Question

In: Finance

You are evaluating a project which has a useful life of 5 years.  However, you suspect that...

  1. You are evaluating a project which has a useful life of 5 years.  However, you suspect that the project’s economic life might be different.  The initial investment for the project is $5,000,000.  The cash flows for the 5 years are $5 million, $1.7 million, $1.8 million, $2 million, and $2 million.  The abandonment value of the project in each of the first 4 years is $4.2 million, $4 million, $3.5 million, and $2 million.   The abandonment value for the 5th year is incorporated into the cash flow given above.  The required rate for this project is 15%.
    1. What is the NPV of the project, assuming its useful life?
  1. Determine the economic life for the asset.
  1. What is the meaning of the result in b?

Solutions

Expert Solution

(a)

Particulars Cashflow PVF @ 15% Year 1 Year 2 Year 3 Year 4 Year 5
A Initial Investment ($5,000,000) 1 ($5,000,000) ($5,000,000) ($5,000,000) ($5,000,000) ($5,000,000)
PV of Cash Outflows
B Operational Cashinflows
Year 1 $   5,000,000 0.8696 $4,347,826 $4,347,826 $4,347,826 $4,347,826 $4,347,826
Year 2 $   1,700,000 0.7561 $ 1,285,444.23 $ 1,285,444.23 $ 1,285,444.23 $    1,285,444.23
Year 3 $   1,800,000 0.6575 $ 1,183,529.22 $ 1,183,529.22 $    1,183,529.22
Year 4 $   2,000,000 0.5718 $ 1,143,506.49 $    1,143,506.49
Year 5 $   2,000,000 0.4972 $        994,353.47
PV of Cashinflows $4,347,826 $5,633,270 $6,816,800 $7,960,306 $8,954,660
C Abandonment Value
Year 1 $   4,200,000 0.8696 $         3,652,173.91
Year 2 $   4,000,000 0.7561 $ 3,024,574.67
Year 3 $   3,500,000 0.6575 $ 2,301,306.81
Year 4 $   2,000,000 0.5718 $ 1,143,506.49
Year 5 $                  -   0.4972 $                        -    
PV of Terminal Cash Inflows $         3,652,173.91 $ 3,024,574.67 $ 2,301,306.81 $ 1,143,506.49 $                          -  
D NPV ((B+C)-A) $               3,000,000 $        3,657,845 $        4,118,106 $        4,103,813 $          3,954,660
E PVAF 0.8696 1.6257 2.2832 2.8550 3.3522
F Annualised NPV $               3,450,000 $        2,250,000 $        1,803,636 $        1,437,423 $          1,179,736

(b) As Annualised NPV of the aset is higher for Usage life of 1 Year, Economic life of th asset = 1Yeaarr.

(c) Economic Life means the time period with in which replacement of the asset is more benefecial.


Related Solutions

You are evaluating a project which has a useful life of 5 years. However, you suspect...
You are evaluating a project which has a useful life of 5 years. However, you suspect that the project’s economic life might be different. The initial investment for the project is $5,000,000. The cash flows for the 5 years are $1.5 million, $1.7 million, $1.8 million, $2 million, and $2 million. The abandonment value of the project in each of the first 4 years is $4.2 million, $4 million, $3.5 million, and $2 million.  The abandonment value for the 5th year...
We are evaluating a project that costs $650,000, has a life of 5 years, and has...
We are evaluating a project that costs $650,000, has a life of 5 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 45,000 units per year. Price per unit is $56, variable cost per unit is $26, and fixed costs are $860,000 per year. The tax rate is 21 percent and we require a return of 14 percent on this project. a. Calculate the accounting break-even...
We are evaluating a project that costs $690,000, has a life of 5 years, and has...
We are evaluating a project that costs $690,000, has a life of 5 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 51,000 units per year. Price per unit is $75, variable cost per unit is $50, and fixed costs are $790,000 per year. The tax rate is 25 percent and we require a return of 13 percent on this project. a. Calculate the accounting break-even...
We are evaluating a project that costs $660,000, has a life of 5 years, and has...
We are evaluating a project that costs $660,000, has a life of 5 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 58,000 units per year. Price per unit is $57, variable cost per unit is $38, and fixed costs are $660,000 per year. The tax rate is 22 percent and we require a return of 16 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $680,000, has a life of 5 years, and has...
We are evaluating a project that costs $680,000, has a life of 5 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 64,000 units per year. Price per unit is $43, variable cost per unit is $26, and fixed costs are $685,000 per year. The tax rate is 24 percent and we require a return of 14 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $670,000, has a life of 5 years, and has...
We are evaluating a project that costs $670,000, has a life of 5 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 59,000 units per year. Price per unit is $44, variable cost per unit is $24, and fixed costs are $760,000 per year. The tax rate is 23 percent and we require a return of 16 percent on this project. What is the sensitivity of...
We are evaluating a project that costs $670,000, has a life of 5 years, and has...
We are evaluating a project that costs $670,000, has a life of 5 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 59,000 units per year. Price per unit is $44, variable cost per unit is $25, and fixed costs are $760,000 per year. The tax rate is 23 percent, and we require a 16 percent return on this project. Suppose the projections given for the...
We are evaluating a project that costs $972,000, has a life of twelve years, and has...
We are evaluating a project that costs $972,000, has a life of twelve years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 117,000 units per year. Price per unit is $35, variable cost per unit is $25, and fixed costs are $989,496 per year. The tax rate is 22 percent, and we require a return of 21 percent on this project. The projections given for price,...
We are evaluating a project that costs $743,000, has a life of eight years, and has...
We are evaluating a project that costs $743,000, has a life of eight years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 124,000 units per year. Price per unit is $37, variable cost per unit is $20, and fixed costs are $749,687 per year. The tax rate is 22 percent, and we require a return of 21 percent on this project. The projections given for price,...
We are evaluating a project that costs $1,100,000, has a life of 10 years, and has...
We are evaluating a project that costs $1,100,000, has a life of 10 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 47,000 units per year. Price per unit is $50, variable cost per unit is $25, and fixed costs are $820,000 per year. The tax rate is 21 percent and we require a return of 16 percent on this project. Suppose the projections given for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT