Question

In: Accounting

Flounder Furniture Company started construction of a combination office and warehouse building for its own use...

Flounder Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $3,000,000 on January 1, 2020. Flounder expected to complete the building by December 31, 2020. Flounder has the following debt obligations outstanding during the construction period.

Construction loan-12% interest, payable semiannually, issued December 31, 2019 $1,200,000
Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 840,000
Long-term loan-11% interest, payable on January 1 of each year. Principal payable on January 1, 2024 600,000

New attempt is in progress. Some of the new entries may impact the last attempt grading.Your answer is incorrect.

Assume that Flounder completed the office and warehouse building on December 31, 2020, as planned at a total cost of $3,120,000, and the weighted-average amount of accumulated expenditures was $2,160,000. Compute the avoidable interest on this project. (Use interest rates rounded to 2 decimal places, e.g. 7.58% for computational purposes and round final answers to 0 decimal places, e.g. 5,275.)

Avoidable Interest

Compute the depreciation expense for the year ended December 31, 2021. Flounder elected to depreciate the building on a straight-line basis and determined that the asset has a useful life of 30 years and a salvage value of $180,000. (Round answer to 0 decimal places, e.g. 5,275.)

Depreciation Expense

Solutions

Expert Solution

Answer a.

Avoidable interest $244,032

Explanation:

Weighted Average Rate for non-specific loans

Type Amount Rate Interest
Short-term loan $840,000 10% $84,000
Long-term loan $600,000 11% $66,000
Total $1,440,000 $150,000

Weighted Average Rate = $150,000 / $1,440,000 = 10.42 %

Calculation of avoidable interest

Amount Rate Avoidable interest
Construction loan $1,200,000 12% $144,000
Balance loan using Weighted Average Rate $960,000 10.42 % $100,032
Weighted-average amount of accumulated expenditures (given) $2,160,000 $244,032

Answer b.

Depreciation Expense $106,134

Explanation:

Type Actual Interest amount
Construction loan ($1,200,000 * 12%) $144,000
Short-term loan ($840,000 * 10%) $84,000
Long-term loan ($600,000 * 11%) $66,000
Total actual interest $294,000

Since total actual interest incurred is more than the avoidable interest, interest amount to be capitalize = Avoidable interest = $244,032

Total building cost = Cost + Avoidable interest = $3,120,000 + $244,032 = $3,364,032

Depreciation Expense = (Total building cost - Salvage value) / Useful life

= ($3,364,032 - $180,000) / 30 years = $106,134


Related Solutions

The Furniture Company started construction of a combination office and warehouse building for its own use...
The Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $14,500,000 on January 1, 2020. The Furniture Company expected to complete the building by December 31, 2020. The Furniture Company has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $5,800,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 4,060,000 Long-term loan-11% interest, payable...
Nash Furniture Company started construction of a combination office and warehouse building for its own use...
Nash Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $ 4,953,300 on January 1, 2017. Nash expected to complete the building by December 31, 2017. Nash has the following debt obligations outstanding during the construction period. Construction loan- 12% interest, payable semiannually, issued December 31, 2016 $2,015,500 Short-term loan- 10% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,609,200 Long-term loan- 11% interest, payable...
Grouper Furniture Company started construction of a combination office and warehouse building for its own use...
Grouper Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $5,024,000 on January 1, 2017. Grouper expected to complete the building by December 31, 2017. Grouper has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2016 $1,990,600 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,603,500 Long-term loan-11% interest, payable on January 1 of...
Riverbed Furniture Company started construction of a combination office and warehouse building for its own use...
Riverbed Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $3,000,000 on January 1, 2020. Riverbed expected to complete the building by December 31, 2020. Riverbed has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $1,200,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 840,000 Long-term loan-11% interest, payable on January 1 of...
Bramble Furniture Company started construction of a combination office and warehouse building for its own use...
Bramble Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $2,500,000 on January 1, 2020. Bramble expected to complete the building by December 31, 2020. Bramble has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $1,000,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 700,000 Long-term loan-11% interest, payable on January 1 of...
Nash Furniture Company started construction of a combination office and warehouse building for its own use...
Nash Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,600,000 on January 1, 2021. Nash expected to complete the building by December 31, 2021. Nash has the following debt obligations outstanding during the construction period. Construction loan—10% interest, payable semi-annually, issued December 31, 2020, maturity on December 31, 2030 $2,096,000 Short-term loan—8% interest, payable monthly, and principal payable at maturity on May 30, 2022 1,422,000 Long-term loan—9% interest,...
Skysong Furniture Company started construction of a combination office and warehouse building for its own use...
Skysong Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,981,900 on January 1, 2017. Skysong expected to complete the building by December 31, 2017. Skysong has the following debt obligations outstanding during the construction period. Construction loan-10% interest, payable semiannually, issued December 31, 2016 $2,000,100 Short-term loan-8% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,595,800 Long-term loan-9% interest, payable on January 1 of...
Pronghorn Furniture Company started construction of a combination office and warehouse building for its own use...
Pronghorn Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,978,200 on January 1, 2017. Pronghorn expected to complete the building by December 31, 2017. Pronghorn has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2016 $2,012,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,615,200 Long-term loan-11% interest, payable on January 1 of...
Culver Furniture Company started construction of a combination office and warehouse building for its own use...
Culver Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $6,000,000 on January 1, 2020. Culver expected to complete the building by December 31, 2020. Culver has the following debt obligations outstanding during the construction period. Construction loan-14% interest, payable semiannually, issued December 31, 2019 $2,400,000 Short-term loan-12% interest, payable monthly, and principal payable at maturity on May 30, 2021 1,680,000 Long-term loan-13% interest, payable on January 1 of...
Pearl Furniture Company started construction of a combination office and warehouse building for its own use...
Pearl Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,981,900 on January 1, 2017. Pearl expected to complete the building by December 31, 2017. Pearl has the following debt obligations outstanding during the construction period. Construction loan-10% interest, payable semiannually, issued December 31, 2016 $2,000,100 Short-term loan-8% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,595,800 Long-term loan-9% interest, payable on January 1 of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT