Question

In: Physics

Suppose you own some land next to a 50 MW wind farm located on Colorado’s Front...

Suppose you own some land next to a 50 MW wind farm located on Colorado’s Front Range. Your land has a fantastic cliff/ridgeline with an elevation difference of 250 m. Evaluate whether or not you can make money by building a pumped hydroelectric energy storage system on your land that interfaces with the wind farm. Your plan is to capture excess energy from the wind farm or buy energy from the wind farm when electricity prices are low and sell that energy back to the grid when electricity prices are high (assume that the utility that owns the grid will grant you a fair contract). You find that a good power rating for your storage system is 50% of the rated wind farm output, or 25 MW. Also your storage system should be able to generate electricity at rated power for 8 h.


a. Determine the flow rate and reservoir size needed to accomplish the required power output and energy capacity. Pumped hydroelectric plants generally run at 80%–90% generating efficiency, depending on the size of the machinery. Suggest a reasonable surface area and depth for your two reservoirs.
b. Assume it costs $500 per kW to install your turbomachinery and penstocks, plus $2 per cubic yard to build reservoirs. Calculate the initial capital cost of your pumped hydroelectric system.
c. Suppose you can buy energy from the wind farm at $0.035/kWh between the hours of 10:00 pm and 8:00 am to charge your storage and sell energy between 1:00 pm and 9:00 pm back to the grid at $0.1/kWh. Select a reasonable simple payback period that would motivate you to invest in energy storage. Calculate the maximum capital cost expenditure on your energy storage system that would allow this payback period.
d. Would you decide to build this energy storage system? Why or why not?

Solutions

Expert Solution

a.) Power output of hydroelectric plant = , where is efficiency, is density of water, F the flow rate. So, for power output of 25MW, we need F=25 x 106 / (90% x 1000 x 9.8 x 250) = 11.33 m3/s.

Also, flow rate = cross sectional area x velocity of water. velocity of water at the base of 250m cliff is = 70m/s

So area of reservoir is 11.33/70 = 0.162m2. To contain water flow of cross section 0.162m2 at velocity 70m/s for 8 hrs, we require a depth of 40816.3 m.

b.) For 25MW of power, it will require, $500 x 25 x 1000 = $12.5 million. For a reservoir of area 0.162m2 and depth 40816.3 m, it requires, $2 x 0.162 x 40816.3 / 0.764555 (conversion factor) = $17293. So two such reservoir would cost $34587. So total capital cost is $12.534587 million.

c.) Energy that can be produced = 25MW x 8h = 200MWh, energy that can be taken = 50MW x 10h = 500MWh

Cost of energy = $0.035/kWh x 500MWh = $17500. Price of energy = $0.1/kWh x 200MWh = $20000, which gives a profit of $2500 per day. So it takes approximately, 12.5million/2500 = 5014 days or 13 years for payback. The maximum capital cost expenditure is less than a million dollars.

d.) No, since within 13 years, the current price of electricity would change, so it will be a loss to buy and sell energy at the current rate. In 13 years the technology is bound to change that would give energy at lower costs than our selling price.


Related Solutions

Suppose you own some land next to a 50 MW wind farm located on Colorado’s Front...
Suppose you own some land next to a 50 MW wind farm located on Colorado’s Front Range. Your land has a fantastic cliff/ridgeline with an elevation difference of 250 m. Evaluate whether or not you can make money by building a pumped hydroelectric energy storage system on your land that interfaces with the wind farm. Your plan is to capture excess energy from the wind farm or buy energy from the wind farm when electricity prices are low and sell...
DATA: The basic information about the wind farm: Wind farm capacity (MW) 50 Capital investment (€)...
DATA: The basic information about the wind farm: Wind farm capacity (MW) 50 Capital investment (€) 65 000 000 Period of operation (years) 20 Decommissioning costs (€) 3 000 000 O&M costs (€/kWh) 0.0091 Annual energy production (kWh) 110 000 000 QUESTIONS: Please use the information given above to answer the following questions. In order to make this calculation, we need to convert some of the information we have into annual figures: The levelized cost of energy (LCOE) from a...
Suppose an electric utility is considering whether to install a wind farm with 30 megawatts (mw)...
Suppose an electric utility is considering whether to install a wind farm with 30 megawatts (mw) of capacity or a natural gas generator that would produce the same amount of annual electricity. An engineering study showed that the site for the wind farm would produce a load factor of 25 percent. (Actual generation would be 25 percent of capacity on average over the course of a year.) The natural gas plant could be operated with a load factor of 50...
Suppose an electric utility is considering whether to install a wind farm with 30 megawatts (mw)...
Suppose an electric utility is considering whether to install a wind farm with 30 megawatts (mw) of capacity or a natural gas generator that would produce the same amount of annual electricity. An engineering study showed that the site for the wind farm would produce a load factor of 25 percent. (Actual generation would be 25 percent of capacity on average over the course of a year.) The natural gas plant could be operated with a load factor of 50...
Assume a wind farm developer spent millions of dollars constructing wind turbines on land outside Mountain...
Assume a wind farm developer spent millions of dollars constructing wind turbines on land outside Mountain . Adjacent residents filed a lawsuit complaining that they never consented to the loud noise and visual obstructions of the turbine. The Mayor of Mountain proposes that the city place a tax on the turbines with the hope that will generate some much-needed revenue for the city and reduce the quantity of turbines. Verbally discuss and graphically demonstrate the problem created by the turbines....
You own a 25 acre strawberry farm. You currently lease the land to a strawberry farmer...
You own a 25 acre strawberry farm. You currently lease the land to a strawberry farmer for $14,000 per year. Your annual administrative (or fixed) costs from owning the farm are approximately $2,000 per year. 1. You could sell the land for $160,000 today and currently have an investment opportunity for the $160,000 from which you expect to make a return of 8% per year. a.        What are your accounting profits for the year? b.       What are your economic profits for the...
An airport is located next to a large tract of land owned by a housing developer....
An airport is located next to a large tract of land owned by a housing developer. The developer would like to build houses on this land, but noise from the airport reduces the value of the land. The more planes that fly, the lower is the amount of profits that the developer makes. Let X be the number of planes that fly per day and let Y be the number of houses that the developer builds. The airport’s total profits...
Suppose you own a vacant but developable land parcel on the outskirts of the metropolitan area....
Suppose you own a vacant but developable land parcel on the outskirts of the metropolitan area. This land produces no income but owes 2% of its value per year in property taxes. Meanwhile, typical income properties are yielding 9% (that is, they have a current cash yield, or “cap rate,” of 9%). If inflation is expected to be around 3% per year, and you expect your land will appreciate at 10% per year, what should you do with this land...
Suppose a farm couple has the option to purchase 400 acres of land. Assume they are...
Suppose a farm couple has the option to purchase 400 acres of land. Assume they are able to purchase the land for $4,000/acre. Assume a 25% down payment with the balance financed by a 30 year loan with a 7% interest rate and equal annual principal payments. What will their interest change in year 2 be? a. $40,000 b. $84,000 c. $78,400 d. $81,200
In 1979, Paul and John Reardon purchased 16 acres of land located next to a manufacturing...
In 1979, Paul and John Reardon purchased 16 acres of land located next to a manufacturing plant in Massachusetts. In 1983, a state environmental agency, responding to a citizen's report, tested soil samples from both properties and discovered extremely high levels of polychlorinated biphenyls (PCBs) on the plant site and on the Reardons' property where it bordered the site. Shortly thereafter, the Environmental Protection Agency (EPA) cleaned up the contaminated areas. In 1985, the EPA notified the Reardons that they...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT