In: Finance
The calculations for project A are shown below:
| Year | Cash flow (CF) | Present value Factor @ 6%(Pv) | CF*Pv | 
| 0 | -10000 | 1 | -10000 | 
| 1 | 800 | 0.943396226 | 754.7169811 | 
| 2 | 2000 | 0.88999644 | 1779.99288 | 
| 3 | 3000 | 0.839619283 | 2518.857849 | 
| 4 | 4000 | 0.792093663 | 3168.374653 | 
| 5 | 5000 | 0.747258173 | 3736.290864 | 
| NPV = | 1958.233228 | ||
| IRR= | 11.44% | 
NPV= 1958.233228
let the IRR be r
The IRR is the rate at which NPV is zero
so, 10000 = 800/(1+r) + 2000/(1+r)^2 + 3000/ (1+r)^3 + 4000/ (1+r)^4 + 5000/(1+r)^5
Solving for r by trial and error method or excel, r = 0.1144 or 11.44%
The calculations for project B are shown below:
| Year | Cash flow (CF) | Present value Factor (Pv) @ 6% | CF*Pv | 
| 0 | -14000 | 1 | -14000 | 
| 1 | 7000 | 0.943396226 | 6603.773585 | 
| 2 | 5000 | 0.88999644 | 4449.9822 | 
| 3 | 3000 | 0.839619283 | 2518.857849 | 
| 4 | 2000 | 0.792093663 | 1584.187326 | 
| 5 | 1000 | 0.747258173 | 747.2581729 | 
| NPV = | 1904.059133 | ||
| IRR= | 12.83% | 
NPV= 1904.059133
let the IRR be r
The IRR is the rate at which NPV is zero
so, 14000 = 7000/(1+r) + 5000/(1+r)^2 + 3000/ (1+r)^3 + 2000/ (1+r)^4 + 1000/(1+r)^5
Solving for r by trial and error method or excel, r = 0.1283 or 12.83%
\
So we see NPV of A and IRR of B is higher
Hence, the correct option is
B) the npv criterion recommends project a while the irr criterion recommends project b.