Question

In: Accounting

I have a question on standard costing. What should management do when actual cost exceeds the...

I have a question on standard costing. What should management do when actual cost exceeds the standard cost?

Solutions

Expert Solution

  • The general response and action by management if the actual cost exceeds the standard cost will be to CONTROL the excess cost in the coming period.
  • For doing that, the management needs to do a thorough analysis regarding the causes for such excess cost.
  • Variance Analysis is one of the method that can used to study the reason for excess of Actual cost over Standard Cost.

Variance Analysis involves calculation of various variances like:
-Material Price Variance, which tells the reason of difference between actual and standard cost due to price.
-Material Usage Variance, which tells the reason of difference between actual & standard cost due to usage of material.
-Labor variances [rate & efficiency] tells the management the reason for difference in actual cost and standard cost is due to wage rate and no. of hours consumed.

  • One the basis of the above Variance analysis and other steps, management can adopt following measures:

-Direct production department to use material more efficiently,
-instruct and help workforce to work more efficiently.
-look out for the rise in material prices and wage rate.
-revise the standard costs if circumstances ask for, like during inflationary conditions.


Related Solutions

1.            (A) What do you understand by “Standard Cost” and “Standard Costing”? Explain the different...
1.            (A) What do you understand by “Standard Cost” and “Standard Costing”? Explain the different types of Standards                 (B)   Material Variance: The Standard material cost of produce One unit of Al Safi Danone co. is: 1200 kg Material A             @ SR 5000 per kg 800 Kg Material B              @ SR 4000 per kg                During a period, 50 units of mixture X was produced from the usages of: 50 tons of Material A          @ SR 4...
1-When price exceeds average total cost in a competitive market, what change should we expect to...
1-When price exceeds average total cost in a competitive market, what change should we expect to see in the long run? a.Firms will exit. b.Firms will enter c.Market demand will shift to the right. 2-Consider a competitive market with identical firms that is in long-run equilibrium. Which of the following statements captures the sequence of events from the short run to the long run after demand increases? a.When demand increases, price rises in the short run, causing each firm to...
I have to do a cost production report in process costing. WIP on 1st is 250000...
I have to do a cost production report in process costing. WIP on 1st is 250000 units. During month 580000 units were added from another dept. Assembling finished 480000 and transferred them out. On the 31st 225000 units were still in wip inventory. The degree of completion of wip inventory at the 30 was DM 80%, DL 65%, and MOH 30%. I know all units have to be accounted for but there are not 830000 units between transferred out and...
I have question about the lower-of-cost-or-market (LCM) method . Can anyone share with me, when do...
I have question about the lower-of-cost-or-market (LCM) method . Can anyone share with me, when do we need to use this method, and what are its benefits? Does every inventory apply to this method? Thank you so much!
I have a question on an excercise from Cost Management, Blocher,, 7 ed. book. You are...
I have a question on an excercise from Cost Management, Blocher,, 7 ed. book. You are currently trying to decide between two cost structures for your business: one that has a greater proportion of short-term fixed costs and another that is more heavily weighted to variable costs. Estimated revenue and cost data for each alternative are as follows: Cost Structure Alternative #1 Alternative #2   Selling price per unit $ 50 $ 50   Variable cost per unit 35 30 Short-term fixed...
Project Management question: Prior to creating Status Report, what should I "double check"?
Project Management question: Prior to creating Status Report, what should I "double check"?
Question 2 – Chap. 10 Material and Labor Variances The following actual and standard cost data...
Question 2 – Chap. 10 Material and Labor Variances The following actual and standard cost data for direct material and direct labor relate to the production of 2,000 units of a product: Actual Costs Standard Costs Direct material 17,550 lbs. @ $5.30 18000 lbs. @ $5.10 Direct labor 27,900 hrs. @ $8.40 27,000 hrs. @ $8.70 Determine the following variances: Do not use negative signs with any of your answers. Next to each variance answer, select either "F" for Favorable...
what should a bussiness do when competitors have counterfeit goodshurting their sales?
what should a bussiness do when competitors have counterfeit goods hurting their sales?
Given the following information in standard costing: Standard 19,400 hours at $7.40 Actual 19,200 hours at...
Given the following information in standard costing: Standard 19,400 hours at $7.40 Actual 19,200 hours at $7.20 What is the direct labor rate variance? Multiple Choice $3,840 Unfavorable $3,840 Favorable $2,860 Unfavorable $2,860 Favorable
The Question just states what I have given in terms of coordinates but I do believe...
The Question just states what I have given in terms of coordinates but I do believe it's related to the shape I assume. (Angles, size, ect.) (a.) Obtain coordinates for: ATP, phosphatidylcholine, B-DNA. G-actin, the lambda represssor/DNA complex or Lac repressor/DNA complex, hemoglobin, myoglobin, HIv gp120, green fluorescent protein (GFP, and RNA polymerase. (b.) Using a structural viewing code like VMD, create a plot of each of the molecules from part (a)​. Their coordinates can be obtained through their PDB...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT