In: Economics
A resource firm is looking to purchase two machines for its extraction plant. The initial costs and net cash flows are captured in the table below. The company uses a discount rate (MARR) of 6 percent.
Table 2
Year |
Machine A |
Machine B |
0 |
($72,000) |
($51,660) |
1 |
24,000 |
18,000 |
2 |
24,000 |
18,000 |
3 |
24,000 |
16,000 |
4 |
22,000 |
16,000 |
5 |
12,000 |
9,000 |
a) Calculate the discounted payback period for Machine A and Machine B. If the discounted payback period was the only decision tool, which machine would the company select?
b) Calculate the net present value (NPV) of both machines if the firm uses a MARR of 6%. Which machine would be selected in this case? Explain.
Machine A
Intial Investment = $72,000
So our target here is $72,000
Year | Cashflow | PV Factor @ 6% | P.V. of cashflows | Cumulative P.V. of cashflows |
1 | 24000 | 0.943 | 22632 | 22632 |
2 | 24000 | 0.890 | 21360 | 43992 |
3 | 24000 | 0.840 | 20160 | 64152 |
4 | 22000 | 0.792 | 17424 | 81576 |
5 | 12000 | 0.747 | 8964 | 90540 |
We can see that the cost of $72000 is covered between year 3 and year 4. To be more precise:
Cashflow is 17424 in 12 months
So a cashflow of 7848 will be in = (12/17424) *7848 = 5.4 months
So the discounted payback period for Machine A is 3 years 5.4 months.
NPV for Machine A = PV of cash inflows - PV of cash outflows = 90540-72000 =$18540
Machine B
Initial Investment= $51660
Year | Cash Flow | PV Factor @ 6% | PV of Cashflows | Cumulative PV of cashflows |
1 | 18000 | 0.943 | 16974 | 16974 |
2 | 18000 | 0.890 | 16020 | 32994 |
3 | 16000 | 0.840 | 13440 | 46434 |
4 | 16000 | 0.792 | 12672 | 59106 |
5 | 9000 | 0.747 | 6723 | 65829 |
Here the cost of $51660 is recovered between year 3 and year 4. To be more precise:
Cashflow of 12672 is in 12 months
So a cashflow of 5226 will be in : (12/12672)*5226 = 4.95 months
So the discounted pay back period for machine B is 3 years 4.95 months.
NPV for machine B= 65829-51660 =$14169
Since the discounted payback period of Machine B is lower than that of Machine A therefore we will select machine B as per discounted pay back period criteria.
Since the NPV for machine A is greater than the NPV for machine B therefore we will select machine A as per the NPV critera.