Question

In: Accounting

Cornwell Construction Company has been operating in Pennsylvania for a Cornwell Construction Company has been operating...

Cornwell Construction Company has been operating in Pennsylvania for a
Cornwell Construction Company has been operating in Pennsylvania for a number of years. During 2019, the firm contracted with the Borough of Lewisburg to build a domed sports complex. Cornwell estimated that it would take three years to complete the facility at a total cost of $25 million. The total contract price was $30 million. During 2019, construction costs of $8 million were incurred related to the sports complex; estimated additional costs to complete the project were $16 million as of December 31, 2019. Contract billings through December 31, 2019, were $9 millions of which the Borough of Lewisburg had paid $7.5 million

1. Determine the amount of revenue and income to be recognized by Cornwell Construction on the sports complex for the year ended December 31, 2019, assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its performance obligation has been satisfied.

2. Determine the amount of revenue and income to be recognized by Cornwell Construction on the sports complex for the year ended December 31, 2019, assuming it recognizes revenue at a point in time when control of the completed complex is transferred to the Borough of Lewisburg

3. How should Cromwell determine which of the two approaches is appropriate?

Solutions

Expert Solution

1) As the company recognizes revenue over time and uses costs incurred to measure the extent to which its performance obligation has been satisfied, it means that the company uses percentage completion method for recognizing revenue over contract period.

First of all, we need to calculate the percentage of completion during the year ended December 31, 2019 which is calculated as follows:-

Percentage of completion = (Cost incurred during 2019/Total estimated cost)*100

Cost incurred during 2019 = $8 million

Additional cost estimated to incurred during contract period = $16 million

Total Estimated cost for the contract = Cost incurred during 2019+Additional cost estimated

= $8 million+$16 million = $24 million

Percentage of completion = ($8 million/$24 million)*100 = 33.33% (or 1/3)

Revenue to be recognized during 2019 should be 1/3rd of total contract price

Revenue recognized in 2019 = 1/3 of $30 million = $10 million

Income to be recognized in 2019 = Revenue recognized - Cost incurred

Income to be recognized in 2019 = $10 million - $8 million = $2

2) As the company recognizes revenue at a point in time when control of the completed complex is transferred to the Borough of Lewisburg, it means that the company uses completed contract method for recognizing revenue.

Under completed contract method, revenue is recognized when contract is completed. Therefore no revenue and income will be recognized for the year ended December 31, 2019 as contract is not completed.

3) According to Matching principle of accounting, expenses are to be recognized in income statement in the same period as the related revenues. As the expenses on construction are incurred during the whole contract period, its related revenue should also be recognized over the contract period according to percentage completion method to provide a true and fair view of financial statements.

Therefore, the first approach adopted by the Cromwell is appropriate (i.e. percentage completion method).


Related Solutions

Express Chemical Company is a publicly traded company that has been operating at a profit for...
Express Chemical Company is a publicly traded company that has been operating at a profit for years. Its officers (all of whom are stockholders) are concerned about the prospects of the company. Customers and employees claiming that toxic chemicals produced by the company caused their health problems have sued many similar firms. Lawsuits have yet been filed against Express, but the officers fully expect them to be filed within the next two years. The officers hold 70% of the stock...
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska....
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska. The project timeline is of the highest priority because work can only be completed during summer months due to adverse weather conditions. One of the suppliers of a key component has longer lead time than is required to complete the pipeline, but may be able to deliver if the construction company will pay fees to expedite. There are other suppliers, but these suppliers are...
A construction company has entered into a contract to build a parking complex. It hsa been...
A construction company has entered into a contract to build a parking complex. It hsa been estimated the complex will cost 700,000 and will take three years to construct. The complex will be billed to the purchasing company at 1,200,000. Information is as follows. X1 YEAR. X2 YEAR X3 YEAR cost incurrect to date 350,000 490,000 700,000 estimated cost yet to be incurrect 350,000. 210,000. 0 customer billings to date 300,000. 650,000 1,200,000 collections of billings to date 250,000. 600,000....
Wangy & Company are a construction and real estate company incorporated and operating in Zambia. They...
Wangy & Company are a construction and real estate company incorporated and operating in Zambia. They have been in this business for 15 years and are considering venturing into the Mauritian market. They have approached you for advice. Required: Advise Wangy and Company on the particular risks they may be faced with if they decided to start doing business overseas. (b) Suggest why a private company might go public. (Wangy & Company are a construction and real estate company incorporated...
A building company has been awarded the contract to undertake the construction works for a multi-storey...
A building company has been awarded the contract to undertake the construction works for a multi-storey office project in a city centre location. A deep basement is to be installed under one half of the building, within a layer of dense gravel. The site is surrounded by public roads and buildings on all sides and it is expected that the water table is extremely close to the ground surface on a year-round basis. You have been asked by the contractor...
Olney Company is a small manufacturing firm located in Allentown, Pennsylvania. The company has a workforce...
Olney Company is a small manufacturing firm located in Allentown, Pennsylvania. The company has a workforce of both hourly and salaried employees. Each employee is paid for hours actually worked during each week, with the time worked being recorded in quarter-hour increments. The standard workweek consists of 40 hours, with all employees being paid time and one-half for any hours worked beyond the 40 regular hours.    Wages are paid every Friday, with one week’s pay being held back by the...
Kipley Company is a small manufacturing firm located in Pittsburgh, Pennsylvania. The company has a workforce...
Kipley Company is a small manufacturing firm located in Pittsburgh, Pennsylvania. The company has a workforce of both hourly and salaried employees. Each employee is paid for hours actually worked during each week, with the time worked being recorded in quarter-hour increments. The standard workweek consists of 40 hours, with all employees being paid time and one-half for any hours worked beyond the 40 regular hours. Wages are paid every Friday, with one week’s pay being held back by the...
Kipley Company is a small manufacturing firm located in Pittsburgh, Pennsylvania. The company has a workforce...
Kipley Company is a small manufacturing firm located in Pittsburgh, Pennsylvania. The company has a workforce of both hourly and salaried employees. Each employee is paid for hours actually worked during each week, with the time worked being recorded in quarter-hour increments. The standard workweek consists of 40 hours, with all employees being paid time and one-half for any hours worked beyond the 40 regular hours. Wages are paid every Friday, with one week's pay being held back by the...
Wildhorse Company has other operating expenses of $338400. There has been a decrease in prepaid expenses...
Wildhorse Company has other operating expenses of $338400. There has been a decrease in prepaid expenses of $15000 during the year, and accrued liabilities are $22600 larger than in the prior period. Using the direct method of reporting cash flows from operating activities, what were Wildhorse's cash payments for operating expenses?
Amanda Ltd is a manufacturing company operating in Parramatta, Sydney. The company has been successful since...
Amanda Ltd is a manufacturing company operating in Parramatta, Sydney. The company has been successful since its inception in the early 1990 and has even won twice the “Best Corporate Citizen Award” presented by the City of Parramatta Council. The company has recently been facing multiple problems including declining profit, loss of inventory (through theft or spoilage) in the warehouse, and declining reputation from its stakeholders. Coincidently, all these problems started when the head of Accounting Department, Sofia Bryant, voluntarily...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT