Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:
Activity Cost Pool | Activity Measure | Estimated Overhead Cost | Expected Activity |
||||
Machining | Machine-hours | $ | 231,600 | 12,000 | MHs | ||
Machine setups | Number of setups | $ | 55,900 | 130 | setups | ||
Production design | Number of products | $ | 77,000 | 2 | products | ||
General factory | Direct labor-hours | $ | 364,500 | 15,000 | DLHs | ||
Activity Measure | Product Y | Product Z | ||||
Machining | 7,300 | 4,700 | ||||
Number of setups | 40 | 90 | ||||
Number of products | 1 | 1 | ||||
Direct labor-hours | 7,300 | 7,700 | ||||
9. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y? (Round your intermediate calculations to 2 decimal places. Round your answers to the nearest dollar amount.)
Activity cost pool | Activity Measure | Estimated Overhead Cost | Expected Activity |
Predetermined overhead rate [ Estimated overhead cost / Expected activity ] |
Machining | Machine-hours | $231,600 | 12,000 MHs | $19.3 per MH |
Machine setups | Number of setups | $55,900 | 130 setups | $430 per setup |
Production design | Number of products | $77,000 | 2 products | $38,500 per product |
General factory | Direct labor-hours | $364,500 | 15,000 DLHs | $24.3 per DLH |
Let us now calculate the total manufacturing overhead cost that would be assigned using the Activity Based Costing (ABC) system to Product Y :
Activity cost pool | Activity measure |
Expected activity of product Y (A) |
Predetermined overhead rate (B) |
Manufacturing overhead cost assigned to product Y ( A * B ) |
Machining | Machine-hours | 7,300 MHs | $19.3 per MH | $140,890 |
Machine setups | Number of setups | 40 setups | $430 per setup | $17,200 |
Production design | Number of products | 1 product | $38,500 per product | $38,500 |
General factory | Direct labor-hours | 7,300 DLHs | $24.3 per DLH | $177,390 |
Total | $373,980 |