Question

In: Finance

a) List and explain three problems with IRR, and whether or not MIRR solves each problem....

a) List and explain three problems with IRR, and whether or not MIRR solves each problem. Your explanation should include why these are problems (why we can't just ignore these issues).

b) List and explain (in one to two sentences each) two problems with payback period that are not problems for NPV. Your explanation should include why these are problems (why we can't just ignore these issues).

c) There are three characteristics that we need to know about a project's cash flows in order to properly value them (correctly calculate the present value). Name the three things, and briefly explain why we need to know each characteristic.

Solutions

Expert Solution

(a) Problems with IRR

1) IRR is that rate at which NPV of the project is zero i.e. present value of cash inflows equals present value of cahs outflows. However, when a project has varying time spans for cash flows i.e. one duration for positive cash flow and another duration for negative cash flow, IRR gives two rates. MIRR overcomes this problem as MIRR considers considers terminal cash inflows

2) If projects are mutually exclusive which means if one project is to be selected then other project will have to be skipped. In this case IRR method suggest that project with High IRR should be accepted but IRR method does not consider the volume of cash inflows i.e. economies of scale. MIRR method does not overcome this problem as like IRR , MIRR also takes decision on the basis that project with highest MIRR should be selected MIRR,too, ignore the size of the NPV: e.g. project A has IRR of 8% and NPV of 2000 whereas Project B has IRR of 6 % and NPV of 4000 , in this case both IRR and MIRR would lead to rejection of Project B though Project B should be selected as having high NPV of the two projects.

3) IRR takes into consideration internal factors and does not consider cost of capital or rate of inflation as this rate is found internally taking into account cash outflow in the beginning of the project and cash inflows of the project. This problem can be overcomed by using MIRR which takes into account cost of capital i.e. rate of return is calculated on the basis of cost of capital.

These problems with IRR cannot be ignored because these may lead to selection of a project which otherwise would have not been accepted if other methods had been used.

(b) Two main problems with Pay Back Period Method

1) It does not take into consideration time value of money and this problem cannot be ignored as generally projects involve huge investments and particularly if they are to be run for longer periods, pay back period method may lead to wrong decision about acceptance or rejection of the project.

2) Another major problem with this project it ignores the cash flows which arise after pay back period which may lead to misleading evaluation of the project.

(c) Three characteriestics which should be known about cash flows

1) Timing of the cash flow While considering cash flows it should also be noted that whether more amount of cash flows is occuring at early years of investment or later years of investment. projects generating cash flows during early years of investment should be preferred to projects generating cash flows at later years other things remaining the same.

2) Size of the cash flows should also be considered along with timing of the cash flows. This means cash flows of large size (more amount) should be preferred to cash flows of small size in early year as with passage of time value of money decreases so later cash flows will give generate less value.

3) Opportunity costs should also be considered i.e what would be amount, timing and present value of cash flow if investment would have been made in some other project or opportunity available.


Related Solutions

List and explain (in one to two sentences each) three problems with IRR, and whether or...
List and explain (in one to two sentences each) three problems with IRR, and whether or not MIRR solves each problem (you can note this for each problem after you explain the problem). Your explanation should include why these are problems (why we can't just ignore these issues).
What is the difference between IRR and MIRR ? Explain with an example.
What is the difference between IRR and MIRR ? Explain with an example.
SHOW YOUR WORK AND EXPLAIN PLEASE! Complete problems: NPV, IRR, MIRR, Profitability Index, Payback, Discounted Payback...
SHOW YOUR WORK AND EXPLAIN PLEASE! Complete problems: NPV, IRR, MIRR, Profitability Index, Payback, Discounted Payback A project has an initial cost of $60,000, expected net cash inflows of $10,000 per year for 8 years, and a cost of capital of 12%. Show your work. a. What is the project’s NPV? (Hint: Begin by constructing a timeline). b. What is the project’s IRR? c. What is the project’s MIRR? d. What is the project’s PI? e. What is the project’s...
compare and contrast the NPV, IRR, and MIRR. what is the difference between the three measures...
compare and contrast the NPV, IRR, and MIRR. what is the difference between the three measures and what each one calculates and represents
. Complete problems: NPV, IRR, MIRR, Profitability Index, Payback, Discounted Payback A project has an initial...
. Complete problems: NPV, IRR, MIRR, Profitability Index, Payback, Discounted Payback A project has an initial cost of $60,000, expected net cash inflows of $10,000 per year for 8 years, and a cost of capital of 12%. Show your work. a. What is the project’s NPV? (Hint: Begin by constructing a timeline). b. What is the project’s IRR? c. What is the project’s MIRR? d. What is the project’s PI? e. What is the project’s payback period? f. What is...
Calculate the IRR, the NPV, and the MIRR for each project, and indicate the correct accept/reject decision for each.
11.  Problem 10-08 (NPVs, IRRs, and MIRRs for Independent Projects)NPVs, IRRs, and MIRRs for Independent ProjectsEdelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $18,000, and that for the pulley system is $22,000. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows:YearTruckPulley1$5,100$7,50025,1007,50035,1007,50045,1007,50055,1007,500Calculate the IRR, the NPV, and the MIRR for each project,...
Set up a spreadsheet that implements the secant method and then solves each of the problems....
Set up a spreadsheet that implements the secant method and then solves each of the problems. Use the graph of each function to select an initial guess. Recall the iteration formula for the secant method: X^k+1=x^k-[f(x^k)/f(x^k)-f(x^k-1)](x^k-x^k-1) Put the formula for the function under the heading f(xk-1) and f(xk). In the cell under xk+1, put the secant method iteration formula. In the second row, replace the previous xk-1 with xk and then xk with xk+1. Now copy the two formulas down...
What does IRR mean? How it is estimated? Be specific. Are there problems with IRR? Explain.
What does IRR mean? How it is estimated? Be specific. Are there problems with IRR? Explain.
Describe and explain the significance of each of the following: payback period, internal rate of return (IRR), modified internal rate of return (MIRR)
  Describe and explain the significance of each of the following: payback period, internal rate of return (IRR), modified internal rate of return (MIRR), net present value (NPV), and profitability index (PI). Explain. Provide examples for better clarity. Discuss the notions of conventional and nonconventional cash flows in capital budgeting. Which investment evaluation criteria would you use for unconventional cash flows and why? Provide a fictitious unconventional cash flow example and apply the payback period, NPV, IRR, MIRR, and PI...
Explain how to calculate the capital budgeting criterion (in excel) : NPV, IRR, MIRR, Payback, Discounted...
Explain how to calculate the capital budgeting criterion (in excel) : NPV, IRR, MIRR, Payback, Discounted Payback, Crossover Rate, and decide between mutually exclusive and/or independent projects
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT