DATA: The basic information about the wind farm: Wind farm capacity (MW) 50 Capital investment (€)...

DATA:
The basic information about the wind farm:
Wind farm capacity (MW) 50
Capital investment (€) 65 000 000
Period of operation (years) 20
Decommissioning costs (€) 3 000 000
O&M costs (€/kWh) 0.0091
Annual energy production (kWh) 110 000 000

QUESTIONS:
Please use the information given above to answer the following questions.

In order to make this calculation, we need to convert some of the information we have
into annual figures:

The levelized cost of energy (LCOE) from a wind farm.
Once again, we need the capital cost of the wind farm (€) and the O&M costs in euro for
each year (€/year) - calculated in exercise above. Finally, we will need the
decommissioning costs (€).


1. Again, using the NPV function, what is the present value of all the maintenance costs
for the 20 years of operation (€)? Hint: For calculating NPV of costs, the sign of each
annual entry should be negative. Note also that the initial capital investment should
not be included here.
Electricity selling price, tariff (€/kWh) 0,075
Annual discount rate (%) 8

2. What is the present value of the payment cost made to decommission the wind farm
(€)? Hint: Use the PV function but take care as the annual payment is zero and the
decommissioning cost is the future value.
3. Finally, add these two together with the initial capital cost to give the present value of
all the costs (€).
4. What is the levelized annual cost (€/year)?
5. What is the levelized cost of energy (LCOE) for the wind farm (€/kWh)?
6. What is this in €c/kWh?

Please help in solving this wind farm project economics.

Please be very specific in your solution & explain any formulas that are used because I am really confused.

Thank you,

J.

Solutions

Expert Solution


Related Solutions

Suppose you own some land next to a 50 MW wind farm located on Colorado’s Front...
Suppose you own some land next to a 50 MW wind farm located on Colorado’s Front Range. Your land has a fantastic cliff/ridgeline with an elevation difference of 250 m. Evaluate whether or not you can make money by building a pumped hydroelectric energy storage system on your land that interfaces with the wind farm. Your plan is to capture excess energy from the wind farm or buy energy from the wind farm when electricity prices are low and sell...
Suppose you own some land next to a 50 MW wind farm located on Colorado’s Front...
Suppose you own some land next to a 50 MW wind farm located on Colorado’s Front Range. Your land has a fantastic cliff/ridgeline with an elevation difference of 250 m. Evaluate whether or not you can make money by building a pumped hydroelectric energy storage system on your land that interfaces with the wind farm. Your plan is to capture excess energy from the wind farm or buy energy from the wind farm when electricity prices are low and sell...
Suppose an electric utility is considering whether to install a wind farm with 30 megawatts (mw)...
Suppose an electric utility is considering whether to install a wind farm with 30 megawatts (mw) of capacity or a natural gas generator that would produce the same amount of annual electricity. An engineering study showed that the site for the wind farm would produce a load factor of 25 percent. (Actual generation would be 25 percent of capacity on average over the course of a year.) The natural gas plant could be operated with a load factor of 50...
Suppose an electric utility is considering whether to install a wind farm with 30 megawatts (mw)...
Suppose an electric utility is considering whether to install a wind farm with 30 megawatts (mw) of capacity or a natural gas generator that would produce the same amount of annual electricity. An engineering study showed that the site for the wind farm would produce a load factor of 25 percent. (Actual generation would be 25 percent of capacity on average over the course of a year.) The natural gas plant could be operated with a load factor of 50...
Consider a 2.0 MW wind turbine that operates with a capacity factor of 30% (i.e. it...
Consider a 2.0 MW wind turbine that operates with a capacity factor of 30% (i.e. it produces 5,300 MWh/y). The initial cost is $3.5 million. The project life is 30 years and the salvage value is negligible. Maintenance costs are $50,000/y. The minimum attractive rate of return is 7%. For each of the following cases, determine the present value of the project and whether the cost is justified. a. Power can be sold to the grid at $0.055/kWh. (ans. -503200,...
2- Find world data for total installed electrical generating capacity data and installed wind generation capacity...
2- Find world data for total installed electrical generating capacity data and installed wind generation capacity for years between 2000 and the most recent year for which data are available. What are the actual annual growth rates for this period?
The following is information regarding the capital structure of Wind Industries: - Capital structure consists of...
The following is information regarding the capital structure of Wind Industries: - Capital structure consists of a single long-term debt issue with a face value of $20 million and 2 million common shares with a current market price of $15 per share - The long-tern debt issue carries a coupon rate of 5% with interest paid semi-annually. It has 8 years remaining until maturity and a current market yield of 6%, also based on semi annual compounding. - The common...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 1,800,000...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 1,800,000 Annual net income $ 200,000 Expected life 8 years Salvage value $ 240,000 Merrill’s cost of capital 10 % Assume straight line depreciation method is used. Required: 1. Calculate the project’s net present value. 2. Without making any calculations, determine whether the internal rate of return (IRR) is more or less than 10 percent. 3. Calculate the net present value using a 15 percent...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 900,000...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 900,000 Annual net income $ 90,000 Expected life 8 years Salvage value $ 100,000 Merrill’s cost of capital 7 % Assume straight line depreciation method is used.   Required: 1. Calculate the project’s net present value. (Future Value of $1, Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) (Use appropriate factor(s) from the tables provided. Do not round intermediate calculations....
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 1,100,000...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 1,100,000 Annual net income $ 110,000 Expected life 8 years Salvage value $ 120,000 Merrill’s cost of capital 7 % Assume straight line depreciation method is used.   Required: 1. Calculate the project’s net present value. (Future Value of $1, Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) (Use appropriate factor(s) from the tables provided. Do not round intermediate calculations....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT