Question

In: Accounting

What is the difference between IRR and MIRR ? Explain with an example.

What is the difference between IRR and MIRR ? Explain with an example.

Solutions

Expert Solution

IRR :- INTERNAL RATE OF RETURN

internal rate of return is a measure in capital budgeting parlance which is used for estimating the profit that can be obtained from the investments.

Internal rate of return is a type of discount rate that is instrumental in making the net present value of all the cash flows from any project equal to zero.

in simple words, it can be referred to as the compounded annual rate of return that can be earned on an investment or a project.

MIRR :- MODIFIED INTERNAL RATE OF RETURN

the modified internal rate of return presumes the constructive cash flows are reinvested to the company's cost of capital and that the inceptive outlays are funded at the company's financing cost. It is a development over IRR and changes many deficiency is like different IRR is deleted, checks reinvestment price issue and initiates outcome, that is in a linked with the today value method.

Differences between IRR and MIRR :-

Particulars IRR MIRR
Definition IRR is the discount amount for investment that corresponds between initial capital outlay and the present value of predicted cash flows MIRR is the price in the investment plan that equalizers the latest value of cash inflows to the first catch out room
Waht does it mean? discount rate at which NPV of all cash flows from a project becomes zero it is a modified form of CRR in which the npv of the inflow is equal to the outflow
Basis of assumption assumes that positive cash flows from a project are reinvested on the same rate of return as that of investment it assumes that positive cash flows are invested based on the cost of capital of the firm
Precision IRR is comparatively less precise in calculating the rate of return MIRR is much precise than IRR

IRR = [( cashflows )÷ (1+r)i] - initial investment

r = rate of interest

i = time period

MIRR = [(FVPCF) ÷ (PVNCF)]1 ÷n - 1

FVPCF = future value of positive cashflows at reinvestment rate

PVNCF = present value negative cash flows at finance rate

n = number of periods

These are all the information required to solve the above given question.

If there is any clarifications required regarding the above provided answer, please mention them in comment box.

I hope, all the above mention information and explanations are useful and helpful to you.

Thank you.


Related Solutions

What is the difference between IRR and RADR ? What does IRR-RADR = (-) value mean...
What is the difference between IRR and RADR ? What does IRR-RADR = (-) value mean and IRR-RADR=(+) value mean as well ?
What is the reasoning for calculating a MIRR instead of just the IRR? Are there any...
What is the reasoning for calculating a MIRR instead of just the IRR? Are there any circumstances in which the two methods provide the same solution?
a) List and explain three problems with IRR, and whether or not MIRR solves each problem....
a) List and explain three problems with IRR, and whether or not MIRR solves each problem. Your explanation should include why these are problems (why we can't just ignore these issues). b) List and explain (in one to two sentences each) two problems with payback period that are not problems for NPV. Your explanation should include why these are problems (why we can't just ignore these issues). c) There are three characteristics that we need to know about a project's...
What is NPV, IRR, PI, MIRR of a project with the following cash flows if the...
What is NPV, IRR, PI, MIRR of a project with the following cash flows if the discount rate is 14 percent? Year CF 0 -18,000    1 5000 2 7500 3 8400 4 2100 Also upload your excel files showing your work.
What is the difference between current ratio and quick ratio. Explain with example ?
What is the difference between current ratio and quick ratio. Explain with example ?
For the data shown, what is the Delta IRR for the difference between the cash flows...
For the data shown, what is the Delta IRR for the difference between the cash flows of the higher initial cost machine and the lower initial cost machine? The increase in costs and benefits trend does not change when a new machine is put into action (The cost keep rising at 4% every year and the benefits increase by 5% every year for the 12 year project life). Machine A Machine B Initial cost $65,000 $17,500 Life in years 12...
explain the difference between a parameter and statistic using an example
explain the difference between a parameter and statistic using an example
Explain how to calculate the capital budgeting criterion (in excel) : NPV, IRR, MIRR, Payback, Discounted...
Explain how to calculate the capital budgeting criterion (in excel) : NPV, IRR, MIRR, Payback, Discounted Payback, Crossover Rate, and decide between mutually exclusive and/or independent projects
What are the pros and cons of the various capital budgeting decision methods (NPV, IRR, MIRR,...
What are the pros and cons of the various capital budgeting decision methods (NPV, IRR, MIRR, PB, DPB)? If you had to pick one method to use for all project valuation situations, which one would you pick, and why? Please explain your answer! I am trying to understand the concept.
(2pts) What is the difference between absolute and relative muscular endurance? Use an example to explain...
(2pts) What is the difference between absolute and relative muscular endurance? Use an example to explain the difference. (1pt) What is the goal of the McGill torso test?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT