Question

In: Finance

Calculate the following project, at cost of capital of 10% Years Cash Flow (RM) 0 -10,000...

Calculate the following project, at cost of capital of 10%

Years Cash Flow (RM)
0 -10,000
1 2000
2 2000
3 4000
4 4000
5 5000

i) calculate NPV (8marks)

ii) calculate PI

iii) Justified should we accept or reject the project?

Solutions

Expert Solution

Year Cash flow PVIF at 10% PV at 10%
0 $          (10,000) 1 $          (10,000)
1 $              2,000 0.90909 $               1,818
2 $              2,000 0.82645 $               1,653
3 $              4,000 0.75131 $               3,005
4 $              4,000 0.68301 $               2,732
5 $              5,000 0.62092 $               3,105
$               2,313
i] NPV = $              2,313
ii] PI = 12313/10000 = 1.23
iii] The project can be accepted as the NPV is positive.
AS NPV is positive, PI>1. All projects with PI>1 can be accepted.

Related Solutions

A project has the following cash flow. Years Costs Benefits 0 $10,000 0 1 $1,000 $5,000...
A project has the following cash flow. Years Costs Benefits 0 $10,000 0 1 $1,000 $5,000 2 $1,000 $5,000 3 $2,000 $6,000 4 $20,000 $3,000 a) Find net present value b) Discounted Benefit-Cost Ratio c)Net discounted Benefit-Cost Ratio discount ratio is 10%
An investment project cost $10,000 and has an annual cash flow of $2870 for six years....
An investment project cost $10,000 and has an annual cash flow of $2870 for six years. what is the discounted payback. If the discount rate is 0% what is the discounted payback. If the discount rate is 5% what is the discount and pay back. If the discount rate is 20%
1.       A project has the following cash flow. Year Costs Benefits 0 $10,000 0 1 0...
1.       A project has the following cash flow. Year Costs Benefits 0 $10,000 0 1 0 $5,000 2 $1,000 $5,000 3 0 $3,000 Assuming a discount rate of 10%, estimate the following: a)      Net Present Value (NPV) b)     Discounted Benefit-Cost Ratio c)      Net discounted Benefit-Cost Ratio d)     Is the project feasible? Explain your answer
A project has an initial cost of $58,425, expected net cash inflows of $10,000 per year for 10 years, and a cost of capital of 10%. What is the project's NPV?
A project has an initial cost of $58,425, expected net cash inflows of $10,000 per year for 10 years, and a cost of capital of 10%. What is the project's NPV? (Hint: Begin by constructing a time line.) Do not round your intermediate calculations. Round your answer to the nearest cent.
Given a project with the following cash flows and a cost of capital of 9%. Calculate...
Given a project with the following cash flows and a cost of capital of 9%. Calculate the NPV, IRR, MIRR, PI, payback and discounted payback. For each of the six calculations, give a brief interpretation of what it measures and how it should be used to evaluate a project. Should the project be accepted? Why or why not? Time Period Cash Flow      0 -$200,000      1 $50,000      2 $70,000      3 -$80,000      4 $75,000      5 $100,000...
Scott Enterprises is considering a project that has the following cash flow and cost of capital...
Scott Enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected. r: 11.00% Year 0 1 2 3 4 Cash flows −$1,000 $350 $350 $350 $350 Reed Enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that a project's expected NPV...
shannon co. is considering a project that has the following cash flow and cost of capital...
shannon co. is considering a project that has the following cash flow and cost of capital (r) data. What is the project discount paycheck? R+ 12.00% Year 0 1 2 3 CF -$1000 $450 $425 $400 $410 $400
reed enterprises is considering a project that has the following cash flow and cost of capital...
reed enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project NPV? note that a projects expected NPV can be negative, in which case it will be rejected. R: 11.00% Year 0 1 2 3 CF -1,065 $500 $475 $450
Robbins Inc. is considering a project that has the following cash flow and cost of capital...
Robbins Inc. is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected. r. 10.25% Year 0 1 2 3 4 5 Cash flows −$1,000 $300 $300 $300 $300 $300 a. $117.33 b. $105.89 c. $123.51 d. $130.01 e. $111.47 Reed Enterprises is considering a project that has the following cash flow and cost of capital (r)...
Robbins Inc. is considering a project that has the following cash flow and cost of capital...
Robbins Inc. is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected. r. 10.25% Year 0 1 2 3 4 5 Cash flows −$1,000 $300 $300 $300 $300 $300 a. $105.89 b. $111.47 c. $117.33 d. $123.51 e. $130.01 Reed Enterprises is considering a project that has the following cash flow and cost of capital (r)...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT