Question

In: Operations Management

Problem 4 (designed to be used with the NORMDIST tutorial) The following table represents a plan...

Problem 4 (designed to be used with the NORMDIST tutorial)

The following table represents a plan for a project:

JOB NO.

PREDECESSOR JOB(S)

a

m

b

A

-

5

6

7

B

A

3

4

5

C

A

6

7

14

D

A

4

5

12

E

B

1

4

7

F

C

2

3

4

G

D

6

9

15

H

E,F

4

6

8

I

H

3

7

17

J

G

4

5

6

K

I,J

6

8

10

  1. Construct the appropriate network diagram.
  2. Indicate the critical path.
  3. What is the expected completion time for the project?
  4. What is the probability the project will:
    take more than 43 days to complete;
    take less than 42 days to complete; and
    take between 37 and 42 days to complete?

USE AN EXCEL FILE

Solutions

Expert Solution

Answer a:

Answer b, c

Activity Optimistic time-a Expected completion time-m Pessimistic time-b Expected time= (a+4*m+ b)/6 Variance, (sigma)^2= (b-a/6)^2
A 5 6 7 6.00 0.11
B 3 4 5 4.00 0.11
C 6 7 14 8.00 1.78
D 4 5 12 6.00 1.78
E 1 4 7 4.00 1.00
F 2 3 4 3.00 0.11
G 6 9 15 9.50 2.25
H 4 6 8 6.00 0.44
I 3 7 17 8.00 5.44
J 4 5 6 5.00 0.11
K 6 8 10 8.00 0.44
Paths Duration Variance
ABEHIK 36.00
ACFHIK 39.00 8.333 CRITICAL PATH
ADGJK 35.50
Critical Path Duration (Expected Completion time of the project) Variance, σ2 Standard Deviation, σ (=sqrt(variance))
ACFHIK 39.00 8.333 2.887
Answer b Answer c

Answer d (i)

we will find the variance of the tasks which lie on critical path ACFHIK
mean project time (u) of critical path is= 39.00
Required completion time 43
standard deviation= sqrt(variance)= 2.887
because Z= (given completion time- u)/standard deviation 1.386
P(z)= using NORM.S.DIST(z,true) 0.9171
the probability of completing within 43 weeks, P(43) = 0.9171


Probability that the project will take more than 43 weeks to complete = 1- P(43) = 1-0.9171 = 0.0829 or 8.29%

Answer d (ii)

we will find the variance of the tasks which lie on critical path ACFHIK
mean project time (u) of critical path is= 39.00
Required completion time 42
standard deviation= sqrt(variance)= 2.887
because Z= (given completion time- u)/standard deviation 1.039
P(z)= using NORM.S.DIST(z,true) 0.8507
the probability of completing within 42 weeks, P(42)= 0.8507
or 85.07%



Answer d (iii)

we will find the variance of the tasks which lie on critical path ACFHIK
mean project time (u) of critical path is= 39.00
Required completion time 37
standard deviation= sqrt(variance)= 2.887
because Z= (given completion time- u)/standard deviation -0.693
P(z)= using NORM.S.DIST(z,true) 0.2442
the probability of completing within 37 weeks, P(37)= 0.2442


Probability that the project will take between 37 and 42 days to complete = P(42) - P(37) = 0.8507 - 0.2442 = 0.6065


=> Probability that the project will take between 37 and 42 days to complete =
0.6065 or 60.65%

Dear Student,
Please ask, if you have any doubts through the comment section. Do rate the answer.


Related Solutions

The table below will be used for the following five questions. The table represents the mean...
The table below will be used for the following five questions. The table represents the mean and standard deviation graduation rates, by candidate age, for a population of flight academies. ( No more data was provided). If you only know one method to solve a problem, please don't add a comment asking for more data! Age Mean Graduation Rate Standard Deviation 16 76.6 1.8 17 74.2 1.8 18 79.5 1.7 19 79.6 2.1 20 81.2 2.1 21 84.2 2.2 22...
The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a...
The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a m b 1 – 2 4 6 2 1 3 3 15 3 1 3 4 11 4 1 1 2 9 5 2 2 6 7 6 3 3 7 8 7 4 4 6 8 8 5,6 2 3 4 9 8 1 4 7 10 7 3 4 5 11 9,10 5 6 7    b. Indicate the critical path. 1-2-5-8-9-11...
Question 4: (Marks: 3) The following table represents the percentage of teenagers in some selected countries...
Question 4: (Marks: 3) The following table represents the percentage of teenagers in some selected countries who have used marijuana and the percentage who have used other drugs. Percentage Who Have Used Country Marijuana x Other Illegal Drugs y Czech Republic 22 4 Denmark 17 3 England 40 21 Finland 5 1 Ireland 37 16 Italy 19 8 Northern Ireland 23 14 Norway 6 3 Portugal 7 3 Scotland 53 31 United States 34 24 Determine the correlation coefficient, rounded...
tell whether each of the following 4 scenarios represents more an efficiency or equity problem 9....
tell whether each of the following 4 scenarios represents more an efficiency or equity problem 9. A free market advocate asks why a government healthcare mandate should require all people to purchase health insurance equivalent to a “fully loaded Lexus.” 10. A man with headaches, caused by stress at work, wants an MRI because he thinks he may have a tumor. The doctor says that there is almost zero probability that he has a tumor, and she warns him that...
  The following table represents the internet advertising revenue (in billions).      (x represents the time in years...
  The following table represents the internet advertising revenue (in billions).      (x represents the time in years since 2007) Round function values to nearest hundredth. Year 2007 2008 2009 2010 2011 2012 2013 2014 Internet Advertising Revenue (in billions) 21.2 23.4 22.7 25.8 28.5 32.6 36 40.5 a) Create a table of the r squared values together with each of your best fit curves (round to nearest thousandth). b) Copy the best of the best fit functions here. Explain how you...
The following table represents a demand schedule for farm workers.
The following table represents a demand schedule for farm workers.Wage/hrNumber of workers/acre hired$102846648210a. (10 points) On a fully-labeled graph, draw the demand curve for labor. Explain what the graph shows as if you were presenting it to a farm owner.b. (10 points) Suppose the current wage rate for farm workers is $4/hr. Calculate the elasticity of demand using the table above and the point-slope formula. Explain what this value of elasticity means as if you were presenting it to a...
Consider the three stocks in the following table.  Pt represents price at time t, and Qt represents...
Consider the three stocks in the following table.  Pt represents price at time t, and Qt represents shares outstanding at time t. Stock C splits two-for-one in the last period. Can you show work with steps and answer c please                         P 0       Q 0     P 1      Q 1     P 2      Q 2             A         80        100      85        100      90        100             B         60        200      45        200      40        200             C         110      200      120      200      60        400 c. Calculate the rate of return of the price-weighted index for the second period (t=1 to t=2).
The final part of the multiple regression output is the coefficients table that represents the following:...
The final part of the multiple regression output is the coefficients table that represents the following: The unstandardized regression coefficient (B). The standardized regression coefficient (beta or β). t and p values. All the above. Three correlation coefficients are displayed in the coefficients table. They include the following: The zero order correlation coefficient. The partial correlation coefficient. The part correlation coefficient. All of the above. If the value for tolerance is acceptable, one should proceed with interpreting the: Model summary....
The following data in the table below represents the relationship between the number of workers and...
The following data in the table below represents the relationship between the number of workers and their outputs in a company for a given day in the short-run: Workers Output P Marginal Product MP Variable Cost VC Fixed Cost FC Total Cost TC Average Variable Cost AVC Average Fixed Cost AFC Average Total Cost TC Marginal Cost MC 0 0 0 1 12 2 2 21 6 3 27 12 4 30 35 5 32 80 6 33 160 1-  ...
assume that the following table represents the daily supply of labor at a shirt factory in...
assume that the following table represents the daily supply of labor at a shirt factory in Haiti – and that labor’s marginal revenue product (MRP) is a constant amount of one hundred ten dollars ($110) per day over the relevant range of hiring considerations. QLabor        W = ACF          TCF                 MCF = ∆TCF/∆QLabor                 --------------------------------------------------------------------------------------------------------------                 30              $40/day                $1,200           ---------------------------------------------------------        $ 800/10 = $ 80           40               $50/day                $2,000           ---------------------------------------------------------        $1,000/10 = $100 50             ...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT