In: Finance
Benson Designs has prepared the following estimates for a long-term project it is considering. The initial investment is $34570, and the project is expected to yield after-tax cash inflows of $9000 per year for 6 years. The firm has a cost of capital of 14%.
a. Determine the net present value (NPV) for the project.
b. Determine the internal rate of return (IRR) for the project.
c. Would you recommend that the firm accept or reject the project?
a). Determing the Net Present value (NPV) of the Project:
Year | Cash Flows ($) | PV Factor @14% | Present Value ($) |
0 | (34,570.00) | 1.0000 | (34,570.00) |
1 | 9,000.00 | 0.8772 | 7,894.74 |
2 | 9,000.00 | 0.7695 | 6,925.21 |
3 | 9,000.00 | 0.6750 | 6,074.74 |
4 | 9,000.00 | 0.5921 | 5,328.72 |
5 | 9,000.00 | 0.5194 | 4,674.32 |
6 | 9,000.00 | 0.4556 | 4,100.28 |
NPV | 428.01 |
So, NPV of the project is $ 428.01
b). Calculating the Internal rate of Return:
Taking, Cost of capital(r) as 15%
NPV = -$ 509.66
As, at rate of 15% NPV is less than 0 & at 14% it is greater than O. Since, IRR is the rate at which NPV is O .
Now Calculating IRR:
IRR = 14.45%
c). As the IRR of the project is 14.45% but the firm's cost of capital is 14% and at this rate NPV of the project is also positive. Thus, you should accept the project.