Question

In: Finance

Washington County’s Board of Representatives is considering the construction of a longer runway at the county...

Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below.

Cost of acquiring additional land for runway $ 75,000
Cost of runway construction 355,000
Cost of extending perimeter fence 23,158
Cost of runway lights 40,000
Annual cost of maintaining new runway 20,000
Annual incremental revenue from landing fees 45,000

In addition to the preceding data, two other facts are relevant to the decision. First, a longer runway will require a new snowplow, which will cost $155,000. The old snowplow could be sold now for $15,500. The new, larger plow will cost $13,000 more in annual operating costs. Second, the County Board of Representatives believes that the proposed long runway, and the major jet service it will bring to the county, will increase economic activity in the community. The board projects that the increased economic activity will result in $66,000 per year in additional tax revenue for the county.

In analyzing the runway proposal, the board has decided to use a 10-year time horizon. The county’s hurdle rate for capital projects is 6 percent.

Use Appendix A for your reference. (Use appropriate factor(s) from the tables provided.)

In analyzing the runway proposal, the board has decided to use a 10-year time horizon. The county’s hurdle rate for capital projects is 6 percent. The County Board of Representatives believes that if the county conducts a promotional effort costing $35,500 per year, the proposed long runway will result in substantially greater economic development than was projected originally. However, the board is uncertain about the actual increase in county tax revenue that will result.

Required:

Suppose the board builds the long runway and conducts the promotional campaign. What would the increase in the county’s annual tax revenue need to be in order for the proposed runway’s internal rate of return to equal the county’s hurdle rate of 6 percent? (Round intermediate and final answer to the nearest dollar amount.)

uired increase in tax revenue?

Solutions

Expert Solution

Let us start with the cashflows assuming that the runway is constructed and the promotional effort is done.

First let us assume that the increase in tax revenue is $66,000 per year as projected. Assuming that the construction costs are upfront and all revenues & annual costs are realized at the end of the year, the cash flows will look like:

Year 0 1 2 3 4 5 6 7 8 9 10
Incremental revenue from landing      45,000      45,000      45,000      45,000      45,000      45,000      45,000      45,000      45,000      45,000
Increased tax revenue      66,000      66,000      66,000      66,000      66,000      66,000      66,000      66,000      66,000      66,000
Cost of land     (75,000)
Cost of construction (355,000)
Cost of perimeter     (23,158)
Cost of runway lights     (40,000)
Maintenance    (20,000)    (20,000)    (20,000)    (20,000)    (20,000)    (20,000)    (20,000)    (20,000)    (20,000)    (20,000)
Cost of new snoplow (155,000)
Salvage of old plow        15,500
Operating cost of new plow    (13,000)    (13,000)    (13,000)    (13,000)    (13,000)    (13,000)    (13,000)    (13,000)    (13,000)    (13,000)
Promotional effort    (35,500)    (35,500)    (35,500)    (35,500)    (35,500)    (35,500)    (35,500)    (35,500)    (35,500)    (35,500)
Total Cash Flows (632,658)      42,500      42,500      42,500      42,500      42,500      42,500      42,500      42,500      42,500      42,500

The IRR of these calcuations can't be computed (mathematically, IRR is coming to be negative)

Now, using excel (or trial and error), we can compute the value of increased tax per year to make IRR equal to 6%.

Increased tax value = $109,450

Year 0 1 2 3 4 5 6 7 8 9 10
Incremental revenue from landing      45,000      45,000      45,000      45,000      45,000      45,000      45,000      45,000      45,000      45,000
Increased tax revenue    109,450    109,450    109,450    109,450    109,450    109,450    109,450    109,450    109,450    109,450
Cost of land     (75,000)
Cost of construction (355,000)
Cost of perimeter     (23,158)
Cost of runway lights     (40,000)
Maintenance    (20,000)    (20,000)    (20,000)    (20,000)    (20,000)    (20,000)    (20,000)    (20,000)    (20,000)    (20,000)
Cost of new snoplow (155,000)
Salvage of old plow        15,500
Operating cost of new plow    (13,000)    (13,000)    (13,000)    (13,000)    (13,000)    (13,000)    (13,000)    (13,000)    (13,000)    (13,000)
Promotional effort    (35,500)    (35,500)    (35,500)    (35,500)    (35,500)    (35,500)    (35,500)    (35,500)    (35,500)    (35,500)
Total Cash Flows (632,658)      85,950      85,950      85,950      85,950      85,950      85,950      85,950      85,950      85,950      85,950

IRR = 6%


Related Solutions

Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 69,000 Cost of runway construction 230,000 Cost of extending perimeter fence 16,967 Cost of runway lights 36,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 75,000 Cost of runway construction 355,000 Cost of extending perimeter fence 23,158 Cost of runway lights 40,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 69,000 Cost of runway construction 230,000 Cost of extending perimeter fence 16,967 Cost of runway lights 36,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 63,000 Cost of runway construction 305,000 Cost of extending perimeter fence 19,880 Cost of runway lights 32,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 79,500 Cost of runway construction 270,000 Cost of extending perimeter fence 19,840 Cost of runway lights 43,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 87,000 Cost of runway construction 295,000 Cost of extending perimeter fence 10,724 Cost of runway lights 48,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 88,500 Cost of runway construction 300,000 Cost of extending perimeter fence 10,180 Cost of runway lights 49,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 75,000 Cost of runway construction 355,000 Cost of extending perimeter fence 23,158 Cost of runway lights 40,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 78,000 Cost of runway construction 265,000 Cost of extending perimeter fence 50,270 Cost of runway lights 42,000...
Required information [The following information applies to the questions displayed below.] Washington County’s Board of Representatives...
Required information [The following information applies to the questions displayed below.] Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 75,000 Cost of runway construction 355,000...