Question

In: Operations Management

There is a 95.05% chance the project below can be completed in X days or less....

There is a 95.05% chance the project below can be completed in X days or less. What is X? In the space provided below type in the values for each activity’s expected time, variance, list of critical activities, Project duration and value of X. Draw the network diagram

1. Expected value for each activity: BLANK-1

2. Variance for each activity: BLANK-2

3. Critical activities: BLANK-3

4. Project duration: BLANK-4

5. X = BLANK-5

ACTIVITY PREDECESSORS OPTIMISTIC (DAYS) Most likely(days) pessimistic (days)
A NONE 1 4 7
B NONE 2 2 2
C A 2 5 8
D A 3 4 5
E B,C 4 6 8
F B,C 0 0 6
G D,E 3 6

9

Solutions

Expert Solution

1. X = 24.1 OR 24


EXPLANATION:


EXPECTED TIME = (A + (4M) + B) / 6; WHERE A = OPTIMISTIC TIME, M = MOST LIKELY TIME, B = PESSIMISTIC TIME

VARIANCE = ((B - A) / 6)**2


ACTIVITY

EXPECTED TIME

VARIANCE

A

(1 + (4 * 4) + 7) / 6 = 4

((7 - 1) / 6)^2 = 1

B

(2 + (4 * 2) + 2) / 6 = 2

((2 - 2) / 6)^2 = 0

C

(2 + (4 * 5) + 8) / 6 = 5

((8 - 2) / 6)^2 = 1

D

(3 + (4 * 4) + 5) / 6 = 4

((5 - 3) / 6)^2 = 0.1111

E

(4 + (4 * 6) + 8) / 6 = 6

((8 - 4) / 6)^2 = 0.4444

F

(0 + (4 * 0) + 6) / 6 = 1

((6 - 0) / 6)^2 = 1

G

(3 + (4 * 6) + 9) / 6 = 6

((9 - 3) / 6)^2 = 1


CPM


ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

A

4

0

4

0

4

0

B

2

0

2

7

9

7

C

5

4

9

4

9

0

D

4

4

8

11

15

7

E

6

9

15

9

15

0

F

1

9

10

20

21

11

G

6

15

21

15

21

0

FORWARD PASS

We calculate the ES and EF values using a forward pass where the ES of an activity is the maximum EF of all the predecessor activities.

BACKWARD PASS

We calculate the LS and LF values using a backward pass where the LF of the activity is the minimum of all the successor activities.

SLACK

Slack is the value which is determined by subtracting EF from the LF or ES from the LS.

CRITICAL PATH

The critical path is the chain in the project network where the slack value of all the activities is 0, what this means is that any delay in these activities would result in delaying the entire project.

CRITICAL PATH = A-C-E-G

DURATION OF PROJECT = 21

CRITICAL PATH VARIANCE = SUM OF VARIANCE OF ACTIVITIES ON THE CRITICAL PATH = 3.4444

STDEV = SQRT(VARIANCE) = SQRT(3.4444) = 1.855909

DUE DATE = EXPECTED COMPLETION TIME + (Z * STANDARD DEVIATION OF CRITICAL PATH)

CONFIDENCE INTERVAL = 95.05

Z VALUE = NORMSINV(95.05 / 100) = 1.65

DUE TIME = 21 + (1.65 * 1.855909) = 24.1



Related Solutions

There is a 95.05% chance the project below can be completed in X days or less....
There is a 95.05% chance the project below can be completed in X days or less. What is X? In the space provided below type in the values for each activity’s expected time, variance, list of critical activities, Project duration and value of X. Draw the network diagram (diagram required only in the pdf file). Activity ----- Predecessors----------- Optimistic (days)----------- Most likely (days) ------------pessimistic(days) ------A ------------none ---------------------------1 --------------------------------4 --------------------------------------- 7 ------B------------none ----------------------------2 --------------------------------2 --------------------------------------- 2 ------C---------------A-------------------------------2 --------------------------------5 --------------------------------------- 8 ------D---------------A-------------------------------3...
A. An equipment installation job in the completion stage can be completed in 40 days of...
A. An equipment installation job in the completion stage can be completed in 40 days of 8 hour day work, with 40 men working. With the contract expiring in 30 days, the mechanical engineer contractor decided to add 10 men on the job, overtime not being permitted. If the liquidated damages is $2,000 per day of delay, and the men are paid $80 per day, will the engineer be able to complete the job on time? How much should he...
x+1 men will do the work in x+1 days, find the number of days that x+2 men can do the same work in.
x+1 men will do the work in x+1 days, find the number of days that x+2 men can do the same work in.
The data below represent the number of days​ absent, x, and the final​ grade, y, for...
The data below represent the number of days​ absent, x, and the final​ grade, y, for a sample of college students at a large university. Complete parts​ (a) through​ (e) below. Number of absences, x Final grade, y 0 88.5 1 85.6 2 82.5 3 79.9 4 76.9 5 72.4 6 62.6 7 67.1 8 64.1 9 61.1 ​(a) Find the​ least-squares regression line treating the number of​ absences, x, as the explanatory variable and the final​ grade, y, as...
The data below represent the number of days​ absent, x, and the final​ grade, y, for...
The data below represent the number of days​ absent, x, and the final​ grade, y, for a sample of college students at a large university. Complete parts​ (a) through​ (e) below. No. of​ absences, x 00 11 22 33 44 55 66 77 88 99 Final​ grade, y 88.188.1 85.285.2 82.282.2 79.879.8 76.876.8 72.372.3 62.862.8 67.267.2 64.364.3 61.461.4 ​(a) Find the​ least-squares regression line treating the number of​ absences, x, as the explanatory variable and the final​ grade, y, as...
The data below represent the number of days​ absent, x, and the final​ grade, y, for...
The data below represent the number of days​ absent, x, and the final​ grade, y, for a sample of college students at a large university. Complete parts​ (a) through​ (e) below. 0 1 2 3 4 5 6 7 8 9 89.0 86.1 83.0 80.5 77.4 73.0 63.3 67.8 64.8 61.8 (a) Find the​ least-squares regression line treating the number of​ absences, x, as the explanatory variable and the final​ grade, y, as the response variable. (b) Interpret the slope...
suppose there is a 32% chance of rain for each of the next two days, find...
suppose there is a 32% chance of rain for each of the next two days, find the following probabilities. a. it doesn't rain tomorrow? b it rains tomorrow and the next day? consider whether independent or dependent. c. it rains tomorrow or the next day? consider whether mutually exclusive or not. d. it rains at least once over the next two days?
This project should be completed using Excel (with formulas and linked data). Below are the deliverables:...
This project should be completed using Excel (with formulas and linked data). Below are the deliverables: 1. Prepare a Multi-Step Income Statement for the year ended 2018. This statement should be flexibly designed (formulas in cells). To the right of your dollars in this statement, show common-sized percentages based on sales (vertical analysis). 2. Show journal entries, adjusting entries and closing entries for the below additional information…none of the journal entries for 2018 have been posted to the ledger. 3....
On each of two days, Alan and Daisy can jointly undertake a project that yields a...
On each of two days, Alan and Daisy can jointly undertake a project that yields a profit of $150 per day. They alternately make proposals (at most one per day), starting with Daisy, about how to split this amount. If a proposal is rejected, they don’t work on the project that day; if it is accepted, the agreement applies to that day and the remaining day (if any) . Suppose, first, that both Alan and Daisy have no outside option...
On each of two days, Alan and Daisy can jointly undertake a project that yields a...
On each of two days, Alan and Daisy can jointly undertake a project that yields a profit of $150 per day. They alternately make proposals (at most one per day), starting with Daisy, about how to split this amount. If a proposal is rejected, they don’t work on the project that day; if it is accepted, the agreement applies to that day and the remaining day (if any) . Suppose, first, that both Alan and Daisy have no outside option...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT