Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...

Budget Performance Reports for Cost Centers

Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow:

Garland Company
Budget Performance Report—Vice President, Production
For the Month Ended November 30
Plant Actual Budget Over Budget Under Budget
Eastern Region $389,000 $389,000 $0
Central Region 280,100 277,300 $2,800
Western Region (g) (h) (i)
$(j) $(k) $(l) $3,120


Garland Company
Budget Performance Report—Manager, Western Region Plant
For the Month Ended November 30
Department Actual Budget Over Budget Under Budget
Chip Fabrication $(a) $(b) $(c)
Electronic Assembly 76,420 77,410 990
Final Assembly 121,510 120,540 $970
$(d) $(e) $(f) $4,090


Garland Company
Budget Performance Report—Supervisor, Chip Fabrication
For the Month Ended November 30
Cost Actual Budget Over Budget Under Budget
Factory wages $30,740 $32,890 $2,150
Materials 71,790 71,290 $500
Power and light 4,250 5,060 810
Maintenance 6,690 7,330 640
$113,470 $116,570 $500 $3,600

a. Complete the budget performance reports by determining the correct amounts for the lettered spaces (a-l) as marked above.

a. $ g. $
b. $ h. $
c. $ i. $
d. $ j. $
e. $ k. $
f. $ l. $

b. The budget for the Chip Fabrication Department indicates that the budget overrun was caused by a combination of budget   in factory wages, power and light, and maintenance that exceeded a budget   in materials.

Solutions

Expert Solution


Related Solutions

Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Actual Budget Over Budget Under Budget Eastern Region $495,600 $495,600 $0 Central Region 356,800 353,200 $3,600 Western Region (g) (h) (i) $(j) $(k) $(l) $3,140 Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Actual Budget Over Budget Under...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Budget Actual Over Budget Under Budget Eastern Region $530,900 $530,900 $0 Central Region 382,200 378,400 (3,800) Western Region (g) (h) (i) $(j) $(k) $(l) $(3,800) Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Budget Actual Over Budget Under...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Actual Budget Over Budget Under Budget Eastern Region $409,200 $409,200 $0 Central Region 294,600 291,700 $2,900 Western Region (g) (h) (i) $(j) $(k) $(l) $3,220 Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Actual Budget Over Budget Under...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Actual Budget Over Budget Under Budget Eastern Region $549,800 $549,800 $0 Central Region 395,900 391,900 4,000 Western Region (g) (h) (i) $(j) $(k) $(l) $3,170 Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Actual Budget Over Budget Under...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Budget Actual Over Budget Under Budget Eastern Region $447,400 $447,400 $0 Central Region 322,100 318,900 (3,200) Western Region (g) (h) (i) $(j) $(k) $(l) $(3,200) Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Budget Actual Over Budget Under...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Actual Budget Over Budget Under Budget Eastern Region $460,300 $460,300 $0 Central Region 331,400 328,100 3,300 Western Region (g) (h) (i) $(j) $(k) $(l) $3,200 Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Actual Budget Over Budget Under...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Budget Actual Over Budget Under Budget Eastern Region $349,500 $349,500 $0 Central Region 251,600 249,100 (2,500) Western Region (g) (h) (i) $(j) $(k) $(l) $(2,500) Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Budget Actual Over Budget Under...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Delmar Company, a manufacturer...
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Delmar Company, a manufacturer of light duty motors, follow: Delmar Company Budget Performance Report—Vice President, Production For the Month Ended June 30 Plant Actual Budget Over Budget (Under) Budget Eastern Region $474,000 $474,000 $0 Central Region 337,900 341,300 (3,400) Western Region (g) (h) (i) $(j) $(k) $(l) $(3,400) Delmar Company Budget Performance Report—Manager, Western Region Plant For the Month Ended June 30 Department Actual Budget Over Budget (Under)...
Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland...
Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland COMPANY Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant   Actual   Budget   Over Budget   Under Budget Eastern Region   $930,150   $932,500       $(2,350) Central Region   665,200   668,400       (3,200) Western Region   (G)   (H)   $(I)   $(J)   $(K)   $(L)   $(5,550) Garland COMPANY Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department   Actual   Budget   Over Budget   Under Budget Chip Fabrication   (A)  ...
Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland...
Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland COMPANY Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Actual Budget Over Budget Under Budget Eastern Region $928,200 $930,500 $(2,300) Central Region 666,600 670,000 (3,400) Western Region (G) (H) (I) Total (J) (K) $(L) $(5,700) Garland COMPANY Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Actual Budget Over Budget Under Budget Chip Fabrication (A) (B)...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT