Question

In: Finance

Robbins Inc. is considering a project that has the following cash flow and cost of capital...

Robbins Inc. is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected.

r. 10.25%
Year

0

1

2

3

4

5

Cash flows

−$1,000

$300

$300

$300

$300

$300

a. $117.33
b. $105.89
c. $123.51
d. $130.01
e. $111.47

Reed Enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that a project's expected NPV can be negative, in which case it will be rejected.

r. 10.00%
Year

0

1

2

3

Cash flows

−$1,050

$450

$460

$470

a. $112.28
b. $92.37
c. $106.93
d. $101.84
e. $96.99

Spence Company is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's IRR can be less than the cost of capital or negative, in both cases it will be rejected.

Year

0

1

2

3

4

Cash flows

−$1,050

$400

$400

$400

$400

a. 15.61%
b. 21.20%
c. 14.05%
d. 19.27%
e. 17.34%

Solutions

Expert Solution

NPV = PV of Cash Inflows - PV of Cash Outflows

Part 1:

OPtion D Correct.

Part 2:

Part 3:

IRR is the rate at which PV of cash inflows and PV Cash Outflows are equal.

IRR = Rate at which least +ve NPV + [ NPV at that rate / change in NPV due to 1% inc in disc rate ] * 1%

= 19% + [ 5.43 / 19.94 ] * 1%

= 19% + 0.27%

= 19.27 %

OPtion D is correct


Related Solutions

Robbins Inc. is considering a project that has the following cash flow and cost of capital...
Robbins Inc. is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected. r. 10.25% Year 0 1 2 3 4 5 Cash flows −$1,000 $300 $300 $300 $300 $300 a. $105.89 b. $111.47 c. $117.33 d. $123.51 e. $130.01 Reed Enterprises is considering a project that has the following cash flow and cost of capital (r)...
Scott Enterprises is considering a project that has the following cash flow and cost of capital...
Scott Enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected. r: 11.00% Year 0 1 2 3 4 Cash flows −$1,000 $350 $350 $350 $350 Reed Enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that a project's expected NPV...
shannon co. is considering a project that has the following cash flow and cost of capital...
shannon co. is considering a project that has the following cash flow and cost of capital (r) data. What is the project discount paycheck? R+ 12.00% Year 0 1 2 3 CF -$1000 $450 $425 $400 $410 $400
reed enterprises is considering a project that has the following cash flow and cost of capital...
reed enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project NPV? note that a projects expected NPV can be negative, in which case it will be rejected. R: 11.00% Year 0 1 2 3 CF -1,065 $500 $475 $450
Craig's Car Wash Inc. is considering a project that has the following cash flow and cost...
Craig's Car Wash Inc. is considering a project that has the following cash flow and cost of capital (r) data. What is the project's discountedpayback? r. 10.00% Year 0 1 2 3 Cash flows −$900 $500 $500 $500 a. 2.09 years b. 1.88 years c. 2.52 years d. 2.78 years e. 2.29 years You have just landed an internship in the CFO's office of Hawkesworth Inc. Your first task is to estimate the Year 1 cash flow for a project...
Redesign Inc. is considering a project that has the following cash flow data. (a) What is...
Redesign Inc. is considering a project that has the following cash flow data. (a) What is the project's payback period? (b) What is the project's discounted payback period? Assume the cost of capital is 12%. Year 0 1 2 3 Cash flows -$500 $200 $200 $200
Susmel Inc. is considering a project that has the following cash flow data. What is the...
Susmel Inc. is considering a project that has the following cash flow data. What is the project's payback? No original investment given Year 0 1 2 3 Cash flows -$500 $150 $200 $300 Group of answer choices 1.90 years 2.63 years 2.50 years 1.93 years
Nichols Inc. is considering a project that has the following cash flow data. What is the...
Nichols Inc. is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's IRR can be less than the cost of capital or negative, in both cases it will be rejected. Year 0 1 2 3 4 5 Cash flows −$1,250 $325 $325 $325 $325 $325 a. 11.47% b. 10.40% c. 9.43% d. 10.92% e. 9.91% Westwood Painting Co. is considering a project that has the following cash flow and cost...
Masulis Inc. is considering a project that has the following cash flow and WACC data.  What is...
Masulis Inc. is considering a project that has the following cash flow and WACC data.  What is the project's discounted payback? WACC:  15.00% Year                            0                1                2                3                4     Cash flows              -$750         $525          $485          $445          $405 Hint: Discounted Payback period: The number of years required to recover a project’s cost. Cumulative cash flow computation takes into account the time value of money by using discounted cash flows. Group of answer choices 1.68 years 1.99 years 1.80 years 2.22 years 2.44 years
XYZ Inc. is considering a new project that has the following cash flow data. What is...
XYZ Inc. is considering a new project that has the following cash flow data. What is the project's IRR? Year 0 1 2 3 4 5 Cash Flows -1043 340 340 340 340 340
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT