Question

In: Operations Management

Moore Housing Contractors Moore Housing Contractors is negotiating a deal with Countryside Realtors to build six...

Moore Housing Contractors

Moore Housing Contractors is negotiating a deal with Countryside Realtors to build six houses in a new development. Countryside wants Moore Contractors to start in late winter or early spring   when the weather begins to moderate and build through the summer into the fall. The summer months are a busy time for the realty company, and it believes it can sell the houses almost as soon as they are ready-sometimes before. The houses all have similar floor plans and are of approximately equal size; only the exteriors are noticeably different. The completion time is so critical for Countryside Realtors that it is insisting a project management network accompany the con­ tractor's bid for the job with an estimate of the completion time for a house. The realtor also needs to be able to plan its offerings and marketing for the summer. The realtor wants each house to be completed within 45 days after it is started. If a house is not completed within this time frame, the realtor wants to be able to charge the contractor a penalty. Mary and Sandy Moore, the president and vice president of Moore Housing Contractors, are concerned about the prospect of a penalty. They want to be confident they can meet the deadline house before entering into any agreement with a penalty involved. (If there is a reasonable likelihood they cannot house within 45 days, they want to increase their bid to potential penalty charges.)

The Moores are experienced homebuilders, so it was not difficult for them to list the activities involved in building a house or to estimate activity times. However, they made estimates conservatively and tended to increase their pessimistic estimates to compensate for the possibility of bad weather and variations in their workforce. Following is a list of the activities for building a house and the activity time estimates:

Activity

Description

Immediate Predecessor

Time (days)

Optimistic

a

Most Likely

m

Pessimistic

b

a

b

c

d

e

f

g

h

i

j

k

l

m

n

o

p

q

r

s

t

u

v

w

x

Excavation, pour footers

Lay foundation

Frame and roof

Lay drain tiles

Sewer (floor) drains

Install Insulation

Pour basement floor

Rough Plumbing, pipes

Install windows

Rough electrical wiring

Install furnace, air conditioner

Exterior brickwork

Install plasterboard, mud, plaster

Roof shingles, flashing

Attach gutter, downspouts

Grading

Lay subflooring

Lay driveway, walks, landscape

Finish carpentry

Kitchen cabinetry, sink, and appliances

Bathroom cabinetry, fixtures

Painting (interior and exterior)

Finish wood floors, lay carpet

Final electrical, light fixtures

a

b

b

b

c

e

e

f

f

c, g

i

j, h, k

l

n

d, o

m

p

q

q

q

t, u

v, s

v

3

2

2

1

1

2

2

2

1

1

3

5

6

2

1

2

3

4

3

2

2

4

2

1

4

3

4

2

2

4

3

4

3

2

5

6

8

3

2

3

4

6

5

4

3

6

5

3

6

5

5

4

3

5

5

7

4

4

8

10

12

6

5

7

6

10

12

8

6

10

8

4

  1. Develop a CPM/PERT network for Moore House Contractors and determine the probability that the contractors can complete a house within 45 days. Does it appear that the Moores might need to increase their bid to compensate for potential penalties?

  1. Indicate which project activities Moore Contractors should be particularly diligent to keep on schedule by making sure workers and materials are always available. Also, indicate which activities the company might shift workers from as the need arises.

Solutions

Expert Solution

Q) Develop a CPM/PERT network for Moore House Contractors and determine the probability that the contractors can complete a house within 45 days. Does it appear that the Moores might need to increase their bid to compensate for potential penalties?

Ans- PERT network chart is following

Probability of completing the project within 45 days = 36.5%

Yes, the probability of completing the project in 45 days is low, therefore there is 63.5% probability of overshooting the deadline and incurring penalty cost. Therefore bid should be revised to account for the penalty cost.

Q) Indicate which project activities Moore Contractors should be particularly diligent to keep on schedule by making sure workers and materials are always available. Also, indicate which activities the company might shift workers from as the need arises.

Ans-Critical path is a-b-e-g-k-m-q-t-v-w. Therefore, Moore Contractors should be diligent about keeping the schedule by ensuring the availablity of resources.

If it's helpful,a thumbs up,pls


Related Solutions

Assume that your company sells portable housing to both general contractors and the government. It sells...
Assume that your company sells portable housing to both general contractors and the government. It sells jobs to contractors on a bid basis. A contractor asks for three bids from different manufacturers. The combination of low bid and high quality wins the job. However, jobs sold to the government are bid on a cost-plus basis. This means the price is determined by adding all costs plus a profit based on cost at a specified percent, such as 10%. You observe...
D5 Assume that your company sells portable housing to both general contractors and the government. It...
D5 Assume that your company sells portable housing to both general contractors and the government. It sells jobs to contractors on a bid basis. A contractor asks for three bids from different manufacturers. The combination of low bid and high quality wins the job. However, jobs sold to the government are bid on a cost-plus basis. This means the price is determined by adding all costs plus a profit based on cost at a specified percent, such as 10%. You...
On 01 May 2015, the management of Netcare concluded a contract with Build-IT Building Contractors, in...
On 01 May 2015, the management of Netcare concluded a contract with Build-IT Building Contractors, in terms of which the construction company undertook to build one Medical Suite Block, consisting of 50 suites of 3 rooms, a waiting room, Doctors consulting room, reception area and kitchenette. The contract stipulated that the building would be completed by 15 December 2015. The contracting parties also agreed to the following: a) If the hostels are not completed by 15 December 2015, Build-IT Building...
You are currently negotiating a book publishing deal on behalf of your client, K.J. Howling, a...
You are currently negotiating a book publishing deal on behalf of your client, K.J. Howling, a writer of moderate repute who specializes in horror stories. Your client is basically happy with the standard form contract offered by the publisher, Scattered House Press (SHP). There is, however, an important exception. Howling would like to have a clause removed from the contract under which SHP would have automatic rights to publish any sequel, on the same royalty terms as the contract now...
Yolanda and Mack are negotiating a contract deal for sale of goods. Yolanda offers Mack $2...
Yolanda and Mack are negotiating a contract deal for sale of goods. Yolanda offers Mack $2 per pound for Mack’s peanuts. Mack wants to sell them for $2.50. Under UCC, what happens when Mack asks for the higher amount, assuming both parties are merchants?
XYZ Manufacturing is negotiating an international deal with Car Parts of Belgium Inc. to provide car...
XYZ Manufacturing is negotiating an international deal with Car Parts of Belgium Inc. to provide car parts to them. The parts will be shipped from Canada to Belgium via freightliner ship. What items to they need to include in their contract? What concerns will each of the party’s have?
An owner of a Downtown Covina office building (“Lessor”) is currently negotiating a six-year lease with...
An owner of a Downtown Covina office building (“Lessor”) is currently negotiating a six-year lease with Chernobai Corporation (“Lessee”) for 20,000 rentable square feet of space. Chernobai Corporation’s offer: Chernobai Corporation would like a base rent of $24 per square foot per year with step-ups of $2 per square foot per year beginning the second year. Downtown Covina Office Building owner would provide full service under the lease terms. Downtown Covina office building’s owner’s counter-offer: The owner of Downtown Covina...
1. McDonnell-Douglas Corp. has struck a deal with a company in China to build aircraft there....
1. McDonnell-Douglas Corp. has struck a deal with a company in China to build aircraft there. What kinds of strategies should be employed by this or other firms doing business internationally? What are the benefits and problems associated with international business?
Mary developed the following payoff table based on the plan to build housing units. Mary has...
Mary developed the following payoff table based on the plan to build housing units. Mary has 3 decision alternatives to build 30 units, 50 units, and 60 units. The probabilities of strong, fair, and poor housing market are provided. Housing Units  Good Market Fair Market  Poor Market 30, d1 $50,000 . $20,000 $10,000 50, d2 80,000 30,000 -10,000 60, d3 150,000 35000 -30,000 Probability .5 .3 .2 Question # 1: If Mary wanted to make a decision based on the expected value...
Suppose that you are offered the following "deal." You roll a six sided die. If you...
Suppose that you are offered the following "deal." You roll a six sided die. If you roll a 6, you win $15. If you roll a 3, 4 or 5, you win $1. Otherwise, you pay $4. a. Complete the PDF Table. List the X values, where X is the profit, from smallest to largest. Round to 4 decimal places where appropriate. Probability Distribution Table X P(X) b. Find the expected profit. $ ____ (Round to the nearest cent) c....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT