Question

In: Operations Management

Plan production for a four-month period: February through May. For February and March, you should produce...

Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders occur. There are 90 workers on January 31. You are given the following demand forecast: February, 80,640; March, 60,480; April, 100,160; May, 40,160. Productivity is four units per worker hour, eight hours per day, 21 days per month. Assume zero inventory on February 1. Costs are hiring, $52 per new worker; layoff, $72 per worker laid off; inventory holding, $8 per unit-month; straight-time labor, $8 per hour; overtime, $12 per hour; backorder, $16 per unit.


Develop a production plan and calculate the total cost of this plan. Note: Assume any layoffs occur at beginning of next month. (Leave no cells blank - be certain to enter "0" wherever required. Negative values should be indicated by a minus sign. Round your answers to the nearest whole number.)


February March April May
Forecast 80,640 60,480 100,160 40,160
Beginning inventory
Production required
Production hours required
Regular workforce
Regular production
Overtime hours
Overtime production
Total production
Ending inventory
Ending backorders
Workers hired
Workers laid off
February March April May
Straight time $ $ $ $
Overtime
Inventory
Backorder
Hiring
Layoff
Total $ $ $ $
Total cost $

Solutions

Expert Solution

For February and March we have to used exact demand production (chase strategy)

For April and May we have to maintain the workforce and go with overtime (with a maximum cap of 5000 hours overtime)

Beginning inventory for February = 0

Workforce in January = 90

Productivity = 4 units per worker hour

Eight hours a day and 21 days per month

Hiring cost = $52 per new worker

Layoff cost = $72 per worker

Inventory holding = $8 per unit per month

Straight time labor = $8 per hour

Overtime = $12 per hour

Backorder = $16 per unit

Concepts uses:

Production required = forecast + previous month back order (if any) – beginning inventory (if any)

Production hours required = production required/4

Regular production = regular workforce * 4 (for productivity) * 8 (daily work hours) * 21 (days in a month)

Overtime hours = minimum between (5000, (required production – regular production)/4)

Overtime production = overtime hours * 4

Total production = regular production + overtime production

Ending Inventory = Maximum between (0, total production – production required)

Ending Backorders = Maximum between (0, production required – total production)

February

March

April

May

Forecast

80640

60480

100160

40160

Beginning Inventory

0

0

0

0

Production Required

80640

60480

100160

59840 (forecast + previous backorder)

Production hours Required

20160

15120

25040

14960

Regular workforce

120

90

90

90

Regular production

80640

60480

60480

60480

Overtime hours

0

0

5000

0

Overtime Production

0

0

20000

0

Total Production

80640

60480

80480

60480

Ending Inventory

0

0

0

640

Ending Backorders

0

0

19680

0

Workers Hired

30

0

0

0

Workers Laid off

0

30

0

0

Cost table:

Straight time = regular workforce * 8 (hours a day) * 21 (days a month) * 8 (straight production cost)

Overtime = overtime hours * 12 (overtime cost)

Inventory = ending inventory * 8 (inventory holding cost)

Backorder = ending backorder * 16 (per unit back order cost)

February

March

April

May

Straight time

$161280

$120960

$120960

$120960

Overtime

0

0

$60000

0

Inventory

0

0

0

$5120

Backorder

0

0

$314880

0

Hiring

$1560

0

0

0

Layoff

0

$2160

0

0

Total

$162840

$123120

$495840

$126080

Total cost

$907880

.

IF YOU HAVE ANY DOUBT, KINDLY COMMENT. I WOULD LOVE TO HELP YOU!!!

IF YOU LIKE THE ANSWER, PLEASE GIVE AN UP-VOTE OR THUMB UP. THIS WILL ENCOURAGE ME TO ANSWER MORE!!


Related Solutions

Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Problem 8-8 Plan production for a four-month period: February through May. For February and March, you...
Problem 8-8 Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply,...
For the 12 month period February 2018 through January 2019, the number of degree days that...
For the 12 month period February 2018 through January 2019, the number of degree days that accrued for the Amherst, MA area was 5903. Many houses in New England heat with oil. Suppose a reasonable-size house required a total of 1400 gallons of oil for that recent entire 12- month period. Suppose also that heating oil is priced at $2.90 per gallon. A. What was the total cost to purchase the oil to heat the house for the entire year?...
Month Sales January $100,000 February $120,000 March $150,000 April $180,000 May $150,000 June $120,000 July $150,000...
Month Sales January $100,000 February $120,000 March $150,000 April $180,000 May $150,000 June $120,000 July $150,000 August $180,000 Actual November and December 2018 sales were $200,000 and $90,000, respectively. Cash sales are 45% of the total and the rest are on credit. About 70% of credit sales are typically collected one month after the sale and 30% the second month. Monthly inventory purchases represent 50% of the following month’s sales. The firm pays 40% of its inventory purchases in cash...
Month Patient Days January 543 February 528 March 531 April 542 May 558 June 545 July...
Month Patient Days January 543 February 528 March 531 April 542 May 558 June 545 July 543 August 550 September 546 October 540 November 535 December 529 Predict naïve forecast of patient days for February and June. Predict the patient days for January, using a four-period moving average. Predict the patient days for January, using the six-period moving average. Plot the actual data and the results of the four period and the six-period moving averages. Which is a better predictor?
This exercise must be completed on the four subscales below, and you should, therefore, produce four...
This exercise must be completed on the four subscales below, and you should, therefore, produce four reliability analyses. Subscale 1 (Fearof statistics): items 1, 3, 4, 5, 12, 16, 20, 21 Subscale 2 (Peerevaluation): items 2, 9, 19, 22, 23 Subscale 3 (Fearof computers): items 6, 7, 10, 13, 14, 15, 18 Subscale 4 (Fear of mathematics): items 8, 11, 17
This exercise must be completed on the four subscales below, and you should, therefore, produce four...
This exercise must be completed on the four subscales below, and you should, therefore, produce four reliability analyses. o Subscale 1 (Fearof statistics): items 1, 3, 4, 5, 12, 16, 20, 21 o Subscale 2 (Peerevaluation): items 2, 9, 19, 22, 23 o Subscale 3 (Fearof computers): items 6, 7, 10, 13, 14, 15, 18 o Subscale 4 (Fear of mathematics): items 8, 11, 17
Your parents plan to give you $200 a month for four years while you are in...
Your parents plan to give you $200 a month for four years while you are in college. At a discount rate of 6 percent, compounded monthly, what are these payments worth to you when you first start college? $8,797.40 $8,409.56 $8,198.79 $8,516.06 $8,279.32
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT