Question

In: Finance

a) discuss three potential flows with the regular payback method.  Discuss whether or not the discounted payback...

a) discuss three potential flows with the regular payback method.  Discuss whether or not the discounted payback method corrects all three flaws.

b) explain why the NPV of a relatively long-term project (one for which a high percentage of its cash flows occurs in the distant future) is more sensitive to changes in the WACC than that of a short-term project.

c) explain why IRR might be overly optimistic metric (give example of cash flows that might drive IRR artificially too high). What is the way to correct for inflationary IRR?

Solutions

Expert Solution

a) The regular payback method has three main flaws

1.Dollars received in differ-ent years are all given the same weight,

2.Cash flows beyond the payback yearare given no consideration regardless of how large they may be and lastly,

3. Unlike the NPV which shows us how much the project would increase the shareholder wealth or the IRR which would tell us how much a project would yield over the cost of capital, the payback method only tells us when the company would be receiving the investment back.

It corrects the first flaw however, it does nothing to correct the other two flaws.

b)  The NPV of a relatively long-term project, with a high percentage of its cashflows expected in the distant future, is more sensitive to changes in cost of capital than in the NPV of a short-term project

Because their payments willbe at the end of the project. The net present vale method discounts allcash flows at the projects cost of capital and then sums those cash flows at theend. Therefore is the payments are at the end of the project, any shift in the cost of capital, postive or negative, the NPV is more sensitive because thereis more time for change to occur.

c) IRR might be overly optimistic metric

A required rate of return is a rough estimate being made by the managers and the method of IRR is not completely based on required rate of return. Once IRR is found out, we can compare it with the hurdle rate. If the IRR is far away from the estimated required rate of return, the manager can safely take the decision on either side and also keep a room for estimation errors.

The real interest rate is 4%.

The inflation rate is 8%. What is the apparent interest rate,

i = i' + f + i'f = 0.04 + 0.08 + 0.04(0.08) = 12.32%


Related Solutions

Calculate the five different criteria for evaluating projects (regular payback, discounted payback, NPV, IRR, and MIRR)...
Calculate the five different criteria for evaluating projects (regular payback, discounted payback, NPV, IRR, and MIRR) for the two projects listed below. The firm’s WACC is 9.90%. If the projects are mutually exclusive and the firm has sufficient budget available, which project (if any) would you choose to proceed with, and why? (Hint: you may want to create the full cash flow table for each project to fully show your work.) periods 0 1 2 3 4 project Hay cash...
Use the discounted payback method, the net present value method, and the profitability index method to...
Use the discounted payback method, the net present value method, and the profitability index method to evaluate the following project: Year 0 Initial Investment 900,000 Year 1 Income 175,000 Year 2 Income 450,000 Year 3 Additional investment 100,000 Year 4 Income 630,000 Discount rate 7% DPB __________ years NPV ______________ PI ______________ Would you recommend that the board accept or reject this project? ________________ Accept or reject
Given the following cash flows for a capital project, calculate its payback period and discounted payback...
Given the following cash flows for a capital project, calculate its payback period and discounted payback period. The required rate of return is 8 percent. Year 0 1 2 3 4 5 Cash Flows $-37500 $11250 $11250 $15000 $6000 $6000 The discounted payback period is 0.16 year longer than the payback period. 0.80 year longer than the payback period. 1.27 years longer than the payback period. 1.85 years longer than the payback period.
Which of the following is(are) the advantage(s) of the discounted payback period method comparing to the...
Which of the following is(are) the advantage(s) of the discounted payback period method comparing to the normal form of payback period method? (There may be more than one correct answer. You will lose marks by choosing a wrong answer. The minimum mark for the question is zero.) Select one or more: a. The discounted payback period method does not bias against long-term projects. b. The discounted payback period method considers all cash flows of a project. c. The discounted payback...
Given the following two projects and their cash​ flows, ​, calculate the discounted payback period with...
Given the following two projects and their cash​ flows, ​, calculate the discounted payback period with a discount rate of 6%, 8​%,and 18​%. What do you notice about the payback period as the discount rate​ rises? Explain this relationship. With a discount rate of 6​%, the cash outflow for project A​ is:  A. recovered in 5 years. B.recovered in 3.16 years. C.recovered in 3 years. D.never fully recovered.  Cash Flow A B   Cost ​ $8,000 ​$100,000   Cash flow year 1...
What is the discounted payback period for the investment project that has the following cash flows,...
What is the discounted payback period for the investment project that has the following cash flows, if the discount rate is 14 percent? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) Year Cash Flows 0 -13779 1 4470 2 5005 3 5877 4 6626
Calculate the discounted payback period for the following cash flows. Investment = $300,000 Salvage Value =...
Calculate the discounted payback period for the following cash flows. Investment = $300,000 Salvage Value = 0 Service Life = 4 Years MARR = 5% n Cash Flow Cost of Capital Balance 0 -300,000 1 100,000 2 150,000 3 125,000 4 100,000
​(Discounted payback period​) ​ Gio's Restaurants is considering a project with the following expected cash​ flows:...
​(Discounted payback period​) ​ Gio's Restaurants is considering a project with the following expected cash​ flows: Year Project Cash Flow​ (millions) 0 ​$(240​) 1 100 2 75 3 100 4 110 If the​ project's appropriate discount rate is 11 ​percent, what is the​ project's discounted payback​ period? The​ project's discounted payback period is nothing years.  ​(Round to two decimal​ places.)
(Discounted payback period​) ​ Gio's Restaurants is considering a project with the following expected cash​ flows:...
(Discounted payback period​) ​ Gio's Restaurants is considering a project with the following expected cash​ flows: Year Project Cash Flow​ (millions) 0 ​$(150​) 1 90 2 70 3 90 4 100 If the​ project's appropriate discount rate is 12 ​percent, what is the​ project's discounted payback​ period? The​ project's discounted payback period is nothing years.  ​(Round to two decimal​ places.)
Distinguish between the payback period and the discounted payback period?
Distinguish between the payback period and the discounted payback period?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT