Calculate the following project, at cost of capital of 10%
| Years | Cash Flow (RM) |
| 0 | -10,000 |
| 1 | 2000 |
| 2 | 2000 |
| 3 | 4000 |
| 4 | 4000 |
| 5 | 5000 |
i) calculate NPV (8marks)
ii) calculate PI
iii) Justified should we accept or reject the project?
| Year | Cash flow | PVIF at 10% | PV at 10% | |
| 0 | $ (10,000) | 1 | $ (10,000) | |
| 1 | $ 2,000 | 0.90909 | $ 1,818 | |
| 2 | $ 2,000 | 0.82645 | $ 1,653 | |
| 3 | $ 4,000 | 0.75131 | $ 3,005 | |
| 4 | $ 4,000 | 0.68301 | $ 2,732 | |
| 5 | $ 5,000 | 0.62092 | $ 3,105 | |
| $ 2,313 | ||||
| i] | NPV = | $ 2,313 | ||
| ii] | PI = 12313/10000 = | 1.23 | ||
| iii] | The project can be accepted as the NPV is positive. | |||
| AS NPV is positive, PI>1. All projects with PI>1 can be accepted. |