In: Accounting
QUESTION 1:
Davie's Hotel budgeted 800 room sales for the week ended June 24th. The estimated average price per room was $18.50. The actual average price per room was 10 percent greater than anticipated, while room sales in units were 10 percent less than forecasted.
Complete the following table for the Hotel’s revenue variance analysis.
Rooms |
Rate |
Total |
|
Budget |
800 |
$18.50 |
|
Actual |
|||
Difference |
A) Calculate the budget variance.
B) Calculate the price variance.
C) Calculate the volume variance.
D) Calculate the price-volume variance.
Correct Answer:
Rooms |
Rate |
Total |
|
Budget |
800 |
$ 18.50 |
$ 14,800 |
Actual |
720 |
$ 20.35 |
$ 14,652 |
Difference |
80 |
$ (1.85) |
$ (148) |
Material Price Variance |
$ 1,332.00 |
Unfavourable-U |
Material quantity variance |
$ 1,480.00 |
Favourable-F |
Material Spending Variance |
$ 148.00 |
Favourable-F |
Working:
Standard DATA for |
800 |
Rooms |
|
Quantity (SQ) |
Rate (SR) |
Standard Cost |
|
Rooms used |
800 |
$ 18.50 |
$ 14,800 |
Actual DATA for |
800 |
Units |
|
Quantity (AQ) |
Rate (AR) |
Actual Cost |
|
Rooms used |
720 |
$ 20.35 |
$ 14,652 |
Material Price Variance |
||||||
( |
Standard Rate |
- |
Actual Rate |
) |
x |
Actual Quantity |
( |
$ 18.50 |
- |
$ 20.35 |
) |
x |
720 |
-1332 |
||||||
Variance |
$ 1,332.00 |
Unfavourable-U |
||||
Material Quantity Variance |
||||||
( |
Standard Quantity |
- |
Actual Quantity |
) |
x |
Standard Rate |
( |
800 |
- |
720 |
) |
x |
$ 18.50 |
1480 |
||||||
Variance |
$ 1,480.00 |
Favourable-F |
||||
Material volume Variance |
||||||
( |
Standard Cost |
- |
Actual Cost |
) |
||
( |
$ 14,800.00 |
- |
$ 14,652.00 |
) |
||
148 |
||||||
Variance |
$ 148.00 |
Favourable-F |
||||
End of Answer.
Thanks