In: Operations Management
You are presented with a situation in a project where you need to measure the performance of the project. Which of these techniques would suit your requirement? Earned value technique Learned value technique Expert Judgement Analogous estimating
Answer:
Earned value technique
Explanation:
This method is used to track the project progress against the project plan.So this method can measure the performance of the project and whether the project meets its objectives