Question

In: Finance

 Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​...

 Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​ firm's warehouse capacity. The relevant cash flows for the projects are shown in the following​ table:

Project X

Project Y

Initial investment

​(CF 0CF0​)

​$500,000

​$310,000

Year

​(t​)

Cash inflows

​(CF Subscript tCFt​)

1

​$140,000

​$150,000

2

​$130,000

​$120,000

3

​$140,000

​$75,000

4

​$180,000

​$90,000

5

​$260,000

​$40,000

. The​ firm's cost of capital is15​%.

a.  Calculate the IRR for each of the projects. Assess the acceptability of each project on the basis of the IRRs.

b.  Which project is​ preferred?

Solutions

Expert Solution

a. IRR is the internal rate of return at which present value of cash flows are equal to initial investment.

initial investment = year 1 cash flow/(1+IRR) + year 2 cash flow/(1+IRR)2 .... + year 5 cash flow/(1+IRR)5

IRR of Project X is 18.29% and Project Y 20.22%. based on IRR, both Project X and Y are acceptable because both have IRRs higher than firm's cost of capital of 15%. both Projects will make profits.

Years Project X Project Y
0 -$500,000 -$310,000
1 $140,000 $150,000
2 $130,000 $120,000
3 $140,000 $75,000
4 $180,000 $90,000
5 $260,000 $40,000
IRR 18.29% 20.22%

Calculations

b. Since both projects are mutually exclusive, so we can accept only one project. Project Y will be accepted because it has IRR of 20.22% higher than IRR of Project X's 18.29% and firm's cost of capital of 15%.


Related Solutions

Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​...
Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​ firm's warehouse capacity. The relevant cash flows for the projects are shown in the following​ table: Project X Project Y Initial investment ​(CF 0CF0​) ​$500,000 ​$310,000 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) 1 ​$130,000 ​$140,000 2 ​$130,000 ​$140,000 3 ​$130,000 ​$85,000 4 ​$180,000 ​$90,000 5 ​$270,000 ​$30,000 The​ firm's cost of capital is 16​%. a.  Calculate the IRR for each of the projects....
 Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​...
 Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​ firm's warehouse capacity. The relevant cash flows for the projects are shown in the following​ table: The​ firm's cost of capital is 16​%. Project X Project Y Initial investment ​(CF 0CF0​) ​$500,000 ​$310,000 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) 1 ​$130,000 ​$140,000 2 ​$130,000 ​$140,000 3 ​$130 comma 000130,000 ​$85 comma 00085,000 4 ​$180,000 ​$90,000 5 ​$270,000 ​$30,000 a.  Calculate the IRR for...
IRRlMutually exclusive projects   Bell Manufacturing is attempting to choose the better of two mutually exclusive projects...
IRRlMutually exclusive projects   Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​ firm'swarehouse capacity. The relevant cash flows for the projects are shown in the following​ table: Initial investment        $500,000         $320,000 Year                 1          $130,000         $130,000 2          $120,000         $120,000 3          $130,000         $105,000 4          $200,000         $90,000 5          $250,000         $40,000 The​ firm's cost of capital is 17​%. a.  Calculate the IRR for each of the projects. Assess the acceptability of each project on the basis of the IRRs. b.  Which project is​ preferred?
IRRlong dash—Mutually exclusive projects Bell Manufacturing is attempting to choose the better of two mutually exclusive...
IRRlong dash—Mutually exclusive projects Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the firm's warehouse capacity. The relevant cash flows for the projects are shown in the following table: LOADING... . The firm's cost of capital is 1313 %. a. Calculate the IRR for each of the projects. Assess the acceptability of each project on the basis of the IRRs. b. Which project is preferred? Project X Project Y Initial investment ​(CF 0CF0​)...
The following two projects of equal risk are mutually exclusive alternatives for expanding the firm’s capacity....
The following two projects of equal risk are mutually exclusive alternatives for expanding the firm’s capacity. The firm’s cost of capital is 15%. The cash flows for each project are given in the following table. Year Project A Project B 0 210,000 20,000 1 15,000 12,000 2 30,000 10,500 3 32,000 9,500 4 425,000 8,200 Required: a) Calculate each project’s payback period. Using the payback period criterion which project is preferable? b) Calculate the net present value for each project....
The following two projects of equal risk are mutually exclusive alternatives for expanding the firm’s capacity....
The following two projects of equal risk are mutually exclusive alternatives for expanding the firm’s capacity. The firm’s cost of capital is 15%. The cash flows for each project are given in the following table. PROJECT A PROJECT B Initial investment 210,000 20,000 Year Net cash inflows Net cash inflows 1 15,000 12,000 2 30,000 10,500 3 32,000 9,500 4 425,000 8,200
KORONA Manufacturing is considering investing in either of two mutually exclusive projects, A and B. The...
KORONA Manufacturing is considering investing in either of two mutually exclusive projects, A and B. The firm has a 14 percent cost of capital, and the risk-free rate is currently 9 percent. The initial investment, expected cash inflows, and certainty equivalent factors associated with each of the projects are shown in the following table. Project A Project B Initial investment (II) $ 40,000 $ 56,000 Year (t) Cash inflows (CFt) Certainty equivalent factors (αt) Cash inflows (CFt) Certainty equivalent factors...
The Sloan Corporation is trying to choose between the following two mutually exclusive design projects:   ...
The Sloan Corporation is trying to choose between the following two mutually exclusive design projects:    Year Cash Flow (I) Cash Flow (II) 0 –$ 61,000 –$ 18,300 1 28,100 9,950 2 28,100 9,950 3 28,100 9,950     a-1 If the required return is 10 percent, what is the profitability index for both projects? (Do not round intermediate calculations. Round your answers to 3 decimal places, e.g., 32.161.)    Profitability Index   Project I      Project II       a-2 If...
a firm must choose between two mutually exclusive projects, a & b. project a has an...
a firm must choose between two mutually exclusive projects, a & b. project a has an initial cost of $10000. its projected net cash flows are $800, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. project b has an initial cost of $14000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. the firm’s cost of capital is 6.00%. choose the...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. At what cost of capital would the firm be...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT