Question

In: Finance

Tampa Company is analyzing a proposed 3-year project using standard sensitivity analysis. The company expects to...

Tampa Company is analyzing a proposed 3-year project using standard sensitivity analysis. The company expects to sell 14,000 units, ±4 percent. The expected variable cost per unit is $10 and the expected fixed costs are $45,000. The fixed and variable cost estimates are considered accurate within a ±5 percent range. The sales price is estimated at $16 a unit, ±5 percent. The project requires an initial investment of $120,000 for equipment that will be depreciated using the straight-line method to zero over the project's life. The equipment can be sold for $42,000 at the end of the project. The project requires $15,600 in net working capital for the three years. The discount rate is 10 percent and tax rate is 34 percent. What is the operating cash flow under the optimistic case scenario?

A $62,346.72

B $55,535.08

C $66,194.76

D $58,576.42

E $72,545.80

Solutions

Expert Solution

Formula sheet

A B C D E F G H
2
3 Under optimistic scenario, revenue shold be higher side and cost should be lower side i.e.
4 Expected Sales =14000*1.04
5 Expected Variable cost =10*0.95
6 Expected Fixed cost =45000*0.95
7 Sales Price =16*1.05
8 Tax rate 0.34
9 Initial investment 120000
10 Salvage Value 0
11 Expected Life 3 years
12
13 Depreciation per year =(Initial investment - Salvage Value) / Expected Life
14 =(D9-D10)/D11
15
16 Operating cashflow can be calculated as follows:
17 Operating cashflow = EBIT*(1-Tax Rate)+Depreciation
18
19 Year 0 1 2 3
20 Revenue =$D$4*$D$7 =$D$4*$D$7 =$D$4*$D$7
21 Variable Cost =$D$4*$D$5 =$D$4*$D$5 =$D$4*$D$5
22 Fixed cost =$D$6 =$D$6 =$D$6
23 Depreciation =$D$14 =$D$14 =$D$14
24 EBIT =E20-SUM(E21:E23) =F20-SUM(F21:F23) =G20-SUM(G21:G23)
25 Tax Expense =E24*$D$8 =F24*$D$8 =G24*$D$8
26 EBIT*(1-Tax Rate) =E24-E25 =F24-F25 =G24-G25
27 Plus Depreciation =E23 =F23 =G23
28 Operating Cash Flow =E26+E27 =F26+F27 =G26+G27
29
30 Hence operating cash flow under optimistic scenario is =E28
31 Thus option (B) is correct.
32

Related Solutions

Norfolk Company is analyzing a proposed 3-year project using standard sensitivity analysis. The company expects to...
Norfolk Company is analyzing a proposed 3-year project using standard sensitivity analysis. The company expects to sell 22,000 units, ±4 percent. The expected variable cost per unit is $13.2 and the expected fixed costs are $51,000. The fixed and variable cost estimates are considered accurate within a ±5 percent range. The sales price is estimated at $16.8 a unit, ±5 percent. The project requires an initial investment of $204,000 for equipment that will be depreciated using the straight-line method to...
Lawrence is analyzing a proposed 3‐year project using standard sensitivity analysis. The company expects to sell...
Lawrence is analyzing a proposed 3‐year project using standard sensitivity analysis. The company expects to sell 18,000 units, ±4 percent. The expected variable cost per unit is $12 and the expected fixed costs are $60,000. The fixed and variable cost estimates are considered accurate within a ±5 percent range. The sales price is estimated at $17 a unit, ±5 percent. The project requires an initial investment of $162,000 for equipment that will be depreciated using the straight‐line method to zero...
Insight Enterprise is analyzing a proposed 3-year project using standard sensitivity analysis. The company expects to...
Insight Enterprise is analyzing a proposed 3-year project using standard sensitivity analysis. The company expects to sell 17,000 units, ±4 percent. The expected variable cost per unit is $12 and the expected fixed costs are $60,000. The fixed and variable cost estimates are considered accurate within a ±5 percent range. The sales price is estimated at $17 a unit, ±5 percent. The project requires an initial investment of $162,000 for equipment that will be depreciated using the straight-line method to...
Maytag Company is analyzing a proposed 5-year project using standard sensitivity analysis. The company expects to...
Maytag Company is analyzing a proposed 5-year project using standard sensitivity analysis. The company expects to sell 18,000 units, ±5 percent. The expected variable cost per unit is $10.50 and the expected fixed costs are $28,000. The fixed and variable cost estimates are considered accurate within a ±5 percent range. The sales price is estimated at $16.70 a unit, ±5 percent. The project requires an initial investment of $198,000 for equipment that will be depreciated using the straight-line method to...
Broadwing Corporation is analyzing a proposed 5-year project using standard sensitivity analysis. The company expects to...
Broadwing Corporation is analyzing a proposed 5-year project using standard sensitivity analysis. The company expects to sell 30,000 units, ±5 percent. The expected variable cost per unit is $22.40 and the expected fixed costs are $180,000. The fixed and variable cost estimates are considered accurate within a ±5 percent range. The sales price is estimated at $42.00 a unit, ±5 percent. The project requires an initial investment of $350,000 for equipment that will be depreciated using the straight-line method to...
LongHorn Corp is analyzing a proposed project. The company expects to sell 10,000 units, plus or...
LongHorn Corp is analyzing a proposed project. The company expects to sell 10,000 units, plus or minus 4 percent. The expected variable cost per unit is $10 and the expected fixed costs are $400,000. The fixed and variable cost estimates are considered accurate within a plus or minus 10 percent range. The depreciation expense is $61,000. The tax rate is 32 percent. The sales price is estimated at $70 a unit. What is the operating cash flow under the best...
You are analyzing two proposed capital investments with the following cash flows: Year Project X Project...
You are analyzing two proposed capital investments with the following cash flows: Year Project X Project Y 0 - $20,000 - $20,000 1 13,730 6,470 2 6,060 6,470 3 6,460 6,470 4 2,120 6,470 The cost of capital for both projects is 10 percent. Calculate the profitability index (PI) for each project. (Do not round discount factors. Round intermediate calculations to 2 decimal places, e.g. 15.25 and final answer to 4 decimal places, e.g. 1.2527.) The PI for project X...
You are analyzing two proposed capital investments with the following cash flows: Year Project X Project...
You are analyzing two proposed capital investments with the following cash flows: Year Project X Project Y 0 - $20,000 - $20,000 1 13,530 6,370 2 5,960 6,370 3 6,460 6,370 4 1,920 6,370 The cost of capital for both projects is 10 percent. Calculate the profitability index (PI) for each project. (Do not round discount factors. Round intermediate calculations to 2 decimal places, e.g. 15.25 and final answer to 4 decimal places, e.g. 1.2527.) The PI for project X...
You are analyzing two proposed capital investments with the following cash flows: Year Project X Project...
You are analyzing two proposed capital investments with the following cash flows: Year Project X Project Y 0 - $20,000 - $20,000 1 12,530 6,570 2 6,360 6,570 3 6,160 6,570 4 2,020 6,570 The cost of capital for both projects is 10 percent. Calculate the profitability index (PI) for each project. (Do not round discount factors. Round intermediate calculations to 2 decimal places, e.g. 15.25 and final answer to 4 decimal places, e.g. 1.2527.) The PI for project X...
You are analyzing two proposed capital investments with the following cash flows: Year Project X Project...
You are analyzing two proposed capital investments with the following cash flows: Year Project X Project Y 0 -$20,000 -$20,000 1 13,630 7,720 2 5,860 7,720 3 6,160 7,720 4   2,020 7,720 The cost of capital for both projects is 10 percent. Calculate the profitability index (PI) for each project. (Do not round discount factors. Round intermediate calculations to 2 decimal places, e.g. 15.25 and final answer to 4 decimal places, e.g. 1.2527.) 1) What is the PI for project...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT