Question

In: Finance

We are evaluating a project that costs $680,000, has a life of 5 years, and has...

We are evaluating a project that costs $680,000, has a life of 5 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 64,000 units per year. Price per unit is $43, variable cost per unit is $26, and fixed costs are $685,000 per year. The tax rate is 24 percent and we require a return of 14 percent on this project. Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within ±10 percent.

  

Calculate the best-case and worst-case NPV figures.

Solutions

Expert Solution

Best case NPV

Time line 0 1 2 3 4 5
Cost of new machine -680000
=Initial Investment outlay -680000
Unit sales 70400 70400 70400 70400 70400
Profits =no. of units sold * (sales price - variable cost) 1682560 1682560 1682560 1682560 1682560
Fixed cost -616500 -616500 -616500 -616500 -616500
-Depreciation Cost of equipment/no. of years -136000 -136000 -136000 -136000 -136000
=Pretax cash flows 930060 930060 930060 930060 930060
-taxes =(Pretax cash flows)*(1-tax) 706845.6 706845.6 706845.6 706845.6 706845.6
+Depreciation 136000 136000 136000 136000 136000
=after tax operating cash flow 842845.6 842845.6 842845.6 842845.6 842845.6
+Tax shield on salvage book value =Salvage value * tax rate 0
=Terminal year after tax cash flows 0
Total Cash flow for the period -680000 842845.6 842845.6 842845.6 842845.6 842845.6
Discount factor= (1+discount rate)^corresponding period 1 1.14 1.2996 1.481544 1.68896016 1.9254146
Discounted CF= Cashflow/discount factor -680000 739338.2456 648542.321 568896.773 499032.257 437747.59
NPV= Sum of discounted CF= 2213557.189

Worst case NPV

Time line 0 1 2 3 4 5
Cost of new machine -680000
=Initial Investment outlay -680000
Unit sales 57600 57600 57600 57600 57600
Profits =no. of units sold * (sales price - variable cost) 581760 581760 581760 581760 581760
Fixed cost -753500 -753500 -753500 -753500 -753500
-Depreciation Cost of equipment/no. of years -136000 -136000 -136000 -136000 -136000
=Pretax cash flows -307740 -307740 -307740 -307740 -307740
-taxes =(Pretax cash flows)*(1-tax) -233882.4 -233882.4 -233882.4 -233882.4 -233882.4
+Depreciation 136000 136000 136000 136000 136000
=after tax operating cash flow -97882.4 -97882.4 -97882.4 -97882.4 -97882.4
+Tax shield on salvage book value =Salvage value * tax rate 0
=Terminal year after tax cash flows 0
Total Cash flow for the period -680000 -97882.4 -97882.4 -97882.4 -97882.4 -97882.4
Discount factor= (1+discount rate)^corresponding period 1 1.14 1.2996 1.481544 1.68896016 1.9254146
Discounted CF= Cashflow/discount factor -680000 -85861.7544 -75317.328 -66067.832 -57954.239 -50837.05
NPV= Sum of discounted CF= -1016038.205

Related Solutions

We are evaluating a project that costs $680,000, has a five-year life, and has no salvage...
We are evaluating a project that costs $680,000, has a five-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 49,000 units per year. Price per unit is $46, variable cost per unit is $26, and fixed costs are $685,000 per year. The tax rate is 24 percent, and we require a return of 20 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $650,000, has a life of 5 years, and has...
We are evaluating a project that costs $650,000, has a life of 5 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 45,000 units per year. Price per unit is $56, variable cost per unit is $26, and fixed costs are $860,000 per year. The tax rate is 21 percent and we require a return of 14 percent on this project. a. Calculate the accounting break-even...
We are evaluating a project that costs $690,000, has a life of 5 years, and has...
We are evaluating a project that costs $690,000, has a life of 5 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 51,000 units per year. Price per unit is $75, variable cost per unit is $50, and fixed costs are $790,000 per year. The tax rate is 25 percent and we require a return of 13 percent on this project. a. Calculate the accounting break-even...
We are evaluating a project that costs $660,000, has a life of 5 years, and has...
We are evaluating a project that costs $660,000, has a life of 5 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 58,000 units per year. Price per unit is $57, variable cost per unit is $38, and fixed costs are $660,000 per year. The tax rate is 22 percent and we require a return of 16 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $670,000, has a life of 5 years, and has...
We are evaluating a project that costs $670,000, has a life of 5 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 59,000 units per year. Price per unit is $44, variable cost per unit is $24, and fixed costs are $760,000 per year. The tax rate is 23 percent and we require a return of 16 percent on this project. What is the sensitivity of...
We are evaluating a project that costs $670,000, has a life of 5 years, and has...
We are evaluating a project that costs $670,000, has a life of 5 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 59,000 units per year. Price per unit is $44, variable cost per unit is $25, and fixed costs are $760,000 per year. The tax rate is 23 percent, and we require a 16 percent return on this project. Suppose the projections given for the...
We are evaluating a project that costs $972,000, has a life of twelve years, and has...
We are evaluating a project that costs $972,000, has a life of twelve years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 117,000 units per year. Price per unit is $35, variable cost per unit is $25, and fixed costs are $989,496 per year. The tax rate is 22 percent, and we require a return of 21 percent on this project. The projections given for price,...
We are evaluating a project that costs $743,000, has a life of eight years, and has...
We are evaluating a project that costs $743,000, has a life of eight years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 124,000 units per year. Price per unit is $37, variable cost per unit is $20, and fixed costs are $749,687 per year. The tax rate is 22 percent, and we require a return of 21 percent on this project. The projections given for price,...
We are evaluating a project that costs $1,100,000, has a life of 10 years, and has...
We are evaluating a project that costs $1,100,000, has a life of 10 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 47,000 units per year. Price per unit is $50, variable cost per unit is $25, and fixed costs are $820,000 per year. The tax rate is 21 percent and we require a return of 16 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $1,080,000, has a life of 10 years, and has...
We are evaluating a project that costs $1,080,000, has a life of 10 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 52,000 units per year. Price per unit is $50, variable cost per unit is $30, and fixed costs are $730,000 per year. The tax rate is 25 percent and we require a return of 15 percent on this project. Suppose the projections given for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT