Question

In: Finance

2. Given the following expected cash flows for two projects, and an opportunity cost of capital...

2. Given the following expected cash flows for two projects, and an opportunity cost of capital of 10%, which project is better and why? (10 points)

            Expected Net Cash Flows

Year    Project A         Project B

0          -$10,000          -$10,000

1          $5000              $0

2          $5000              $0

3          $5000              $8,000

4          $5000              $2,000

3. Given the following expected cash flows for two projects, and an opportunity cost of capital of 8%, which project is better and why? (10 points)

            Expected Net Cash Flows

Year    Project A         Project B

0          -$1,000            -$1,000

1          $500                $50

2          $500                $300

3          $500                $400

4          $500                $2,000

Solutions

Expert Solution


Related Solutions

choosing between two projects. The cash flows for the projects are given in the following table​...
choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A negative $ 48 −$48 $ 24 $24 $ 21 $21 $ 19 $19 $ 15 $15 B negative $ 102 −$102 $ 20 $20 $ 41 $41 $ 48 $48 $ 58 $58 a. What are the IRRs of the two​ projects? b. If your discount rate is 4.7 %...
The cash flow in respect of two projects is given below. The cost of capital is...
The cash flow in respect of two projects is given below. The cost of capital is 8.5%. Year Project A Project B 0 (200) (300) 1 65 100 2 65 100 3 65 90 4 60 70 5 60 70 Answer the following question using the above information. I           What is the NPV of Project A? Should this project be accepted? II         What is the NPV of Project B? Should this project be accepted? (Please state based on what the...
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost...
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost of capital; answer the next 2 questions: year Project A Project B 0 -5000 -1000 1 2500 600 2 2500 600 3 2500 600 1)  Which project should be accepted, if any and why? Project B; it has a higher IRR and PI Neither project should be accepted, they both have negative NPVs Both project should be accepted; they have IRRs greater than the cost...
You are given the following two projects cash flows that will be used to illustrate the...
You are given the following two projects cash flows that will be used to illustrate the application of the various capital techniques in project analysis. PROJECTS / CASHFLOWS (RM) YEAR A B 0 (100,000) (120,000) 1 30,000 20,000 2 30,000 30,000 3 30,000 40,000 4 30,000 40,000 5 30,000 50,000 a. Identify the payback period for both of the project. (2mark) b. Assume that the firm’s cost of capital is 10%, calculte the Net Present Value (NPV) for both projects....
3.         The cash flow in respect of two projects is given below. The cost of capital...
3.         The cash flow in respect of two projects is given below. The cost of capital is 8.5%. Year Project A Project B 0 (200) (300) 1 65 100 2 65 100 3 65 90 4 60 70 5 60 70 Answer the following question using the above information. I           What is the NPV of Project A? Should this project be accepted? II         What is the NPV of Project B? Should this project be accepted? III        What is the Accounting...
Given a project with the following cash flows and a cost of capital of 9%. Calculate...
Given a project with the following cash flows and a cost of capital of 9%. Calculate the NPV, IRR, MIRR, PI, payback and discounted payback. For each of the six calculations, give a brief interpretation of what it measures and how it should be used to evaluate a project. Should the project be accepted? Why or why not? Time Period Cash Flow      0 -$200,000      1 $50,000      2 $70,000      3 -$80,000      4 $75,000      5 $100,000...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$52 $27 $19 $22 $17 B −$100 $22 $41 $48 $61 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.4%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV rank the two projects​ differently?
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$52 $27 $19 $18 $17 B −$101 $19 $40 $51 $58 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.4%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV rank the two projects​ differently? a. What...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A -$ 49 $ 24 $ 19 $ 20 $ 13 B -$ 100 $ 18 $ 39 $ 48 $ 59 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.5 % what are the NPVs of the two​ projects? c. Why...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A -$48 $27 $ 21 $ 19 $ 12 B −$98 $20 $ 41 $ 51 $ 59 a. What are the IRRs of the two​ projects? (Round to one decimal​ place.) b. If your discount rate is 4.7%​ what are the NPVs of the two​ projects? c. Why...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT