Washington County’s Board of Representatives is considering the construction of a longer runway at the county...

Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below.

Cost of acquiring additional land for runway $ 75,000
Cost of runway construction 355,000
Cost of extending perimeter fence 23,158
Cost of runway lights 40,000
Annual cost of maintaining new runway 20,000
Annual incremental revenue from landing fees 45,000

In addition to the preceding data, two other facts are relevant to the decision. First, a longer runway will require a new snowplow, which will cost $155,000. The old snowplow could be sold now for $15,500. The new, larger plow will cost $13,000 more in annual operating costs. Second, the County Board of Representatives believes that the proposed long runway, and the major jet service it will bring to the county, will increase economic activity in the community. The board projects that the increased economic activity will result in $66,000 per year in additional tax revenue for the county.

In analyzing the runway proposal, the board has decided to use a 10-year time horizon. The county’s hurdle rate for capital projects is 6 percent.

Use Appendix A for your reference. (Use appropriate factor(s) from the tables provided.)

Required:

  1. 1. Prepare a net-present-value analysis of the proposed long runway.

  2. 2. Should the County Board of Representatives approve the runway considering NPV?

  3. 3-a. Which of the data used in the analysis are likely to be most uncertain?

  4. 3-b. Which of the data used in the analysis are likely to be least uncertain?

  • Req 1
  • Req 2
  • Req 3A
  • Req 3B

Prepare a net-present-value analysis of the proposed long runway. (Round your "Annuity discount factor" to 3 decimal places. Negative amounts should be indicated by a minus sign.)

Annual incremental benefit $0
Annuity discount factor
Present value of annual benefits
Initial costs:
Net present value

$0

Should the County Board of Representatives approve the runway considering NPV?

Which of the data used in the analysis are likely to be most uncertain? (Select which of the following statements (is) are true by selecting an "X".)

Cost of acquiring land
Annual cost of maintaining new runway
Annual incremental revenue from landing fees
Cost of new snow plow
Cost of runway lights
Annual additional tax revenue
Salvage value of old snow plow

Which of the data used in the analysis are likely to be least uncertain? (Select which of the following statements (is) are true by selecting an "X".)

Annual additional tax revenue
Annual cost of maintaining new runway
Cost of acquiring land
Annual incremental revenue from landing fees
Cost of runway lights
Salvage value of old snow plow
Cost of new snow plow

Solutions

Expert Solution

Answer is given below


Related Solutions

Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 69,000 Cost of runway construction 230,000 Cost of extending perimeter fence 16,967 Cost of runway lights 36,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 75,000 Cost of runway construction 355,000 Cost of extending perimeter fence 23,158 Cost of runway lights 40,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 75,000 Cost of runway construction 355,000 Cost of extending perimeter fence 23,158 Cost of runway lights 40,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 69,000 Cost of runway construction 230,000 Cost of extending perimeter fence 16,967 Cost of runway lights 36,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 63,000 Cost of runway construction 305,000 Cost of extending perimeter fence 19,880 Cost of runway lights 32,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 79,500 Cost of runway construction 270,000 Cost of extending perimeter fence 19,840 Cost of runway lights 43,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 87,000 Cost of runway construction 295,000 Cost of extending perimeter fence 10,724 Cost of runway lights 48,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 88,500 Cost of runway construction 300,000 Cost of extending perimeter fence 10,180 Cost of runway lights 49,000...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county...
Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 78,000 Cost of runway construction 265,000 Cost of extending perimeter fence 50,270 Cost of runway lights 42,000...
Required information [The following information applies to the questions displayed below.] Washington County’s Board of Representatives...
Required information [The following information applies to the questions displayed below.] Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 75,000 Cost of runway construction 355,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT