In: Accounting
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:
| Direct Labor-Hours per Unit  | 
Annual Production  | 
||
| Hubs | 0.80 | 12,000 | units | 
| Sprockets | 0.40 | 48,000 | units | 
Additional information about the company follows:
Hubs require $35 in direct materials per unit, and Sprockets require $17.
The direct labor wage rate is $13 per hour.
Hubs require special equipment and are more complex to manufacture than Sprockets.
The ABC system has the following activity cost pools:
| Estimated | Activity | ||||
| Activity Cost Pool (Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
| Machine setups (number of setups) | $ | 20,250 | 125 | 100 | 225 | 
| Special processing (machine-hours) | $ | 148,000 | 3,700 | 0 | 3,700 | 
| General factory (organization-sustaining) | $ | 259,200 | NA | NA | NA | 
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
Requirement 1
| Calculation of Activity rates | |||||
| Activity Cost Pool | Activity driver | Overhead Cost | Expected Activity (B) | Activity rate (A/B) | |
| Machine setups | Number of Setups | $ 20,250.00 | 225 | $ 90.00 | Per Setups | 
| Special processing | Number of Machine hours | $ 1,48,000.00 | 3700 | $ 40.00 | Per Machine hours | 
Requirement 2
| Calculation of total cost | ||
| HUBS | Sprockets | |
| Direct material | $ 35.00 | $ 17.00 | 
| Direct labor | $ 10.40 | $ 5.20 | 
| Overheads | $ 13.27 | $ 0.19 | 
| Total Cost | $ 58.67 | $ 22.39 | 
Labor cost per unit = Cost per hour x Hours required per unit
Working
| Cost assigned to Hubs | |||
| Activity name | Activity Rates | Activity | ABC Cost | 
| (A) | (B) | (A x B) | |
| Machine setups | $ 90.00 | 125 | $ 11,250 | 
| Special processing | $ 40.00 | 3700 | $ 1,48,000.00 | 
| Total Overheads assigned | $ 1,59,250.00 | ||
| Production | 12000 | ||
| Overhead cost per unit | $ 13.27 | ||
| Cost assigned to Sockets | |||
| Activity name | Activity Rates | Activity | ABC Cost | 
| (A) | (B) | (A x B) | |
| Machine setups | $ 90.00 | 100 | $ 9,000.00 | 
| Special processing | $ 40.00 | 0 | $ - | 
| Total Overheads assigned | $ 9,000.00 | ||
| Production | $ 48,000.00 | ||
| Overhead cost per unit | $ 0.19 | ||