In: Accounting
Windsor Supply Company, a newly formed corporation, incurred the
following expenditures related to Land, to Buildings, and to
Machinery and Equipment.
Abstract company’s fee for title search | $780 | |||
Architect’s fees | 4,755 | |||
Cash paid for land and dilapidated building thereon | 130,500 | |||
Removal of old building |
$30,000 |
|||
Less: Salvage |
8,250 |
21,750 | ||
Interest on short-term loans during construction | 11,100 | |||
Excavation before construction for basement | 28,500 | |||
Machinery purchased (subject to 2% cash discount, which was not taken) | 82,500 | |||
Freight on machinery purchased | 2,010 | |||
Storage charges on machinery, necessitated by noncompletion of | ||||
building when machinery was delivered | 3,270 | |||
New building constructed (building construction took 6 months from | ||||
date of purchase of land and old building) | 727,500 | |||
Assessment by city for drainage project | 2,400 | |||
Hauling charges for delivery of machinery from storage to new building | 930 | |||
Installation of machinery | 3,000 | |||
Trees, shrubs, and other landscaping after completion of building | ||||
(permanent in nature) | 8,100 |
Determine the amounts that should be debited to Land, to Buildings,
and to Machinery and Equipment. Assume the benefits of capitalizing
interest during construction exceed the cost of implementation.
Company uses net method to record discount. (Please
leave spaces blank if there is no answer. Do not enter zeros in
those spaces.)
Land |
Buildings |
Machinery and Equipment |
Other |
|||||
---|---|---|---|---|---|---|---|---|
Abstract fees |
$enter a dollar amount |
$enter a dollar amount |
$enter a dollar amount |
$enter a dollar amount |
||||
Architect’s fees |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
||||
Cash paid for land and old building |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
||||
Removal of old building |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
||||
Interest on loans during construction |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
||||
Excavation before construction |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
||||
Machinery purchased |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
||||
Freight on machinery |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
||||
Storage charges caused by noncompletion of building |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
||||
New building |
enter a dollar amount |
enter a dollar amount |
enter a dollar amount |
Machinery is purchased at cash discount has been reported after discount cost (82500 * 0.98)
Please upvote if satisfied