Question

In: Economics

You are on the phone with the project sponsor of a project you are managing. He...

  1. You are on the phone with the project sponsor of a project you are managing. He informs you that he accepted the role reluctantly and now, two months into this eight month project, he is considering withdrawing as a project sponsor. He does not see the need for this role and is extremely busy with his other responsibilities. How do you respond?
  2. You are surprised when your project team "pushes back" on your request for them to schedule a full-day offsite to work with you to develop a risk management plan. They state that they are simply too busy to afford time for this activity. And besides, they feel that if something unforeseen occurs, it is your responsibility to react to it. How do you respond to your team?

Solutions

Expert Solution

1. Being a manager of a project that is assigned to me first of all i would try to find a competent person as a project sponsor and then fix a deal with him. Since we have a project in hand so it is quite essential as the reputation of the company and myself is attached with this project.

Now if the project sponsor wants to withdraw he is bounded by a contract. Still if he wants to give up the role then it becomes a necessity to find a suitable match. It is required to be calm and very precise in choosing the sponsor. At the same time i would have filed a law suit against the old sponsor.

2. As a manager of the team it is required of me to completely assure the safety and security of my team. This can be done by making an insurance for the team members that will assure them of their offsite work and will willingly come to join the team. Secondly an added incentive in cash or kind can be introduced for them or arrangement of loans for future help from the company can also be done. These are progressive measures. Along with these progressive meansures regressive measures like penalty charges, amount cut from salary, incentive cut also be introduced to allow them to forcefully join me in the team for the work. But this decreases the willingness to work of the employees. As a result the efficiency gets affected.


Related Solutions

a.Imagine that the sponsor of Online Asset Management System project, which you are currently managing, suddenly...
a.Imagine that the sponsor of Online Asset Management System project, which you are currently managing, suddenly decides to terminate the project early. What are two possible reasons for this decision? b. Imagine you are creating a lessons learned database for the Online Asset Management System you have recently completed. What would you list as your top 3 issues? Your top 3 successes? (3 + 3 mark)
create a project charter GENERAL PROJECT INFORMATION Project Name: Project Sponsor: Project Manager: Email Address: Phone...
create a project charter GENERAL PROJECT INFORMATION Project Name: Project Sponsor: Project Manager: Email Address: Phone Number: Organizational Unit: Process Impacted: Expected Start Date: Expected Completion Date: Expected Savings: Estimated Costs: PROBLEM, ISSUE, GOALS, OBJECTIVES, DELIVERABLES Problem or Issue: Purpose of Project: Business Case: Goals/Metrics: Expected Deliverables: PROJECT SCOPE & SCHEDULE Within Scope Outside of Scope PROJECT RESOURCES & COSTS Project Team Support Resources Special Needs PROJECT BENEFITS & CUSTOMERS Process Owner Key Stakeholders Final Customers Expected Benefits PROJECT RISKS,...
Your project sponsor is concerned about the duration of your project schedule and thinks that you...
Your project sponsor is concerned about the duration of your project schedule and thinks that you need to cut some time out of the schedule. He thinks that all of the testing that you have included in the plan is not necessary. How would you respond to this? What are the risks of removing the testing with regard to the overall project?
CREATING THE PROJECT SCHEDULE - PROJECT MANAGEMENT Your project sponsor is concerned about the duration of...
CREATING THE PROJECT SCHEDULE - PROJECT MANAGEMENT Your project sponsor is concerned about the duration of your project schedule and thinks that you need to cut some time out of the schedule. He thinks that all of the testing that you have included in the plan is not necessary. How would you respond to this? What are the risks of removing the testing with regard to the overall project?
You are working on a project to install 200 new computers for your department. Your sponsor...
You are working on a project to install 200 new computers for your department. Your sponsor is the CTO (Chief Technology Officer). Although the CTO is your key stakeholder, you know that many other individuals will affect the success or failure of your project. This is the first time you have worked with this CTO, and you have heard that he often changes his mind about the requirements and due date. In fact, you heard that a PM who failed...
Assume your local congressman calls you for some economic advice. He wants to sponsor legislation to...
Assume your local congressman calls you for some economic advice. He wants to sponsor legislation to increase public spending on such common medical interventions as because he’s been told early detection saves money: Getting all children the right immunizations at the right time, before they turn 24 months, Screening for hypertension Screening for cervical cancer Smoking cessation classes How would you advise him?
What are the roles of a project sponsor and the approval committee during the different SDLC...
What are the roles of a project sponsor and the approval committee during the different SDLC phases?
Analyzing Project Viability. What are the responsibilities of the project sponsor(s) if a project—when proposed/undertaken—requires new...
Analyzing Project Viability. What are the responsibilities of the project sponsor(s) if a project—when proposed/undertaken—requires new or unproven technologies? What are some of challenges that may arise even if the project’s technology has been previously demonstrated or is deemed standardized? Note: Respond in a short essay of approximately 150 -200 words.
. Explain role of the following project stakeholders i) Functional managers ii) Project sponsor (4 Marks)
. Explain role of the following project stakeholders i) Functional managers ii) Project sponsor
Your project sponsor is Shirley, the Chief Information Officer. She is a member of the hospital...
Your project sponsor is Shirley, the Chief Information Officer. She is a member of the hospital leadership team who controls the IT budget and resources. She understands the requirements and how the portal will integrate with other systems. Shirley wants you to use agile project management practices to deliver the functionality in increments, ensuring a high-quality solution that meets user needs. You review the requirements and technical approach drafted by the IT team and they seem complete. Shirley is anxious...