Question

In: Accounting

The NPV of a series of cash flows is the following: At a 5% required rate...

The NPV of a series of cash flows is the following:

At a 5% required rate of return, the NPV is $41,728

At a 10% required rate of return, the NPV is $24,708

At a 15% required rate of return, the NPV is $9,940

At a 20% required rate of return, the NPV is -$2,968 (note the negative sign)

The IRR for the series of cash flows is in which range:

Multiple Choice

0% to 5%

Between 5% and 10%

Between 10% and 15%

Between 15% and 20%

Solutions

Expert Solution

The correct answer is option (d). Between 15% and 20%

INTERNAL RATE OF RETURN (IRR) means the rate at which NPV is zero . It means the rate at which present values of total cash inflows is equal to present value of total cash outflows.

We know that as discount rate increases the Net present value of series of cash flows decreases.

EXPLANATION

We can observe that in the given case as required rate increased from 5% to 20% the NPV of series of cash flows has decreased from $41,728 to -$2,968.

So, we need to find the required rate at which the net present value (NPV) is zero.

From the given case we can observe that the NPV is near to zero when the required rate is 20% (-$2,968).

And as the rate has decreased to 15% the NPV has increased and became positive ($9,940). It means the required discount rate at which NPV is zero is present in between the required rates of 15% and 20%.

I have concluded that NPV is zero when required rate is between 15% and 20% because, we know that a number changes its sign from negative to positive or positive to negative at Zero (0). In the given case the NPV has changed from $9,940 (positive) to -$2,968 (negative) when in between 15% and 20%. So, I have concluded that the NPV is zero when the rate is in between 15% and 20%.

Internal rate of return means the rate at which NPV is zero. From our discussion NPV is zero between 15% and 20%.

So, IRR (Internal rate of return) is present in between the required rate of 15% and 20%.

​​​​​​Hope you understood the solution. If you have any doubt please leave your doubt in the comment section so that I can clarify your doubt.

Thank you.


Related Solutions

A. What is the NPV of the following cash flows if the required rate of return...
A. What is the NPV of the following cash flows if the required rate of return is 0.05? Year 0 1 2 3 4 CF -13868 2129 2503 694 3244    Enter the answer with 2 decimals (e.g. 1000.23). B. Winnebagel Corp. currently sells 39298 motor homes per year at $59840 each, and 17359 luxury motor coaches per year at $116566 each. The company wants to introduce a new portable camper to fill out its product line; it hopes to...
​(NPVcalculation​)Calculate the NPV given the following free cash​ flows, if the appropriate required rate of return...
​(NPVcalculation​)Calculate the NPV given the following free cash​ flows, if the appropriate required rate of return is 8 percent. Should the project be​ accepted? YEARCASH FLOW    0 −​$90,000    1      10,000    2      10,000    3      15,000    4      15,000    5      30,000    6      30,000 MIRRcalculation​)Calculate the MIRR given the following free cash​ flows if the appropriate required rate of return is 12 percent​ (use this as the reinvestment​rate). Should the project be​ accepted? YEAR   CASH FLOWS 0   -50,000 1   35,000 2   35,000 3   35,000...
For what value of W will the NPV of the series of cash flows be zero...
For what value of W will the NPV of the series of cash flows be zero at 12% per period interest rate? please use excel and the Goal seek function solving for W. and explain work please....the answer is one of the four Year Cash Flow 0 +$25000 1 -4W 2 18W 3 -16W 4 48W 5 -64W 6 42W 7 -256W 8 52W 9 -64W 10 42W 11 -256W 12 52W $98 $124 $167 $184
Calculate the NPV for a 3-year project with the following cash flows and a required return...
Calculate the NPV for a 3-year project with the following cash flows and a required return of 15%: CF0 = -$800,000 ATCF1 = $160,000 ATCF2 = $160,000 ATCF3 = $160,000 ATER = $600,000 Calculate the IRR for a 2-year project with the following cash flows and a required return of 12%: CFO = -$375,000 ATCF1 = $27,500 ATCF2 = -$134,800 ATER = $596,000 ATER = After-Tax Equity Reversion ATCF = After-Tac Cash Flow Please show me how you answer the...
Use a 5 percent discount rate to compute the NPV of each of the following series...
Use a 5 percent discount rate to compute the NPV of each of the following series of cash receipts and payments: Use Appendix A and Appendix B. $6,200 received now (year 0), $1,890 paid in year 3, and $4,000 paid in year 5. $10,000 paid now (year 0), $12,690 paid in year 2, and $31,000 received in year 8. $20,000 received now (year 0), $13,500 paid in year 5, and $7,500 paid in year 10. (For all requirements, round discount...
Use a 5 percent discount rate to compute the NPV of each of the following series...
Use a 5 percent discount rate to compute the NPV of each of the following series of cash receipts and payments: Use Appendix A and Appendix B. $6,200 received now (year 0), $1,890 paid in year 3, and $4,000 paid in year 5. $10,000 paid now (year 0), $12,690 paid in year 2, and $31,000 received in year 8. $20,000 received now (year 0), $13,500 paid in year 5, and $7,500 paid in year 10. (For all requirements, round discount...
Use a 5 percent discount rate to compute the NPV of each of the following series...
Use a 5 percent discount rate to compute the NPV of each of the following series of cash receipts and payments: Use Appendix A and Appendix B. $6,200 received now (year 0), $1,890 paid in year 3, and $4,000 paid in year 5. $10,000 paid now (year 0), $12,690 paid in year 2, and $31,000 received in year 8. $20,000 received now (year 0), $13,500 paid in year 5, and $7,500 paid in year 10.
1A) What is the discount rate at which the following cash flows have a NPV of...
1A) What is the discount rate at which the following cash flows have a NPV of $0? Answer in %, rounding to 2 decimals. Year 0 cash flow = -158,000 Year 1 cash flow = 30,000 Year 2 cash flow = 36,000 Year 3 cash flow = 38,000 Year 4 cash flow = 39,000 Year 5 cash flow = 43,000 Year 6 cash flow = 42,000 1B) Your firm is evaluating a capital budgeting project. The estimated cash flows appear...
1A) What is the discount rate at which the following cash flows have a NPV of...
1A) What is the discount rate at which the following cash flows have a NPV of $0? Answer in %, rounding to 2 decimals. Year 0 cash flow = -149,000 Year 1 cash flow = 39,000 Year 2 cash flow = 30,000 Year 3 cash flow = 40,000 Year 4 cash flow = 30,000 Year 5 cash flow = 41,000 Year 6 cash flow = 37,000 1B) What is the discounted payback period on Versace's proposed investment in a new...
Find the modified internal rate of return (MIRR) for the following series of future cash flows...
Find the modified internal rate of return (MIRR) for the following series of future cash flows if the company is able to reinvest cash flows received from the project at an annual rate of 8.91 percent.The initial outlay is $354,000. Year 1: $169,600 Year 2: $137,900 Year 3: $178,100 Year 4: $132,200 Year 5: $182,300 Round the answer to two decimal places in percentage form.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT