number of setups $ 137,500 250 setups
Product design Number of products $ 89,000 2 products
General factory Direct labor-hours $ 357,000 14,400 DLHs
Activity Measure Product Y Product Z
Machine-hours 7,500 4,500
Number of setups 40 210
Number of products 1 1
Direct labor-hours 8,500 5,900

5. What is the activity rate for the Product Design activity cost pool?

6. What is the activity rate for the General Factory activity cost pool?

7. Which of the four activities is a batch-level activity?

  • Machine setups activity

  • Machining activity

  • Product design activity

  • General factory activity

  • 8. Which of the four activities is a product-level activity?

  • Product design activity

  • Machining activity

  • Machine setups activity

  • General factory activity

Solutions

Expert Solution

(5) activity rate for the Product Design activity cost pool

Activity cost pool Product design
Activity Measure Number of product
Estimated overhead cost (a) $ 89000
Expected Activity (b) 2 product
activity rate for the Product Design activity cost pool (a)/(b) $ 44500 per product

(6)  activity rate for the General Factory activity cost pool

Activity cost pool General Factory
Activity Measure Direct labor hour
Estimated overhead cost (a) $ 357000
Expected Activity (b) 14400 Direct labor hour
activity rate for the Product Design activity cost pool (a)/(b) $ 24.79 ( Approx to 2 decimal place)

7. Which of the four activities is a batch-level activity?

Answer - Machine setups activity

Explanation

Batch level activity will apply whenever a batch is produced. Batch level activity will include Machine set up,

Quality testing and purchase order.

8. Which of the four activities is a product-level activity?

Answer : Product design activity

Explanation

Product level activity connected to specific product and it is not related to Batch or unit of product .It will include Design a product ,advertising a product.


Related Solutions

Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool   Activity Measure   Estimated Overhead Cost   Expected Activity Machining   Machine-hours   $   242,400   12,000   MHs...
Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $813,600 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 249,600 12,000...
Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $630,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 228,000 12,000...
Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $813,600 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 249,600 12,000...
39-42 Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z....
39-42 Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $829,500 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 246,000...
Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company...
Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $788,400 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 238,800 12,000 MHs...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 231,600 12,000 MHs...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 231,600 12,000 MHs...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:    Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity   Machining Machine-hours $ 249,600   ...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 231,600 12,000 MHs...