In: Accounting
The following payments and receipts are related to land, land improvements, and buildings acquired for use in a wholesale apparel business. The receipts are identified by an asterisk.
a. |
Architect's and engineer's fees for plans and supervision |
80,000 |
||
b. |
Cost of filling and grading land |
30,000 |
||
c. |
Cost of removing building purchased with land in (e) |
10,000 |
||
d. |
Cost of paving parking lot to be used by customers |
25,000 |
||
e. |
Cost of real estate acquired as a plant site: Land ($375,000) and Building ($25,000) |
400,000 |
||
f. |
Cost of repairing windstorm damage during construction |
5,000 |
||
g. |
Cost of repairing vandalism damage during construction |
1,800 |
||
h. |
Cost of trees and shrubbery planted |
12,000 |
||
i. |
Delinquent real estate taxes on property, assumed by purchaser |
20,000 |
||
j. |
Fee paid to attorney for title search |
3,000 |
||
k. |
Finder's fee paid to real estate agency |
4,000 |
||
l. |
Interest incurred on building loan during construction |
40,000 |
||
m. |
Money borrowed to pay building contractor |
775,000 |
* |
|
n. |
Payment to building contractor for new building |
750,000 |
||
o. |
Proceeds from insurance company for windstorm and vandalism damage |
3,600 |
* |
|
p. |
Premium on one-year insurance policy during construction |
7,500 |
||
q. |
Proceeds from sale of salvage materials from old building |
4,000 |
* |
|
r. |
Refund of premium on insurance policy (p) canceled after 10 months |
1,250 |
* |
|
s. |
Special assessment paid to city for extension of water main to the property |
10,500 |
Instructions:
Item Land Land Building Other Accounts
Improvements
a. 80,000
The table will be prepared in the following manner:
Workings
Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you.