Question

In: Operations Management

Sensitivity analysis (20 marks, 2 marks per subquestion) A garden store prepares various grades of pine...

Sensitivity analysis (20 marks, 2 marks per subquestion)

A garden store prepares various grades of pine bark for mulch: nuggets (x1), mini-nuggets (x2), and chips (x3). The production process requires pine bark, machine time, and labour time. Each bag of nuggets requires 5 pounds of barks, 2 minutes of machine time, and 2 hours of labour time. To produce one bag of mini-nuggets, 6 pounds of barks, 4 minutes of machine time, and 4 hours of labour time are needed. The production of one bag of chips consumes 3 pounds of barks, 5 minutes of machine time, and 3 labour hours. The store has 600 pounds of barks, 660 minutes of machine time, and 480 hours of labour time available for the next production run. The demand for the three products is at least a total of 150 bags. The unit profit contribution of nuggets, mini-nuggets, and chips are $9, $9, and $6 per bag, respectively. The following linear programming model has been developed:

Decision variables

x1 = bags of nuggets to produce

x2 = bags of mini-nuggets to produce

x3 = bags of chips to produce

Objective function

Maximize        z = 9x1 + 9x2 + 6x3

Constraints:

Bark:               5x1+ 6x2 + 3x3< 600 pounds

Machine:         2x1+ 4x2 + 5x3< 660 minutes

Labour:           2x1+ 4x2 + 3x3< 480 hours

Demand:         x1+ x2 + x3> 150 bags

Non-negativity requirement: x1, x2, x3> 0

The Excel Solver sensitivity report is given on the next page, please answer the following questions based on the report.

NOTE:

1. EACH QUESTION THAT FOLLOWS REFERS TO THE ORIGINAL PROBLEM. THAT IS, EACH QUESTION IS INDEPENDENT OF THE OTHER QUESTIONS.

2. IF IT IS IMPOSSIBLE TO ANSWER THE QUESTION WITHOUT USING THE COMPUTER, YOU MUST STATE THAT IN YOUR ANSWER AND BRIEFLY EXPLAIN WHY.

3. NO MARKS WILL BE GIVEN FOR UNSUPPORTED ANSWERS. CALCULATIONS SHOULD BE DONE IN THE SPACE PROVIDED. CLEARLY PRINT YOUR ANSWER IN THE BOX PROVIDED.

4. ALL EXPLANATIONS MUST BE LIMITED TO 15 WORDS. ONLY THE FIRST 15 WORDS OF YOUR EXPLANATION WILL BE READ BY THE MARKER.

Sensitivity Report

(a) What are the optimal solution and its objective function value?

Answer

x1 =   x2 =   x3 =   

The objective function value is:

Explain where you find this information and show your calculation of the objective function value below (clearly PRINT no more than 15 words):

Calculation

(b) If the manager is able to obtain additional 50 minutes of machine time through better scheduling. What is the impact of this change on the objective function value?

Calculations

The new objective function value is:

Answer (Complete ONE appropriate box ONLY)

The impact on the objective function can be obtained without resolving the problem on the computer. Mark X here:        

The new objective function value is:

Explain (clearly PRINT no more than 15 words):

The problem must be re-solved on the computer. Mark X here:

Explain (clearly PRINT no more than 15 words):

(c) What is the impact on the optimal solution and the objective function value if the unit profit contribution for mini-nuggets increases from $9/bag to $10/bag?

Calculations

Answer (Complete ONE appropriate box ONLY)

Current solution remains optimal. Mark X here:       the profit contribution increases for mini-nuggets is less than reduced cost

The new objective function value is:  

Explain (clearly PRINT no more than 15 words):

The problem must be re-solved on the computer. Mark X here:

Explain (clearly PRINT no more than 15 words):

(d) The manager noticed that a new product, super-chip, is now available at its competitors’ stores. Based on his estimate, super-chips would be able to bring in a profit of $7.00 per bag, requiring 4 pounds of barks, 7 minutes of machine time, and 4 labour hours. Assume that the total demand for all products remains at 150 bags. What is the impact on the optimal solution and objective function value if the store manager decides to introduce this new product?

Calculations

Answer (Complete ONE appropriate box ONLY)

Current solution remains optimal. Mark X here:      

The new objective function value is:  

Explain (clearly PRINT no more than 15 words):

The problem must be re-solved on the computer. Mark X here:

Explain (clearly PRINT no more than 15 words):

(e) After the production process goes on for one week, the manager found that each bag of nuggets needs only 4 pounds of barks rather than 5. What is the impact on the objective function value if this error is corrected?

Calculations

Answer (Complete ONE appropriate box ONLY)

The impact on the objective function can be obtained without resolving the problem on the computer. Mark X here:        

The new objective function value is:

Explain (clearly PRINT no more than 15 words):

The problem must be re-solved on the computer. Mark X here:

Explain (clearly PRINT no more than 15 words):

(f) The manager now realizes that he has limited storage space for the product: he will not be able to stock up anything beyond 160 bags for the total of all products. What is the impact on the optimal solution?

Calculations

Answer (Complete ONE appropriate box ONLY)

Current solution remains optimal. Mark X here:      

The new objective function value is:  

Explain (clearly PRINT no more than 15 words):

The problem must be re-solved on the computer. Mark X here:

Explain (clearly PRINT no more than 15 words):

(g) If the supplier does not have enough barks and, hence, provides only 550 pounds of barks to the manager, what is the impact on the objective function value?

Calculations

Answer (Complete ONE appropriate box ONLY)

The impact on the objective function can be obtained without resolving the problem on the computer. Mark X here:        

The new objective function value is:  

Explain (clearly PRINT no more than 15 words):

The problem must be re-solved on the computer. Mark X here:

Explain (clearly PRINT no more than 15 words):

(h) What is the impact on the optimal solution and the objective function value if the unit profit contributions for nuggets and mini-nuggets both increase by 10%?

Calculations

Answer (Complete ONE appropriate box ONLY)

Current solution remains optimal. Mark X here:      

The new objective function value is:  

Explain (clearly PRINT no more than 15 words):

The problem must be re-solved on the computer. Mark X here:

Explain (clearly PRINT no more than 15 words):

(i) The manager has been notified that he should not worry about the availability of labour hours as another production line has been closed due to the recent economic turmoil. Therefore, there will be unlimited labour hours available (in the context of the size of this particular business) to him without any additional cost. What is the impact on the optimal solution and the objective function value?

Calculations

Answer (Complete ONE appropriate box ONLY)

Current solution remains optimal. Mark X here:      

The new objective function value is:  

Explain (clearly PRINT no more than 15 words):

The problem must be re-solved on the computer. Mark X here:

Explain (clearly PRINT no more than 15 words):

Solutions

Expert Solution

*****Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please*****

a)

X1 = 53.6842, X2 = 0 and X3 = 110.526

Objective function value = 9*53.6842+9*0+6*110.526 = 1146.3138

Value of X1,X2and X3 are found from Cells $B$10,$c$10 and $D$10

b)


The impact on the objective function can be obtained without resolving the problem on the computer. X
The new objective function value is: 1146.3138+50*0.157895 = 1154.20855 [ Shadow price of machine time 0.157895 is valid for another 86.6666666667 minutes(Allowable increase)]

c)

Current solution remains optimal. X [ As the profit contribution increase for mini-nuggets is less than reduced cost]   

The new objective function value is same as earlier 1146.3138

d)

The problem must be re-solved on the computer. X

It is not possible to estimate how much share will the new product grab within the existing product mix without resolving on the computer

e)

The problem must be re-solved on the computer. X

It is not possible to estimate the effect on objective function without resolving on the computer

f)

New Constraint x1 + x2 + x3 <= 160 plus the current optimal solution in it

New constraint, current optimal solution doesn't satisfy it.

g)

RHS by 50 pounds, allowable decreas 90

Shadow price $1.737/lb is valid

New OFV = old OFV +

RHS decreases within the Allowable decrease limit. Shadow price is valid

h)

Nugget profit Increase by 1% = increase by 0.9

Mini nugget profit increase by 1% = increase by 0.9

0.9/1 + 0.9/2.052 = 1.34 > 100%

Two simulataneous objective function coefficients, change, 100% rule is violated

i)

Remove the labour hour contraint, as it is non-binding no change

The problem must be re-solved on the computer. Mark X here: X

The new objective function value = 1146,314

Removal of a non-binding constraint and there will be no change.

*****Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please*****


Related Solutions

A garden store prepares various grades of wood chips for mulch for sale in various tonnages...
A garden store prepares various grades of wood chips for mulch for sale in various tonnages for delivery to large garden construction sites around town. The grades are (a) fine, (b) standard and (c) course. The process requires red gum, machine time, labour time, and storage space. The garden store owner has identified that the store can generate $90 profit per storage bin for fine, $90 for standard but only $60 for course chips. Each load of chips require inputs...
1) Describe "Sensitivity Analysis" within the Linear Programming context. Why is sensitivity analysis important? 2) Discuss...
1) Describe "Sensitivity Analysis" within the Linear Programming context. Why is sensitivity analysis important? 2) Discuss the impact of the changes in the following to your optimal solution: objective function coefficient resources or right-hand-side values. I need at least 200 words
QUESTION 3 (20 MARKS) QUESTION 3 (20 MARKS) An analysis of the Business School graduates found...
QUESTION 3 QUESTION 3 An analysis of the Business School graduates found that 210 out of 318 randomly selected graduates used An analysis of the Business School graduates found that 210 out of 318 randomly selected graduates used  a statistical inference technique during their first year of employment.a statistical inference technique during their first year of employment. (a) Calculate a 90% confidence interval for the proportion of graduates who used a statistical inference (a) Calculate a 90% confidence interval for the...
Question 2 [20 Marks] You are provided with the following information. Conduct an ABC analysis, categorising...
Question 2 [20 Marks] You are provided with the following information. Conduct an ABC analysis, categorising each item of stock appropriately. (80% = A, 15% = B, 5%=C Item no. Unit cost (R) Annual Demand 101 5 48 000 102 11 2000 103 15 300 104 8 800 105 7 4800 106 16 1200 107 70 18000 108 4 300 109 9 5000 110 12 500
QUESTION 2 (33 marks) (Module 5) Mist Fertilizer Ltd manufactures pre-mixed garden fertilizer for the garden...
QUESTION 2 (Module 5) Mist Fertilizer Ltd manufactures pre-mixed garden fertilizer for the garden centre retail market. The original ingredients including nitrogen, phosphorous and potassium components are mixed in the Primary Process Department (PPD). The fertilizer mix is then transferred to the Granulating and Blending Department (G&BD) for blending and drying (and where a final ingredient is added 70% through the process) and then the mix is transferred to the Bagging Department (BD) where the product is finished and bagged...
QUESTION 4 Regression Analysis Guide to marks: 20 marks – 5 for a, 10 for b,...
QUESTION 4 Regression Analysis Guide to marks: 20 marks – 5 for a, 10 for b, 3 for c, 2 for d Belinda, the accountant at Murray Manufacturing Company wants to identify cost drivers for support overhead costs. She has the impression that the staff spend a large part of their time ensuring that the equipment is correctly set up and checking the first units of production in each batch. Deborah has collected the following data for the past 12...
QUESTION 4 CVP Analysis Guide to marks: 20 marks – 4 for a, 4 for b,...
QUESTION 4 CVP Analysis Guide to marks: 20 marks – 4 for a, 4 for b, 4 for c, 8 for d Show all calculations to support your answers. A manufacturer can make two products, A and B. The following data are available:B Product A B Total Sales price per unit $12 $15 Variable cost per unit $8 $10 Total fixed costs/month $5000 (a)Calculate the unit contribution margin for each product. (b)This month the manufacturer will specialise in making only...
QUESTION 3 Regression Analysis Guide to marks: 20 marks – 5 for a, 10 for b,...
QUESTION 3 Regression Analysis Guide to marks: 20 marks – 5 for a, 10 for b, 3 for c, 2 for d Belinda, the accountant at Murray Manufacturing Company wants to identify cost drivers for support overhead costs. She has the impression that the staff spend a large part of their time ensuring that the equipment is correctly set up and checking the first units of production in each batch. Deborah has collected the following data for the past 12...
A typical lawn averages 21 blades of grass per square inch. A garden store sells an...
A typical lawn averages 21 blades of grass per square inch. A garden store sells an expensive fertilizer designed to transform an average lawn into a thick carpet within three weeks. To test the claim, a random sample of 32 average lawn plots were selected and treated with the fertilizer. Three weeks later the density of each plot was measured by counting the blades of grass per square inch. n = 32 and X = 22.4 Based on data from...
Explain in your own words the concept of the sensitivity analysis in 2 paragraphs.
Explain in your own words the concept of the sensitivity analysis in 2 paragraphs.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT